LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S CHAHAL ENGINEERING CONSTRUCTION CO. versus IRRIGATION DEPARTMENT, PUNJAB, SIRSA

Citation: [1993] SUPP. 1 S.C.R. 449 · Decided: 30-07-1993 · Supreme Court of India · Bench: KULDIP SINGH · Disposal: Disposed off

cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

MIS CHAHAL ENGINEERING CONSTRUCTION CO. 
A 
v. 
IRRIGATION DEPARTMENT, PUNJAB, S!RSA 
JULY 30, 1993 
[KULDJP SINGH AND P.B. SA WANT, JJ.] 
Arbitration Act, 1940: 
Sections 30( a), 30( c }-Award-Grounds for setting aside-Ar-
bitratm-Misconduct-Held, misconduct includes an e1rnr on the face of the 
record-Award suffers from several patent emn:r-Objection allowed. award 
set aside-Matter rcfC1red to a new arbitration. 
The appellant-company entered into a contract with the respondent-
Department for construction of an aqueduct on turn-key basis for a lump-
B 
c 
sum total cost of Rs. 6.10 crores. According to the agreement, the drawing o· 
and dc;ign works were to be supplied by the appellant for approval of the 
respondent Department and in case of any deviation in the design increase 
in cost would not be charged to the respondent. The detailed designs and 
specifications furnished by the appellant did not show any sealing arrange-
ments 'lith provision for proper bearing pads and hence it was decided .fo 
adopt pre-stressed complete super-structure. The involved increase in the 
quantities of matters. The appellant claimed extra amount on account ol"the 
increase in the quantities and costs. This give rise to a dispute between the 
parties and the matter \\'as referred to an arbitrator. 
E 
The arbitrator held that the contract on lump-sum basis had come 
F 
to an end and was replaced by a contract on the item rate basis. He allowed 
reimbursement of extra costs due to incr~ase in quantities in intern1ediate 
well-foundations as well as reimbursements of costs for providing well-
foundations under the abutments and a\varded cotnpensation f'or the 
actual work done at the rates provided in the common schedule of rates, 
Volume II, PWD manual. Over and above these rates he also allowed a G 
premium of 575%. The arbitrator held that the appellant was entitled to 
the extra cost incurred by in on account of increase in quantities not~ 
withstanding that the contract was on a lump-sum basis because the 
modification made in the design were not the type of aqueduct which 
formed part of the agreetnent, the modifications in the design were not the H 
449 
450 
SUPREME COURT REPORTS 11993] SUPP. l S.C.R. 
A 
1nodifications referred to in the agreement, and the increase in quantities 
B 
· on account of the changes was verified by the respondent. Since the work 
was in progress, the award did not mention either the specific quantities 
or the total amount to be payable and the actual amount was left to be 
worked out in the light of the observations made in the award. The 
Arbitrator also pronounced and interirn a\\·ard in favour of the appellant 
amounting to Rs. 55 lakhs pending the working out of the final amount. 
The award was sought to be made a rule of the court by the appellant 
by, filing a suit in the civil court. The respondent preferred objections 
which were rejected and the award was made rule of the court. The 
C respondent filed an appeal before the High Court. 
Meanwhile the respondent terminated the contract on 4.4.1988. By 
the time the appellant had completed the work relating to the sun-struc-
ture. 
D 
The High Court allowed the appeal and set aside the order of the 
trial court holding that the Arbitrator had travelled beyond the scope of 
the agreement between the parties, the contract \Vas to be carried out on 
a lump-sum basis and that the Arbitrator completely ignored the terms in 
the agreement that the lump-sum tender would be inclusive of all expenses 
E for proper and entire completion of work. Hence the appeal, by special 
leave. 
The Court by its order date 13.8.191, appointed another arbitrator 
indicating that the new arbitrator should take not of the fact that the 
n1atter had once been arbitrated upon and some conclusions \\'ere reached 
F which were not seriously disputed by either side and proceed to complete 
the, unfinished part of the a\\-·ard by hearing the parties to the extent, he in 
his discretion considered necessary. 
The respondent submitted counter l:laims before the arbitrator "'ho 
G rejected the same on the ground that as per the directions of this Court 
he had only to quantify the amount which were left unspecified by the 
earlier arbitr.a':or. 
Ultimately, the arbitrator pronounced an a\Vard in favour of the 
appellant for Rs. 2,82,26,401 pins cost of Rs.1,42,500. The amount included 
H interest upto March 1992 and also escalation on the awarded amount. The 
·1 
CHAHAL 

Excerpt shown. Read the full judgment & AI analysis in Lexace.