M/S MITRA GUHA BUILDERS (INDIA) COMPANY versus OIL AND NATURAL GAS CORPORATION LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 368 SUPREME COURT REPORTS [2019] 14 S.C.R. M/S. MITRA GUHA BUILDERS (INDIA) COMPANY v. OIL AND NATURAL GAS CORPORATION LIMITED (Civil Appeal No. 5511 of 2012) NOVEMBER 08, 2019 [R. BANUMATHI, A. S. BOPANNA AND HRISHIKESH ROY, JJ.] Arbitration : Contract for building construction β Dispute β Arbitrator appointed β Arbitrator allowed the claims of the contractor/ claimants, while rejected the counter-claim for liquidated damages/ compensation β Single Judge of High Court upheld the Award β Division Bench of High Court set aside the Award holding that question of levy of liquidated damages was not arbitrable β Appeal to Supreme Court β Held : The relevant clause of the contract shows that the parties had agreed that levy of liquidated damages by the Superintending Engineer of the respondent-Company was final β Therefore the issue was not arbitrable being an βexcepted matterβ β Division Bench of High Court rightly set aside the Award. Contract : Interpretation of contractual clause β Held : The entire contract between the parties and the terms thereon have to be read as a whole to decide the rights and liabilities of the parties, arising out of the contract. Dismissing the appeals, the Court HELD : 1. Upholding the award of the Arbitrator, the Single Judge of High Court held that the delay in completion of the work was on account of both parties and by applying the equitable principles, the Single Judge held that the damages were payable by either of the parties. The Single Judge failed to note the implication of Clause 2 of the contract and also various correspondences between the parties, while affirming the award passed by the Arbitrator. In terms of Clause 2 of the agreement dated 05.02.1996 between the parties, the contractor is to proceed [2019] 14 S.C.R. 368 368 A B C D E F G H 369 with the work with due diligence throughout the contract period. By the terms of the agreement, the parties have consciously agreed that in case the contractor fails to comply with the conditions and complete the work with due diligence, the Superintending Engineer may decide the compensation in terms of Clause 2 of the agreement. [Para 13 and 14][378-C-D] 2. A reading of Clause 2 of the Contract makes it clear that the Superintending Engineer has been conferred with not only a right to levy compensation, but it also provides a mechanism for determination of the liability/quantum of compensation. The very Clause 2 would show that such a decision taken by the Superintending Engineer shall be final. The finality clause in the contract in terms of Clause 2 makes the intention of the parties very clear that there cannot be any further dispute on the said issue between the parties; much less before the arbitrator. The intention of the parties to exclude some of the decisions of the Superintending Engineer from the purview of arbitration is clearly seen from clause 25 of the Contract. The very prayer to declare the amount levied by the Superintending Engineer as illegal is against the tenor of the terms of the contract (Clause 2) between the parties. By virtue of the finality clause in the contract, any decision taken by the Superintending Engineer in levying compensation cannot be referred to an arbitrator. The parties have consciously agreed to have finality to the decision of the Superintending Engineer and the same cannot be frustrated by challenging the same as illegal. Any other meaning to the finality clause in the contract and allowing further adjudication by another authority would make the agreed Clause 2 and Clause 25 of the agreement meaningless and redundant. [Paras 15 and 16][379- E-F; 381-A-C] 3. According to the respondent, the completion time was extended without prejudice to its right to recover compensation in accordance with Clause 2 of the agreement. The contention of the respondent is that by the letter dated 15.05.2001, the contractor was put on notice that in exercise of the power conferred on the Superintending Engineer under Clause 2, the contractor is liable to pay 10% of the contract value by way of compensation. The contractor was informed by the said letter dated 15.05.2001 M/S. MITRA GUHA BUILDERS (INDIA) COMPANY v. OIL AND NATURAL GAS CORPORATION LTD. A B C D E F G H 370 SUPREME COURT REPORTS [2019] 14 S.C.R. that the compensation is levied on him for the period of 39 weeks at half per cent per week subject to maximum of 10% of the contract value and that the actual amount of compensation s
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex