LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S. P. MANOHAR REDDY & BROS. versus MAHARASHTRA KRISHNA VALLEY DEV. CORPN. & ORS.

Citation: [2008] 17 S.C.R. 1217 · Decided: 18-12-2008 · Supreme Court of India · Bench: S.B. SINHA · Disposal: Dismissed

Cited by 3 judgment(s) · cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2008] 17 S.C.R. 1217 
M/S. P. MANOHAR REDDY & BROS. 
v. 
MAHARASHTRA KRISHNA VALLEY DEV. CORPN. & 
ORS. 
(Civil Appeal No. 7408-7409 of 2008) 
DECEMBER 18, 2008 
[S.8. SINHA AND CYRIAC JOSEPH, JJ.] 
Arbitration Act, 1940- ss. 8, 20 and 37(4)-Appointment 
A 
B 
of arbitrator - Works contract - Claim for additional and extra C 
work - Rejection of claim as also appointment of arbitrator by 
Government - Trial court appointed arbitrator but High Court 
set aside the same - Correctness of - Held: Trial court not 
correct in directing appointment of arbitrator - Arbitration 
clause could not be invoked having regard to the limited 
application of clauses 37, 54, 55 of General Conditions of D 
Contract - Contractor did not raise claim for extra or additional 
work during the tenure of contract but after its completion and 
acceptance of final bill - He accepted the final bill without any 
demur - Contract came to an end and arbitration agreement 
which was part of it also perished - Jurisdiction of civil court 
E' 
could be invoked if disputes arising between parties was one 
to which arbitration agreement applied - More so, contractor 
did not seek extension of time uls. 37(4) and in any event no 
sufficient cause was made out. 
Respondent-government and the appellant-
F 
contractor entered into a work contract. The General 
"' 
Conditions of Contract were specified. Clause 37 
imposed an obligation upon the contractor to furnish to 
j:xecutive Engineer a release of claims against 
Government arising out of the contract other than the 
claims_ specified, after completion of the work and prior G 
t-o payment thereof. The work was completed. 
Respondent paid the final bill prepared and the appellant 
accepted the same without any protest. As the appellant 
was asked to do extra items of work, it raised the claim 
1217 
H 
.··,, .. · 
1218 
SUPREME COURT REPORTS 
[2008] 17 S.C.R. 
"A for the same but was rejected.Appellantissued notice·to 
the Executive Engineer of respondent Corporation. 
Respondent rejected the claim on the ground that the 
. stipulated period therefor expired and as such the matter 
could not be considered for arbitration. Aggrieved, 
s appellant filed -appeal thereagainst before the 
Superintending Engineer for arbitration but the same was 
rejected as the contractor did not submit their claim 
before expiry of 30 days after the defect liability period 
nor the arbitrator was appointed.Thereafter, Chief 
Engineer was issued notice for appointment of sole 
C arbitrator but was rejected. Appellant filed appHcation u/ 
s. 8 of the Arbitration Act, 1940 for appointment of . 
·Arbitrator. Civil Judge appointed a retired Chief Engineer 
· ·as Arbitrator with regard to the additional and extra works 
carried out by appellant. Respondent filed Revision 
D ··Application which was a.llowed. Review Petition 
thereagainst was.· also dismissed. Hence the present 
appeals. 
Dismissing the appeals, the Court 
HELD:1.1. As arbitration clause could not be invoked 
E having regard to the limited application of clauses 37, 54 
and 55 of the General Conditions of the Contract, the trial 
court was not correct in directing appointment of 
arbitrator. [Para 28] [1237-F] 
1.2. The arbitration agreement is contained in a 
F commercial document. It must be interpreted having 
regard to the language used in it. A bare perusal of 
clauses 37, 54 and 55 of the General Conditions of 
Contract clearly shows that the arbitration agreement 
entered into by and between the parties is not of wide 
G amplitude. In a case where arbitration clause is of wide 
.amplitude, the same may cover also the claims arising 
during the tenure of contract or thereafter, provided the 
arbitration clause subsists. Clause 37 imposes an 
obligation upon the contractor to furnish to the Executive 
H Engineer a release of claims against the Government 
->. 
P. MANOHAR REDDY & BROS. v. MAHARASHTRA 1219 
KRISHNA VALLEY DEV. CORPN. & ORS. 
arising out of the contract other than the claims A 
specifically identified, evaluated and expected from the 
operation of the release by the Contractor only after 
completion of the work and prior to payment thereof. 
[Paras 15 and 16] [1230-D-F] 
1.3. There is nothing on record to show that any claim B 
in relation to extra or additional work had been raised by 
the contractor prior to 27.2.1991 although final 
measurement had been recorded on 26.11.1990 and the 
bill was paid in full and final satisfaction on 4.12.1990. 

Excerpt shown. Read the full judgment & AI analysis in Lexace.