LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S. P. DASARATHARAMA REDDY COMPLEX versus GOVERNMENT OF KARNATAKA AND ANOTHER

Citation: [2013] 14 S.C.R. 579 · Decided: 25-10-2013 · Supreme Court of India · Bench: G.S. SINGHVI · Disposal: Disposed off

Cited by 1 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2013] 14 S.C.R. 579 
M/S. P. DASARATHARAMA REDDY COMPLEX 
v. 
GOVERNMENT OF KARNATAKA AND ANOTHER 
(Civil Appeal No. 1586 of 2004) 
OCTOBER 25, 2013 
[G.S. SINGHVI, V. GOPALA GOWDA AND 
C. NAGAPPAN, JJ.) 
Contract - Works contract - Disputes pertaining thereto 
A 
B 
- Clause in the contract - Analysis of- If it could be construed C 
as an arbitration clause -
Distinction between expert 
determination and arbitration - Held: On facts, in terms of the 
relevant clauses in the agreements entered into between· the 
parties, any dispute or difference between the parties was 
required to be first referred to the Chief Engineer or the 
D 
Designated Officer of the Department - The Chief Engineer 
or the Designated Officer was not an independent authority 
or person, but was in fact having over all supervision and 
charge of the execution of the work - Decision of the Chief 
Engineer was non-adjudicatory subject to the right of the 
E 
aggrieved party to seek remedy - Thus, relevant clauses in 
the agreements entered into between parties provided for 
settlement of disputes through Court and could not be relied 
upon for seeking reference to an arbitrator of any dispute 
arising under the· contract - Arbitration and Conciliation Act, 
1996 - ss. 11 (6) and (8). 
F 
Contracts were awarded by the Government of · 
Karnataka and/or its agencies/instrumentalities for 
execution of particular projecUworks. Disputes arose 
between the parties out of the said contracts. 
G 
In the instant appeals the issue for consideration 
before this Court was whether the relevant clauses in the 
contracts entered into between the parties (Clause 29 in 
579 
H 
580 
SUPREME COURT REPORTS 
(2013] 14 S.C.R. 
A one of the contract and similar clauses in other contracts) 
ought to be treated as an arbitration clause providing for 
resolution of the disputes by arbitration or were in the 
nature of departmental dispute resolution mechanism. 
B 
Disposing the appeals, the Court 
HELD: There is distinction between an expert 
determination and arbitration. In terms of Clause 29 of the 
Agreement entered into between the parties (the 
appellant and the respondents in Civil Appeal No.1586/ 
C 2004) and similar other clauses, any dispute or difference 
irrespective of its nomenclature in matters relating to 
specifications, 
designs, 
drawings, 
quality 
of 
workmanship or material used or any question relating 
to claim, right in any way arising out of or relating to the 
D contract designs, drawings etc. or failure on the 
contractor's part to execute the work, whether arising 
during the progress of the work or after its completion, 
termination or abandonment has to be first referred to the 
Chief Engineer or the Designated Officer of the 
E Department. The Chief Engineer or the Designated Officer 
is not an independent authority or person, who has no 
connection or control over the work. As a matter of fact, 
he is having over all supervision and charge of the 
execution of the work. He is not required to hear the 
F 
parties or to take evidence, oral or documentary. He is not 
invested with the power to adjudicate upon the rights of 
the parties to the dispute or difference and his decision 
is subject to the right of the aggrieved party to seek relief 
in a Court of Law. The decision of the Chief Engineer or 
G the Designated Officer is treated as binding on the 
contractor subject to his right to avail remedy before an 
appropriate Court. The use of the expression 'in the first 
place' unmistakably shows that non-adjudicatory 
decision of the Chief Engineer is subject to the right of 
H 
P. DASARATHARAMA REDDY COMPLEX v. 
581 
GOVERNMENT OF KARNATAKA 
the aggrieved party to seek remedy. Therefore, Clause 
A 
29 which is subject matter of consideration in most of the 
appeals and similar clauses cannot be treated as an 
Arbitration Clause. Liberty is given to the aggrieved party 
to avail appropriate legal remedy, if any. (Paras 15, 21 and 
29) [595-E; 608-D-H; 609-A-B; 620-B] 
B 
Mysore Construction Company v. Karnataka Power 
Corporation Ltd. ILR 2000 KAR 4953 - affirmed. 
Smt. Rukmanibai Gupta ~- Collector, Jabalpur and others 
(1980) 4 SCC 556; Punjab State and others v. Dina Nath 
C 
(2007) 5 SCC 28: 2007 (6) SCR 536; Mal/ikarjun v. Gulbarga 
University case (2004) 1 SCC 372: 2003 (5) Suppl. SCR 
272; Krishna Bhagya Jala Nigam Limited v. 
G. 
Harishchandra Reddy and another (2007) 2 sec 720: 2007 
(1) SCR 698 and Karnataka State Road Transport

Excerpt shown. Read the full judgment & AI analysis in Lexace.