M/S. ASSOCIATED CONSTRUCTION versus PAWANHANS HELICOPTERS PVT LTD
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2008] 7 3 C.R 970 A MIS. ASSOCIATED CONSTRUCTION v. PAWANHANS HELICOPTERS PVT LTD (Civil Appeals Nos. 3376-3377 of 2008) B MAY 7, 2008 [TARUN CHATTERJEE AND HARJIT SINGH BEDI, JJ.] Arbitration - Award - Challenge to - Held: The Court does not sit in appeal over an arbitral award - If view taken by c arbitrator permissible, it cannot be interfered with, on the premise that a different view is also possible - On facts. it cannot be said that the arbitra! award was so unconscionable that it required interference by Court Contract - For construction work - Between Appellant D and Respondent-Government undertaking - Delay in .. complr->tion of work on account of reasons attributable to Respondent - Respondent demanded "No Dues Certificate" for release of payment - Appellant gave such certificate - Claim towards escalation by Appellant - On facts held: Even E assuming that there could be no price escalation during pendency of the contract, such embargo could not be carried beyond that period as time was essence of the contract- Plea raised by Appellant that it issued "No Dues Certificate" under duress not an after thought. F Appellant-contracting firm entered into a contract for construction work with the Respondent, a Government of India undertaking. The construction work was scheduled to be completed in 4 month but the Appellant could not meet the deadline due to the fault of the G Respondent. The Respondent demanded a "No Dues Certificate" for release of payment. Appellant gave such certificate allegedly "under duress" as it was in economic .. distress. There was a disagreement between the parties over the payment of bills. The matter was referred for H 970 MIS ASSOCIATED CONSTRUCTION v. PAWANHANS 971 HELICOPTERS PVT LTD. arbitration. The arbitral award passed was in favour of A Appellant. on which the Respondent moved the High Court. The Single Judge too held in favour of Appellant stating that clauses 18 and 34 of the contract, when read together, provided for the payment of escalation charges ...... as the work had not been completed within four months B on account of the fault on the part of the Respondent and that the said clauses did not prohibit such payment, more particularly as time was essence of the contract and as the contract was not on a fixed price, the prohibition of escalation was, if at all, to be read during the period of c contract only. The Single Judge also repelled the arguments of the Respondent that after having submitted the final bill on 25th October 1991, it was not open to the Appellant to submit a second final bill on 2nd February 1993 by observing that the payment received as a consequence of D the bills submitted on 25th October 1991, was "under duress" and it is on that account that the App~llant had given the aforesaid "No Dues Certificate". The Division Bench of the High Court however set aside the order of the Single Judge. Hence the present appeals. E Allowing the appeals, the Court HELD:1.1. Clause 43 and 43 (1) and (2) of the contract in question when read together clearly visualize escalation of price on account of reasons beyond the control of the F contractor and attributable to the other side. Moreover, ~ . clause 43 (2) clearly states that the remedy under clause 43(1) would be in addition to such other remedy that may be open to the contractor under the other provisions. Clause 43 should be read in aid of the contractor as it clearly provides for indemnity in case there was a delay in the completion of G the work which could be attributable to the Respondent. Further, even assuming for a moment that there could be no price escalation during the period of 4 months i.e. during the pendency cf the contract, such embargo would not be carried beyond that period as time was the essence of the H 972 SUPREME COURT REPORTS [2008] 7 S.C.R. A contract. [Paras 7, 11] [981-C,D, 984-F,G] 1.2. The Court does not sit as one in appeal over the award of the arbitrator and if the view taken by the arbitrator is permissible, no interference is called for on the premise that a different view was also possible. Also, 8 in commercial transactions, all situations cannot be visualized and the positive and unchallenged finding in the present case is that the delay in the execution of the work was occasioned on account of reasons attributable the to Respondent. It cannot, therefore, be said that the C awa
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex