LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

LATA CONSTRUCTION AND ORS. versus DR. RAMESHCHANDRA RAMNIKLAL SHAH AND ANR.

Citation: [1999] SUPP. 1 S.C.R. 412 · Decided: 12-08-1999 · Supreme Court of India · Bench: S. SAGHIR AHMAD · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
LATA CONSTRUCTION AND ORS. 
v. 
DR. RAMESHCHANDRA RAMNIKLAL SHAH AND ANR. 
AUGUST 12, 1999 
[S. SAGHIR AHMAD AND R.P. SETHI, JJ.] 
Consumer Protection Act, 1986-Section 24A-Respondents entered 
into an Agreement with Appellant No. I in 1987 for purchase of a flat to be 
built by the appellants afterwards-Part payment made by the respondents-
C Appellants failed to deliver possession of the flat-later the flat found to be 
in possession of some other person-Appellants entered into a fresh Agreement 
with (he Respondents in 1991-Agreed to pay compensation to the 
Respondents in lieu of the flat on or before 30-05-1991-New Agreement 
stipulated that the 1987 Agreement would remain unajfected-1987 Agreement 
D was to be treated as terminated only on full payment of compensation-
Appellants neither delivered possession of the flat nor paid the said amount-
Complaint fi/ed before the Natienal Commission in July, 1993-Claim decreed 
for the compensation amount in lieu of flat-Order of the National Commission 
appealed on ground of limitation-Held, as 1991 Agreement not complied 
with, the 1987 Agreement remained in force-Appellants were under a 
E constant obligation to provide a flat to the Respondents under the previous 
Agreement-Appellants failing to provide a flat, cause of action continued 
to exist-Claim was not beyond time. 
Contract Act, 1872-Section 62-Agreement between Appellant No. I 
and the Respondents in 1987-Respondents to purchase flat from Appellants 
F to be built later-Appellants failed to deliver possession of the flat-Appellants 
entered into afresh Agreement with the respondents in 199/_:_Agreed to pay 
compensation to the respondents in lieu of the flat on or before 30-05-1991-
New Agreement stipulated that the 1987 Agreement would remain unaffected-
1987 Agreement was to be treated as terminated only on full payment of 
G compensation-Appellants neither delivered possession of the flat nor paid 
the said amount-Complaint filed before the National Commission for the 
amount of compensation-Claim decreed for compensation amount-Order 
of the National Commission appealed against-Contended that after 1991 
Agreement, the rights under the 1987 Agreement could not be claimed-No 
remedy available to the respondents before the National Commission-
H 
412 
... 
. ..
LATA CONSTRUCTION v. DR. R.R. SHAH 
413 
; 
Respondents could approach civil court for recovery of the compensation A 
amount-Held, as 1991 Agreement not complied with, the terms of 1987 
Agreement remained in force-Respondents could legally claim enforcement 
of right under the 1987 Agreement-Entitled to file a complaint before the 
.... 
National Commission for compensation on account of deficiency in service. 
The respondents who were in Libya had entered into an agreement B 
dated 27-01-1987 with Appellant No. 1 according to which the appellants 
were to develop, construct and hand over possession of flat No. AG-2 on the 
ground floor with an area of 670 sq. ft. situated in a building named 
"Madhusudan" in Ville Parle, Bombay. On 27th of January, 1987, the 
respondents paid a sum of Rs. 3,38,000 to the appellants in cash but without C 
any receipt and a sum of Rs. 32,000 by cheque against receipt. The respondents 
also paid a further sum of Rs. 2,00,000 to the appellants on various dates 
as demanded by them. In June, 1988 when the appellants returned from 
Libya, they requested the appellants to deliver, on payment of balance amount 
~f sale consideration, possession of the flat to them as the construction of D 
the building was complete. However, the appellants refused to accept the 
payment and deliver the possession on the plea that the building was still 
under construction particularly as the electricity, plumbing etc. work was 
in progress. The appellants assured the respondents that as and when the 
building would be completed in all respects, they would deliver the possession 
by accepting the balance amount. In April, 1990, when the respondents again E 
came back from Libya and visited the building, they found the flat locked, 
with a name plate ofsome other person on the main door. In January, 1991 
after returning from Libya, the respondents demanded the possession of the 
flat, but the appellants expressed their inability to give possession of the Oat 
to the respondents in compliance of the agreement dated 27-01-1987. The F 
appellants, however, entered into a fresh agreement with the respondents on 
23-02-1991 agreeing t

Excerpt shown. Read the full judgment & AI analysis in Lexace.