LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

M/S. MSK PROJECTS (I) (JV) LTD versus STATE OF RAJASTHAN & ANR.

Citation: [2011] 9 S.C.R. 402 · Decided: 21-07-2011 · Supreme Court of India · Bench: P. SATHASIVAM · Disposal: Disposed off

Cited by 4 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2011] 9 S.C.R. 402 
A 
MIS. MSK PROJECTS (I) (JV) LTD 
~ 
v. 
STATE OF RAJASTHAN & ANR. 
(Civil Appeal No. 5416 of 2011) 
B 
JULY 21, 2011 
I 
' 
[P. SATHASIVAM AND DR. B.S. CHAUHAN, JJ.] 
Contract: 
c 
Construction of a bypass road - Concession agreement 
authorising contractor to collect toll fee - Dispute between 
parties as to delay in issuance of notification by State 
Government barring the use of old route as also entitlement 
of contactor to collect toll fee from vehicles using a specific 
D patch of the road - Arbitral tribunal holding that there had 
.. 
been delay on the part of the State in issuing the notification 
and the State failed to implement the same and the contractor 
was entitled to collect fee even from vehicles using the 
specific patch of the road - District Judge and High Court 
E holding that there was no clause in the agreement to issue 
notification barring the old route - However, the High Court 
held that the contractor could collect toll fee from the specific 
patch of the road - HELD: The State Government had not 
taken the defence that it was not agreed between the parties 
F 
to issue the notification barring the traffic through the old route 
- The only issue remained as to whether there was delay in 
issuance of notification and implementation thereof - In such 
a fact-situation, the District Judge as well as the High Court 
fell in error in considering the issue which was not taken by 
G 
the State before the arbitral tribunal during the arbitration 
proceedings and holding that there was no agreement for 
issuance of notification by State barring the old route - The 
issue as to whether the specific patch of the road was an 
integral or composite part of the project and the contractor 
could collect the toll fee on that part also stands concluded 
H 
402 
MSK PROJECTS (I) (JV) LTD v. STATE OF 
403 
RAJASTHAN & ANR. 
~ยท 
by the High Court and stands settled in favour of the contractor A 
- Rajasthan Motor Vehicles Taxation (Amendment) Act, 
1994 - Tolls Act, 1851. 
Tolls Act, 1851: 
'; โ€ข 
8 
Toll fee - Nature of - Construction of a bypass road -
Concession agreement authorising the contractor to collect 
toll fee - Dispute between parties - Arbitration - HELD: Toll 
fee is compensatory in nature wherein the Government can 
reimburse itself the amount which it had spent on construction 
of road/bridge etc. - State is competent to levy/collect the toll c 
fee only for the period stipulated under the Statute or till the 
actual cost of the project with interest etc. is recovered - It 
cannot be a source of revenue for the State - A person is 
... 
debarred by law and statutory inhibition, as contained in 
Clause IV(a) of the notification, from collection of toll beyond D 
the recovery of cost of construction - In the instant case, the 
work was to be executed in two phases - The first phase was 
completed and the amount spent by contractor on the said 
work was recovered with certain profit - The work of second 
phase was never executed - Therefore, contractor cannot be E 
permitted to claim damages/compensation on this count -
The arbitrator cannot proceed beyond the terms of reference 
and, therefore, the question of considering the non-execution 
of the work of second phase was neither permissible nor 
possible as it had arisen subsequent to the date of aw_ard. in 
F 
the arbitration proceedings - In order to do complete Justice 
between the parties and protect the public exchequer, matter 
remitted to arbitral tribunal to work out the entitlement of the 
contractor - Arbitration and Conciliation Act, 1996 - Code of 
, !., 
Civil Procedure, 1908 - 0.8, r.5. 
G 
Arbitration: 
Jurisdiction of arbitratorlarbitral tribunal - HELD: Special 
tribunals like arbitral tribunals and Labour Courts get 
jurisdiction to proceed with the case only from the reference H 
404 
SUPREME COURT REPORTS 
[2011] 9 S.C.R. 
A 
made to them - Thus, an arbitrator cannot be allowed to 
~ 
B 
assume jurisdiction over a question which has not been 
referred to him. Similarly, he cannot widen his jurisdiction by 
holding contrary to the fact that the matter which he wants to 
decide is within the submission of the parties in the case. 
Interest - HELD: While award of interest for the period 
prior to an arbitrator entering upon the reference is a matter 
of substantive law, the grant of interest for the post-award 
period is a matter of procedure - Therefore, the arbitrator is 
competent to award interest fo

Excerpt shown. Read the full judgment & AI analysis in Lexace.