M/S BHAGHEERATHA ENGINEERING LTD. versus STATE OF KERALA
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2026] 1 S.C.R. 303 : 2026 INSC 4 M/s Bhagheeratha Engineering Ltd. v. State of Kerala (Civil Appeal No. 39 of 2026) 05 January 2026 [J.B. Pardiwala and K.V. Vishwanathan,* JJ.] Issue for Consideration Whether the High Court by the impugned order was justified in holding that the Arbitral Tribunal was appointed at the request of the State to adjudicate dispute No.1 only; was the non-issuance of a notice u/s.21, Arbitration and Conciliation Act, 1996 by the appellant fatal for it to pursue its claim before the Arbitrator. Headnotesβ Arbitration and Conciliation Act, 1996 β Four packages of Road Maintenance Contract were awarded to the appellant β Appellant quantified the amounts due and submitted the same for decision by the Executive Engineer β As per the appellant, since the Executive Engineer/Superintending Engineer failed to take any decision, the appellant approached the Adjudicator under Clause 25.1 of the General Conditions of Contract, who ruled in favour of the appellant on dispute Nos.1 and 3 and against it on dispute Nos.2 and 4 β Respondent issued letter referring to arbitration Clause 25.3 expressing intention to refer only dispute No.1 to arbitration β Eventually, co-arbitrator nominated β By its award, the Arbitral tribunal answered all four disputes in favour of the appellant β Award challenged by the Respondent u/s.34 β Petition allowed by District Judge, award was set aside and the decision of the Adjudicator restored β Order upheld by High Court β Interference with: Held: High Court erred in setting aside the award on the basis that the appointment of the Tribunal was only to adjudicate dispute No.1 β On facts, conduct of the respondent precluded it from relying on the mandate of clause 24, 24.1 and 25 to contend that the appellant was foreclosed from raising the entire dispute *βAuthor 304 [2026] 1 S.C.R. Supreme Court Reports before the Arbitrator β The party at fault cannot be permitted to take advantage of the same β High Court also erred in holding that the non-issuance of notice u/s.21, A&C Act by the appellant with regard to dispute no.2 to 4 was fatal for it to pursue its claim before the arbitrator β There is no mandatory prerequisite for issuance of a s.21 notice prior to the commencement of Arbitration β Also, High Court erred in holding that the Arbitral Tribunal exceeded its jurisdiction in deciding the entire dispute β Arbitration Clause 25.3 is widely worded and any dispute or difference arising between the parties relating to any matter arising out of or concerned with the agreement are to be settled in accordance with the A&C Act by the Arbitral Tribunal β Judgment of High Court set aside β Award of the arbitrator upheld in its entirety β Contract Act, 1872 β s.28(b). [Paras 14-16, 18, 22] Arbitration and Conciliation Act, 1996 β s. 21 β Object of β Was the non-issuance of a notice u/s.21 by the appellant fatal for it to pursue its claim before the Arbitrator: Held: No β The object of s.21 is only for the purpose of commencement of arbitral proceedings β s.21 is concerned only with determining the commencement of the dispute for the purpose of reckoning limitation β There is no mandatory prerequisite for issuance of a s.21 notice prior to the commencement of Arbitration β Issuance of a s.21 notice may come to the aid of parties and the arbitrator in determining the limitation for the claim β Failure to issue a s.21 notice would not be fatal to a party in Arbitration if the claim is otherwise valid and the disputes arbitrable β High Court erred in holding that the non-issuance of notice u/s.21 by the appellant with regard to dispute no.2 to 4 was fatal for it to pursue its claim before the arbitrator. [Paras 14, 16] Arbitration and Conciliation Act, 1996 β s.2(9), 23: Held: Once the Arbitral Tribunal is constituted claims, defence and, counter claims are filed β Party which normally files the claim first is, for convenience, referred to as the βclaimantβ and the party which responds is called the βrespondentβ β The said respondent is also along with the defence statement entitled to file its counter claim β Hence, to contend that the appellant cannot be referred to as a claimant because no notice u/s.21 has been issued is completely untenable. [Para 21] [2026] 1 S.C.R. 305 M/s Bhagheeratha Engineering Ltd. v. State of Kerala Case Law Cited State of Goa v. Praveen Enterprises [2011] 10 SCR 1026 : (2012) 12 SCC 581; M.K.
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex