M/S. M.K. SHAH ENGINEERS AND CONTRACTORS versus STATE OF MADHYA PRADESH
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
# , MIS. M.K. SHAH ENGINEERS AND CONTRACTORS A ___.. "f v. STATE OF MADHYA PRADESH FEBRUARY 5, 1999 [SUJATA V. MANOHAR AND R.C. LAHOTI, JJ.] B .. Ji" Arbitration Act 1940 : Section 33-Arbitration clause in agreement prescribing decision by Superintending Engineer on dispute between parties as condition prece- c dent-Dispute arising between the parties-Reference of dispute to ar- bitrato,..-f'reliminary objection by one party regarding maintainability of arbitration proceedings as condition precedent for invoking arbitration clause not satisfied-Party raising preliminary objection responsible for fmstration of condition precedent prescribed in arbitration clause-Held, preliminary objec- tion not maintainable as no one can be pennitted to take advantage of one's D own wrong and it shall be deemed that the condition precedent was waived by the party at fault by its conduct. Sections 16, Jo-Non-speaking award-Objections filed-Held, it is not necessary that award should be a speaking award. E Interest Act, 183~S.13-Award of Interest-Pre-reference period- Held, interest cannot be awarded in the absence of statute, contract, usage or custom-Post-reference period-Held, arbitrator can award interest pendente lite-Such award of interest pendente lite can be upheld in proceedings pending on 12.12.1991. F f ... The appellants in the two appeals were the contractors entrusted by the respondent-State with the construction of blocks in the Barna Main Dam across River Barna, a tributary of Narmada near Bhopal. The contract between the parties contained an arbitration clause which provided that all disputes were required to be referred for the decision of G ... the Superintending Engineer of the Circle whose decision was agreed by "' the parties to be treated as final and if any party was aggrieved by such final decision, then it could demand a reference of disputes to arbitrator. The appellants could not complete the work assigned to them and disputes arose between them and the respondent-State. The contracts were ter- H 419 420 SUPREME COURT REPORTS (1999] 1 S.C.R. A . minated in between and the respondent-State ge>t the remaining parts of the work executed through other agencies. Both the contractors raised disputes before the Superintending Engineer. In the first appeal, the Superintending Engineer kept the disputes B pending for a. long tiJiie and referred all the disputes raised by the appellant-contractor to a sub-committee consisting of highly placed offi- cials of the State Government. The contractor addressed a communication to the Chief Secretary and other concerned authorities lodging a strong protest against the action of the Superintending Engineer for having c delegated his function to the sub-committee and demanded the appoint- ment of an arbitrator as per the arbitration clause for referring the disputes raised by the appellant for his decision as the Superintending Engineer had rendered himself incapable of taking decision under the contract. A list of disputes raised by the appellant was annexed with the D letter. The State Government yielded to the demand of the appellant and appointed a sole arbitrator for deciding the dispute between the parties. The arbitrator entered upon the reference. The respondent-State appeared before the arbitrator but raised a preliminary objection to the legality of the arbitration on the ground that it was not in accordance with the arbitration clause and the claims put forth by the appellant were not E arbitrable in as much as they were not preceded by a decision of the Superintending Engineer in accordance with the arbitration clause. The respondent-State filed an application under S. 33 of the Arbitra- F tion Act before the Additional District Judge, Bhopal seeking an adjudica- ti on on the preliminary objection raised by them before the arbitrator. During the pendency of the application, the arbitrator expired. The resp on- dent-State got the petition under S. 33 of the Act dismissed as having been rendered infructuous. The appellant served a notice on the respondent for filling up the vacancy in the office of arbitrator. When the respondent G failed to comply with the notice, the appellant filed a petition under S. 8(2) of the Act before the Additional District Judge, Bhopat The Court allowed the petition and appointed an arbitrator for deciding the disputes referred to the previous arbitrator. The arbitra
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex