LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S. DSR STEEL (P) LTD. versus STATE OF RAJASTHAN & ORS.

Citation: [2012] 5 S.C.R. 583 · Decided: 01-05-2012 · Supreme Court of India · Bench: T.S. THAKUR · Disposal: Dismissed

Cited by 5 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2012] 5 S.C.R. 583 
MIS. DSR STEEL (P) LTD. 
v. 
STATE OF RAJASTHAN & ORS. 
(Civil Appeal No. 3814 of 2007 etc.) 
MAY 1, 2012 
[T.S. THAKUR AND GYAN SUDHA MISRA, JJ.] 
Electricity Act, 2003 - s. 125 - Appeal under -
Maintainability of - Held: Appeal uls. 125 is maintainable only 
A 
B 
on the grounds specified uls. 100 CPC - It is maintainable C 
only when the case involves substantial question of law -
Concurrent findings of facts recorded by courts below cannot 
be reopened in appeal u/s. 125 - On facts, no substantial 
question of law arose for consideration - No perversity is found 
in the findings by courts below - Code of Civil Procedure, 1908 D 
- s. 100. 
Limitation - Reckoning of /imitation - Original order and 
the order dismissing the review petition - Whether the two 
orders merged and whether limitation to be reckoned from the 
E 
date of judgment/order in review petition and not original 
order - Held: Where review petition is dismissed, there is no 
question of merger - Limitation would be reckoned from the 
date of the original order - Doctrine of merger. 
Distribution Companies filed applications before 
F 
State Electricity Regulatory Commission for revision of 
tariff to be effective from 1.12.2004. The Commission 
directed that the revised tariff determined by it would 
become effective from 1.1.2005 and shall remain in force 
till the same is amended by the Commission by a G 
separate order. Appellants and other consumers filed 
review petitions seeking review of the order of the 
Commission and asking for continuation of the incentive 
scheme. They took the plea that withdrawal of the 
583 
H 
584 
SUPREME COURT REPORTS 
[2012] 5 S.C.R. 
A scheme offended the1 principle of promissory estoppal. 
The Commission dismissed the review petitions holding 
that the incentive scheme had a limited validity i.e. till 
31.3.2003 or till the C1ommission issued a tariff order, and 
thus its withdrawal did not offend the principles of 
B promissory estoppal. The appeal against the order was 
dismissed by the appellate tribunal for electricity. Hence 
the instant appeals were filed. 
Dismissing the appeals, the Court 
C 
HELD: 1.1 The appeals are liable to be dismissed as 
no substantial question of law arises for consideration. 
An appeal u/s. 125 of the Electricity Act, 2003 is 
maintainable before the Supreme Court only on the 
grounds specified in Section 100 CPC. Section 100 
D c:P.C. in turn permits filing of an appeal only if the case 
involves a substantial question of law. Findings of fact 
re.corded by the courts below, which would in the present 
case, imply the Regulatory Commission as the court of 
first instance and the Appellate Tribunal as the court 
E hearing the first appeal, cannot be re-opened before 
Supreme Court in an appeal u/s. 125 of the Electricity Act, 
2003. Just as the High Court cannot interfere with the 
concurrent findings of fact recorded by the courts below 
in a second appeal u/s. 100 CPC so also Supreme Court 
F would be loathed to entertain any challenge to the 
concurrent findings of fact recorded by the Regulatory 
Commission and the Appellate Tribunal. [Para 7] [592-D-
G] 
Govindaraju v. Mariamman AIR 2005 SC 1008: 2005 (1) 
G SCR1100; Hari Singh v. Kanhaiya Lal AIR 1999 SC 
3325:1999 (2) Suppl. SCR 216;Ramaswamy Ka/ingaryar v. 
MathayanPadayaci"1i AIR 1992 SC 115; Kehar 
Singh v. 
Yash Pal and Ors.AIR 1990 SC 2212; Bismil/ah Begum 
(Smt.) (Dead) by LRs. v. Rahmatu/lah Khan (Dead) by LRs. 
H AIR 1998 SC 970: 1998 (1) SCR 284 - relied on. 
DSR STEEL (P) LTD. v. STATE OF RAJASTHAN & 585 
ORS. 
1.2 The Regulatory Commission has, recorded a clear 
A 
finding of fact that the old incentive scheme was limited 
only upto 31st March, 2007 or till the Commission issued 
a tariff order whichever was earlier. It also recorded a 
finding that while considering revision of tariff it had 
gone into the proposals regarding introduction of a new 
B 
incentive scheme and approved the same, effectively 
bringing the existing scheme to an end and introducing 
a new scheme in its place. The Commission had declined 
to accept the contention that the appellant companies had 
altered their position to their detriment by making c 
additional investments or that there was any specific 
representation or promise made to them that the old 
scheme would inevitably continue till 31st March, 2007. 
The additional material which the appellants had sought 
to introduce belatedly at the review stage ha

Excerpt shown. Read the full judgment & AI analysis in Lexace.