LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S GAYATRI PROJECT LIMITED versus MADHYA PRADESH ROAD DEVELOPMENT CORPORATION LIMITED

Citation: [2025] 5 S.C.R. 2534 · Decided: 15-05-2025 · Supreme Court of India · Bench: J.B. PARDIWALA · Disposal: Disposed off

cites 7 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 5 S.C.R. 2534 : 2025 INSC 698
M/s Gayatri Project Limited  
v.  
Madhya Pradesh Road Development Corporation Limited
(Civil Appeal No. 6856 of 2025)
15 May 2025
[J.B. Pardiwala* and R. Mahadevan, JJ.]
Issue for Consideration
1.	
Whether an arbitral award rendered under the Arbitration 
and Conciliation Act, 1996 (hereinafter “Act, 1996”), where 
the arbitration proceedings ought to have been governed 
by the M.P. Madhyastham Adhikaran Adhiniyam, 1983 
(hereinafter “MP Act, 1983”), can be set aside solely on the 
ground of lack of jurisdiction, even when no such plea was 
raised before the arbitral tribunal in terms of Section 16(2) 
of the Act, 1996?
2.	
Whether the decision of this Court in M.P. Road Development 
Authority & Anr v. L.G. Chaudhary Engineers & Contractors 
reported in (2018) 10 SCC 826 can be said to be per incuriam 
for not considering the Court’s ruling in Lion Engineering? 
In other words, is there a conflict between the decisions in 
Lion Engineering and L.G. Chaudhary (II), particularly on 
when a plea of lack of jurisdiction may be raised under the 
Act, 1996?
Headnotes†
Arbitration and Conciliation Act, 1996 – M.P Madhyastham 
Adhikaran Adhiniyam, 1983 – Arbitral award cannot be set 
aside solely on the ground of jurisdiction if no objection was 
raised under Section 16(2) of the Arbitration and Conciliation 
Act, 1996:
The appellant executed a “works contract” dated 12.12.2005 with 
the respondent for “Rehabilitation and Strengthening of Khargone-
Barwani Road (SH-26) Project Road No.19” & “Rehabilitation and 
Strengthening of Khargone-Bistan Road (SH-31) Project Road 
No.20” in the State of Madhya Pradesh – Clause 67.3 of the 
* Author
[2025] 5 S.C.R. 
2535
M/s Gayatri Project Limited v. 
Madhya Pradesh Road Development Corporation Limited
“General Conditions of Contract” read with Clause 67.4 of the 
“Conditions of Particular Application” provided for arbitration as 
the means for resolution of disputes between the Parties – The 
arbitration agreement mandated that the tribunal shall comprise 
of three members, one to be appointed by each party and the 
two coarbitrators had to nominate the presiding arbitrator – The 
disputes arose between the parties from 06.08.2010 onwards in 
relation to the appellant’s right to be reimbursed additional cost 
incurred by it on account of introduction of subsequent legislation 
on increase in entry tax on High-Speed Diesel under Clause 70.8 
of the Particular Conditions of Contract – The appellant invoked 
arbitration under Clause 67.4 vide its notice dated 06.08.2010 and 
the Tribunal stood constituted on 24.09.2010 – The Tribunal passed 
a unanimous award dated 08.07.2011 in favour of the appellant 
for a sum of Rs.1,03,55,187 (i.e. Rs.1.04 Crore) – As is evident 
from Para 1.19 of the Award quoted above, the quantification of 
this amount was in-fact recommended by the Engineer and had 
been admitted by the respondent – The Tribunal also awarded 
future interest at the rate of 10% p.a. from the date of the award 
till the date of actual payment as per para 3.1 – As of 17.02.2025, 
the amount payable by the respondent to the appellant stands at 
Rs.2,44,63,775 – The respondent challenged the award before the 
Civil Court under Section 34 of the Arbitration Act vide a petition 
filed on 30.09.2011 – The same came to be allowed holding that 
the Arbitral Tribunal did not jurisdiction in view of M.P Madhyastham 
Adhikaran Adhiniyam, 1983 – The order passed by the Commercial 
Court and 19th Additional Sessions Judge, Bhopal (M.P.) came 
to be challenged by way of appeal before the High Court under 
Section 37 of the Act, 1996 – The appeal came to be dismissed – 
Hence, the present Appeal before this Court.
Held: It was noted that the decision in M.P. Road Development 
Authority & Anr v. L.G. Chaudhary Engineers & Contractors 
(2018) 10 SCC 826 elucidated how the courts are expected to 
deal with the various issues that may arise insofar as the pending 
proceedings that were inadvertently initiated under the Arbitration 
and Conciliation Act, 1996 and any awards already passed 
thereunder are concerned – M.P. Road Development Authority v. 
L.G. Chaudhary, (2018) 10 SCC 826 was referred to wherein it was 
held that an arbitral award cannot be set aside solely on the ground 
of jurisdiction if no objection was raised under Section 16(2) of the 
2536
[2025] 5 S.C.R.
Supreme Court Reports
Arbitration and Conciliation Act, 1996 – However, other challenge

Excerpt shown. Read the full judgment & AI analysis in Lexace.