LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S C & C CONSTRUCTIONS LTD. versus IRCON INTERNATIONAL LTD.

Citation: [2025] 1 S.C.R. 1413 · Decided: 31-01-2025 · Supreme Court of India · Bench: ABHAY S. OKA · Disposal: Dismissed

cites 3 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 1 S.C.R. 1413 : 2025 INSC 138
M/s C & C Constructions Ltd. 
v. 
IRCON International Ltd.
(Civil Appeal No. 6657 of 2023)
31 January 2025
[Abhay S. Oka* and Ujjal Bhuyan, JJ.]
Issue for Consideration
Matter pertains to the order passed by the Division Bench of the 
High Court, dismissing an appeal u/s.37 of the Arbitration and 
Conciliation Act, 1996, holding that the requirement of clause 49.5 
was never waived by the respondent, that clause 49.5 was a valid 
clause, upheld the arbitral award.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.37 – Arbitration 
award – Scope of interference in an appeal u/s.37 – Dispute 
between the appellant and the respondent over construction 
of Road Over Bridges – Case of the appellant that delay 
in construction work for the reasons attributable to the 
respondent, resulted in additional financial burdens – Appellant 
sought extension of time, and the same was extended by the 
respondent – Appellant then sought damages on account 
of delay on part of the respondent, however, the claims 
rejected – Thereafter, undertakings by the appellant that it 
would not claim anything extra other than escalation for 
the work executed – Two years later, the appellant invoked 
arbitration clause on basis of the claims raised – Arbitral 
tribunal rejected the claims based on clause 49.5 of GCC 
which disentitles the appellant from raising any claim for 
damages or compensation for failure or delay caused by the 
respondent in fulfilling its obligations under the contract – 
Petition u/s.34 by the appellant – Dismissed by the Single 
Judge of the High Court holding that the clause 49.5 would 
bar the appellant’s claim – Appeal before the Division Bench 
u/s.37 also dismissed – Correctness:
* Author
1414
[2025] 1 S.C.R.
Supreme Court Reports
Held: Scope of interference in an appeal u/s.37, in examining an 
order, setting aside or refusing to set aside an award, is limited 
and restricted – On facts, the appellant acted upon clause 49.5 
and sought an extension of time on three occasions – Solemn 
undertaking by the appellant not to make any claim other than 
escalation in respect of delays in the completion of work, however, 
claim made contrary to the undertakings – By the undertakings, the 
appellant agreed not to make a claim contrary to what is provided 
in clause 49.5, thus, by conduct, the appellant was estopped from 
challenging the validity of clause 49.5 – Furthermore, Clause 49.4 
would apply when the delay is not due to the respondent – In the said 
matter, the delay was on the part of the respondent, hence, clause 
49.5 would apply and not clause 49.4 – Also it cannot be inferred 
that clause 49.5 was waived by the respondent – Respondent 
stated that the claim for financial burden would have to be dealt with 
together with the proposal for an extension of time, and the said 
claim cannot be processed separately – Thus, on two occasions, 
on specific requests made by the appellant under clause 49 of 
the GCC, the extension of time was granted by the respondent – 
Except sub-clause 5 of clause 49, no other sub-clause which 
provides for grant of extension when the delay was attributable 
to the respondent – Thus, the order passed by the Division 
Bench upheld – General Conditions of Contract – Clause 49.5. 
[Paras 19, 23, 26-29]
Case Law Cited
Larsen Air Conditioning and Refrigeration Company v. Union of 
India and Ors. [2023] 11 SCR 86 : (2023) 15 SCC 472; Konkan 
Railway Corporation Limited v. Chenab Bridge Project Undertaking 
[2023] 11 SCR 215 : (2023) 9 SCC 85 – relied on.
Pam Developments Pvt. Ltd. v. State of West Bengal [2019] 9 
SCR 252 : (2019) 8 SCC 112; ONGC v. Wig Brothers Builders 
and Engineers Private Limited (2010) 13 SCC 377 – referred to.
List of Acts
Arbitration and Conciliation Act, 1996.
List of Keywords
Arbitration award; Arbitral award; Arbitration clause; Scope of 
interference in appeal u/s.37; Construction of Road Over Bridges; 
Delay in construction work; Additional financial burdens; Extension 
[2025] 1 S.C.R. 
1415
M/s C & C Constructions Ltd. v. IRCON International Ltd.
of time; Damages; Escalation for the work executed; Claim for 
damages or compensation; Solemn undertaking; Estopped from 
challenging validity of clause 49.5; Delay; Financial burden; General 
Conditions of Contract Clause 49.5.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6657 of 2023
From the Judgment and Order dated 01.03.2021 of the High Court 
of Del

Excerpt shown. Read the full judgment & AI analysis in Lexace.