LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S GANGOTRI ENTERPRISES LTD. versus UNION OF INDIA & ORS.

Citation: [2016] 2 S.C.R. 1074 · Decided: 05-05-2016 · Supreme Court of India · Bench: JASTI CHELAMESWAR · Disposal: Appeal(s) allowed

Cited by 2 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
c 
D 
E 
F 
G 
H 
[2016] 2 S.C.R. 1074 
M/S GANGOTRI ENTERPRISES LTD. 
v. 
UNION OF INDIA & ORS. 
(Civil Appeal No. 4814 of2016) 
MAYOS,2016 
(J. CHELAMESWAR AND ABHAY MANOHAR SAPRE, JJ.] 
Arbitration and Conciliation Act, 1996 ·- s. 9 - Bank guarantee 
- Encashment - Injunction against - Award of two contracts by 
Railway Department to Contractor - Termination of the first contract 
for non-completion of work-As regards second contract, contractor 
on its completion asked for return of Bank guarantee - However. 
Railway Department sought encashment of Bank Guarantee -
Invocation of arbitration clause by Contractor - Application uls. 9 
by contractor seeking injunction against the Department from 
encashing Bank Guarantee - Dismissed by the courts below - On 
appeal, held: Arbitration proceedings in relation to the first contract 
still pending - Sum claimed from the contractor does not relate to 
the contract for which the Bank Guarantee was furnished but relates 
to another contract for which no bank guarantee was furnished -
Further. the sum claimed by the contractor neither an admitted sum 
and nor a sum which stood adjudicated by any court of law in any 
;udicial proceedings but a disputed sum - Bank Guarantee being 
in the nature of a· performance guarantee furnished for execution 
work of second contract and work having been completed to the 
satisfaction of the Department, they had no right to encash the Bank 
Guarantee - Contractor made out a prillia facie case in their favour 
for grant of injunction against the Department so also balance of 
convenience and irreparable loss - Thus, entitled to claim injunction 
against the Department in relation to encashment of Bank Guarantee 
- Order passed by the High Court set aside. 
Allowing the appeal, the Court 
HELD: 1.1 On perusal of the record of the case, it is found 
that firstly; arbitration proceedings in relation to the contract dated 
22.08.2005 are still pending. Secondly, the sum claimed by the 
respondents from the appellant does not relate to the contract 
for which the Bank Guarantee had been furnished but it relates 
1074 
M/S GANGOTRI ENTERPRISES' LTD. v. UNION OF INDIA 
to another contract dated 22.08.2005 for which no bank 'guarantee 
had been furnished. Thirdly, the sum claimed by the respondents 
from the appellant is iu the nature of da~.ages, which is not yet 
adjudicated upon. in arbitration proceedings. Fourthly, the sum 
claimed is neither a sum due in praesenti no~ a sµm payable. In 
other words,. the sum claimed by the respondents is neither an 
admitted sum and.nor a sum which stood adjudicated. by any Court 
of law in any judicial proceedings but it is a disputed sum and 
lastly, the Bank Guarantee in question· being in the nature of a 
performance guarantee furnished for execution work of contract 
dated 14.07.2006 (AV works) and the work ha_vjng b.een 
completed to th{ satisfaction of the respondents, they had iio 
right to encash the·BankGuarantee. Both the courts below erred 
in dismissing the appellant.'s application for grj\nt of_injunction. 
Both the courts' committed jurisdictional error when they failed 
to take note of the law laid down by this Court in Union of India 
(DGS&D) relating to the Bank Guarantee. [Paras 42, 43) [1086-
G-H; 1087-A-C] 
Union of India vs.· Ralnan Iron Foundry 1974 (3) SCR 
556:(1974) 2 sec 231 - relied on. 
1.2 The District Judge having decided the· injunction 
application in the first i.nstance in appellant's favour in, rejecting 
the application made by. the appellant second. time. It is ,not in 
dispute that the respondents despite having suffered the 
injunction order did not file any appeal against this order. Such 
order thus attained finality and was, therefore, binding on the 
pa_rties. [Para 44) [1087-F-G] 
1.3 The appellants have made out a prima facie case in their 
favour for grant of injunction against the respondents so also they 
have made out a case. of balance of convenience and irreparable 
loss in their favour. They are, therefore, entitled to claim 
injunction against the. respondent in relation to eucashment of 
Bank Guarantee. The impugned order is set .aside and in 
consequence the injunction application made by the appellant 
under Section 9 of the Act in Arbitration Suit is aliowed and 
injunction is granted in appellant's favour by restraining the 
respondents jointly and severally from encashing Bank Guarantee 
furnished by the appellant in connection with AV Works. [P

Excerpt shown. Read the full judgment & AI analysis in Lexace.