M/S. EMM ENN ASSOCIATES versus COMMANDER WORKS ENGINEER & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2016] 5 S.C.R. 503 M/S. EMM ENN ASSOCIATES v. COMMANDER WORKS ENGINEER & ORS. (Civil Appeal No.7184 of2008) JUNE 29, 2016 [ABHAY MANOHAR SAPRE AND ASHOK BHUSHAN, JJ.) Arbitration and Conciliation Act, 1996 - s. 11 - Work contract - To appellant-contractor, by Government - After completion of work, payment of undisputed part of final bill on 10.4.2001 - As per the contract defect liability period was two years, during which recovery could be made from the contractor - On 23.2.2005 contractor served notice to the Government raising other claims which were disputed - Claim denied - Letter by contractor to Government for appoint111ent of arbitrator as per the contract - Thereafter application uls.11 filed - Rejection of application by the Chief Justice of High Court on the ground that the clai111 was not a live clai111 and the notice dated 23.2.2005 was ti111e-barred - On appeal, held: The Chief Justice since exercises judicial power while deciding application u/s. 11, can examine the question as to whether the claim survives or needs to be adjudicated - But a clai111 can be held to be a dead claim only when the clai111 is evidently and patently long time-barred and there is no need for any detailed consideration of evidence - Jn the present case there was a dispute which needed adjudication after looking into all relevant documents, which could have been appropriately exa111ined by Arbitral Tribunal - Case remitted to Designated Judge for appointment of the arbitrator. Allowing the appeals and remitting the matters to Designated Judge, the Court HELD: 1. The Chief Justice exercises the judicial power while passing an order under Section 11 of the Arbitration and Conciliation Act, 1996 and thus can examine the question as to whether the claim which has been raised before him survives and needs to he adjudicated. If Chief Justice finds that claim is a dead claim, he can exercise jurisdiction in rejecting the application. [Para 17] [ 509-B-C) 503 A B c D E F G H 504 SUPREME COURT REPORTS [2016) 5 S.C.R. A SEP & CO. versus Patel Engineering Ltd and another 2005 (4) Suppl. SCR 688 : (2005) 8 SCC 618 - relied on. B c D E F G H 2. An application under Section 11 of the Act is expected to contain pleading about the existence of a dispute and the applicant is not expected to justify the claim or plead extensively in regard to limitation or production of document to demonstrate that claim is within time in proceeding under Section 11 and that issue should normally be left to the Arbitral Tribunal. Therefore, the Chief Justice may chose to hold a claim as a dead claim only when the claim is evidently and patently long time barred claim and there is no need for any detailed consideration of evidence. [Paras 19 and 20] [510-C-D, H; 511-A) Indian Oil Corporation Limited v. SPS Engineering Limited 2011 (2) SCR 512 : 2011 (3) SC 507 - relied on. 3. In the present case, the appellant has also contended that there is a defect liability period of two years during which any recovery can be made from the contractor. Further the categorical case of the appellant was that final payment made at 10.04.2001 was the final payment of the undisputed claim and there were other claims of the appellant which were disputed. There being no adjudication with regard to disputed claim, the claim raised by notice dated 23.02.2005 cannot be said to be barred by time or a dead claim. [Para 21] [511-B-C] 4. The examination of the additional materials brought on this appeal, d.oes indicate that the case required consideration of relevant bills and certificates and determination on the question as to whether the claim laid by appellant was a dead claim and was not a live claim depended upon scrutiny of relevant documents. The pleadings in the proceeding under Section 11 by the appellant were clearly to the effect that on 10.04.2001, he was paid only undisputed part and the appellant has reserved his right to raise claim to the disputed part. [Para 25] [513-A-B) 5. Thus, there was a dispute which needed an adjudication after looking into all relevant documents, bills and certificates which could have been appropriately examined by Arbitral MIS. EMM ENN ASSOCIATES v. COMMANDER WORKS 505 ENGINEER & ORS. Tribunal and the observation of the Chief Justice "As the appellant A has failed to prinw facie show this court that there was a live claim of the appellant" is not co
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex