LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S. LARSEN & TOUBRO LTD. versus M/S. MOHAN LAL HARBANS LAL BHAYANA

Citation: [2014] 3 S.C.R. 162 · Decided: 25-02-2014 · Supreme Court of India · Bench: S.S. NIJJAR · Disposal: Appeal(s) allowed

Cited by 2 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
[2014] 3 S.C.R. 162 
MIS. LARSEN & TOUBRO LTD. 
v. 
M/S. MOHAN LAL HARBANS LAL BHAYANA 
(Civil Appeal No. 7586 of 2009) 
FEBRUARY 25, 2014 
[SURINDER SINGH NIJJAR AND A.K. SIKRI, JJ.] 
ARBITRATION AND CONG/LIA T/ON ACT, 1996: 
c 
s. 11 (6) - Application before High Court for appointment 
of arbitrator - Agreement between employer SCOPE and 
appellant contractor - Clause 25 of agreement bearing 
arbitration clause - Appellant engaging respondent sub-
contractor - Application by respondent for appointment of 
0 arbitrator - Allowed by High Court - Held: SCOPE being 
Principal/Employer of appellant, the liability for honouring the 
claim of respondent was that of SCOPE and appellant was 
not supposed to make any payment from its coffers - Further, 
by virtue of first supplementary agreement, the modalities of 
E settling the dispute between parties underwent a significant 
change - It was unambiguously provided that in view of 
arbitration between appellant and SCOPE, pertaining to 
claims of respondent as well, even if the disputes between the 
appellant and the respondent were deemed to have been 
settled and were not referable to arbitration again between 
F these two parties Order of High Court is set aside - In view of 
subsequent developments after the decision of the High 
Court, when the final bill is almost at the stage of finalization, 
the only aspect that can be taken care of at this stage is to 
hasten the process of arbitration, in case after the passing of 
G the final bill by SCOPE, some claims of respondent still 
survive -- Directions issued accordingly to balance the 
equities. 
In the instant appeal, the appellant challenged the 
H 
162 
M/S. LARSEN & TOUBRO LTD. v. M/S. MOHAN LAL 163 
HARBANS LAL BHAYANA 
order of the High Court passed on an application A 
preferred by the respondent u/s 11 (6) of the Arbitration 
and Conciliation Act, 1996 appointing an arbitrator on 
behalf of the appellant on the ground that in spite of 
notice by the respondent in this behalf, the appellant had 
failed to nominate its arbitrator in terms of Clause 25 of B 
the agreement entered into between the parties. Since the 
respondent had already nominated its arbitrator, further 
direction was given that the two arbitrators (one 
nominated by the respondent and one appointed by the 
High Court for the appellant), would appoint an Umpire c 
in consonance with the said Clause 25. The stand of the 
appellant was that Clause 25 was modified by three , 
supplementary agreements and resultantly there was no 
question of arbitration between the appellant and the 
respondent in view of the modifications. The appellant 0 
claimed that by agreement dated 29.2.1988 entered into 
between the Standing Conference of Public Enterprises 
(SCOPE) and the appellant, SCOPE awarded certain 
construction works to the appellant. This agreement also 
permitted the appellant to sub-contract. Accordingly, the 
E 
appellant entered into an agreement dated 3.3.1988 with 
the respondent. Clause 2 of this agreement dated 
3.3.1988 pertained to the payments which were to be 
made by the appellant to the respondent and the amount 
under this sub contract was payable to the respondent 
by the appellant only on receipt of corresponding 
F 
receipts from SCOPE. Further, as per Clause 6, the 
respondent was to perform the work awarded to it to the . 
satisfaction of SCOPE. It was further the case of the 
appellant that the appellant and the respondent entered 
into a supplementary agreement dated 31.1.1990 and the 
G 
modalities of settling the disputes between the parties 
through arbitrator also underwent a significant change, 
as was clear from Clause (viii) of the first supplementary 
agreement. 
H 
164 
SUPREME COURT REPORTS 
[2014] 3 S.C.R. 
A 
Allowing the appeal, the Court 
HELD: 1.1 In essence, the parties understood that as 
the Principal/Employer was SCOPE, for whom the work 
was to be performed by virtue of main agreement dated 
8 29.2.1988 entered into between the parties, and the sub 
contract between the appellant and respondent was on 
back to back basis, any work done by the respondent 
was for the benefit of SCOPE and, ultimately, liability for 
honoring the claims of the respondents was that of 
SCOPE and the appellant was not supposed to make any 
C payment from its coffers. The parties even acted on the 
basis of said understanding initially. [para 5-6] [169-F-G] 
1.2 Clause (viii) of the first supplementary agreement 
acknowled

Excerpt shown. Read the full judgment & AI analysis in Lexace.