LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S FERRO CONCRETE CONSTRUCTION (INDIA) PVT. LTD. versus THE STATE OF RAJASTHAN

Citation: [2025] 4 S.C.R. 529 · Decided: 01-04-2025 · Supreme Court of India · Bench: PAMIDIGHANTAM SRI NARASIMHA · Disposal: Appeal(s) allowed

Cited by 1 judgment(s) · cites 12 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 4 S.C.R. 529 : 2025 INSC 429
M/s Ferro Concrete Construction (India) Pvt. Ltd. 
v. 
The State of Rajasthan
(Civil Appeal No. 4723 of 2025)
02 April 2025
[Pamidighantam Sri Narasimha* and Joymalya Bagchi, JJ.]
Issue for Consideration
Whether the contractual clause that bars the appellant/contractor 
from claiming any interest on any payment, arrears or balance due 
to it amounts to an express bar on the arbitrator’s power to grant 
pendente lite interest as per the law under the Arbitration Act, 1940.
Headnotes†
Arbitration Act, 1940 – Appellant was awarded a works 
contract by the respondent – A Clause 22 of the agreement 
barred the appellant from claiming interest on any payment 
or arrears or balance due to him – Disputes arose between 
the parties – Arbitration invoked – Arbitral award came out 
in favour of appellant – Arbitrator granted 15% pendente lite 
interest – However, the District Judge granted 9% simple 
interest on the Principal sum – Same was upheld by the High 
Court – Correctness:
Held: Both the decisions in Reliance Cellulose and the First 
Ambica case emphasise the need for an express contractual bar 
on the payment of pendente lite interest to create a bar on the 
arbitrator from awarding interest – They also emphasise that a 
bar on the arbitrator’s power would depend on the phraseology 
of the contractual clause in that case – In the instant case, the 
Clause 22 prohibits the appellant (contractor) from claiming interest 
on any payment, arrears or balance, which may be found due to 
him at any time – Applying the above-stated law, this Court finds 
that this clause does not expressly bar the award of pendente lite 
interest in the event of disputes, differences, or misunderstandings 
between the parties, or on delayed payment, or in any other respect 
whatsoever – Under the 1940 Act, this Court has not readily 
inferred a bar on the arbitrator from clauses that merely bar the 
* Author
530
[2025] 4 S.C.R.
Digital Supreme Court Reports
contractor from claiming interest, and the same will apply to this 
case as well – In view thereof, the judgment of the High Court is set 
aside – However, considering that the arbitrator entered reference 
in 1991 and the award was made in 1995, along with the passage 
of time in litigation as well as the amounts already paid by the 
respondent including post-award interest @ 9%, this Court deems 
it appropriate to grant 9% pendente lite interest, instead of 15% 
as granted by the arbitral tribunal, from 18.12.1991 till 07.03.1995 
(date of the arbitral award). [Paras 14, 15, 16]
Arbitration Act, 1940 – Arbitration and Conciliation Act, 1996 – 
Position of law on the grant of interest – Discussed.
Case Law Cited
Secretary, Irrigation Department, Government of Orissa v. G.C. 
Roy [1991] Supp. 3 SCR 417 : (1992) 1 SCC 508; Executive 
Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj 
[2001] 1 SCR 264 : (2001) 2 SCC 721 – followed.
Reliance Cellulose Products Ltd v. Oil and Natural Gas Corporation 
Limited [2018] 6 SCR 618 : (2018) 9 SCC 266; Union of 
India v. Ambica Construction [2016] 2 SCR 810 : (2016) 6 SCC  
36 – relied on.
Pam Developments Private Limited v. State of West Bengal [2024] 
8 SCR 615 : (2024) 10 SCC 715; M.B. Patel & Co. v. ONGC [2008] 
8 SCR 35 : (2008) 8 SCC 251; Union of India v. Krafters Engg. 
& Leasing (P) Ltd. [2011] 8 SCR 196 : (2011) 7 SCC 279; Board 
of Trustees For The Port of Calcutta v. Engineers-De-Space-Age 
[1995] Supp. 6 SCR 327 : (1996) 1 SCC 516; Sayeed Ahmed 
& Co. v. State of U.P. [2009] 10 SCR 841 : (2009) 12 SCC 26; 
Sree Kamatchi Amman Constructions v. Railways [2010] 10 SCR 
487 : (2010) 8 SCC 767; Union of India v. Bright Power Projects 
(India) (P) Ltd. [2015] 6 SCR 488 : (2015) 9 SCC 695; Chittaranjan 
Maity v. Union of India [2017] 11 SCR 722 : (2017) 9 SCC 611; 
Garg Builders v. BHEL (2022) 11 SCC 697; Madnani Construction 
Corpn. (P) Ltd. v. Union of India [2009] 16 SCR 216 : (2010) 1 
SCC 549; Tehri Hydro Development Corpn. Ltd. v. Jai Prakash 
Associates Ltd. [2012] 8 SCR 813 : (2012) 12 SCC 10 – referred to.
List of Acts
Arbitration Act, 1940; Arbitration and Conciliation Act, 1996.
[2025] 4 S.C.R. 
531
M/s Ferro Concrete Construction (India) Pvt. Ltd. v.  
The State of Rajasthan
List of Keywords
Grant of interest under Arbitration Act, 1940; Contractual clauses; 
Payment of interest; Pendente lite interest on arbitral sum; 
Phraseology of the agreement; Clauses conferring powers relating 

Excerpt shown. Read the full judgment & AI analysis in Lexace.