LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

LARSEN AND TOUBRO LIMITED versus PURI CONSTRUCTION PVT. LTD. AND OTHERS

Citation: [2025] 4 S.C.R. 2811 · Decided: 21-04-2025 · Supreme Court of India · Bench: ABHAY S. OKA · Disposal: Dismissed

cites 4 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 4 S.C.R. 2811 : 2025 INSC 523
Larsen and Toubro Limited 
v. 
Puri Construction Pvt. Ltd. and Others
(Civil Appeal No(s). 2575-2578 of 2016)
21 April 2025
[Abhay S. Oka* and Pankaj Mithal, JJ.]
Issue for Consideration
In petition u/s.34, Arbitration and Conciliation Act, 1996, Single 
Judge had set aside the Arbitral Award. Division Bench in appeal 
thereagainst u/s.37, Arbitration Act by way of the impugned 
judgment, inter alia upheld the dismissal of L&T’s counter-claim 
and agreed with the findings of the Arbitral Tribunal that the 
Supplementary Agreement was a non-starter as it was vitiated 
by economic duress; that the Development Agreement was not 
novated by the Supplementary Agreement; that L&T committed 
fundamental breach of the Development Agreement. The operative 
part of the award fixing the monetary liability of L&T was set aside 
while leaving open the remedy of PCL for the quantification of 
the monetary claim. The award regarding costs was confirmed 
however, the Division Bench did not restore any part of the arbitral 
award and the parties were left to pursue the appropriate course of 
action. Issue as regards the correctness of the impugned judgment, 
challenged by both, L&T and PCL; power of the court u/s.34, 
Arbitration Act of partly setting aside the award; whether in the 
facts and circumstances of the present case, the Division Bench 
modified the Award by partly setting aside the judgment u/s.34.
Headnotes†
Arbitration and Conciliation Act, 1996 – ss.34, 37 – Puri 
Construction Limited and its sister concerns (β€˜PCL’) were in 
possession of certain lands as the owner – PCL had entered 
into a joint venture with ITC Classic Real Estate Finance Limited 
(ITCREF) for the development of lands, however, ultimately, 
ITCREF exited from the business – L&T and PCL entered into an 
agreement for land development (Development Agreement) – 
Later, a supplementary agreement was entered into between 
them on the basis of which a Tripartite Agreement was entered 
* Author
2812
[2025] 4 S.C.R.
Supreme Court Reports
into between PCL, L&T and the Bank – Disputes arose – Arbitral 
Award was passed holding inter alia that L&T jeopardised 
PCL’s obligations towards ITCREF; it resiled from and went 
back upon its original contractual obligations and tried to 
effect sales without sanction under the revised development 
plan and without making any provision for the responsibility 
towards ITCREF; L&T abandoned the Development Agreement; 
Supplementary Agreement was tainted by economic coercion 
and the signatures of PCL were obtained by fraud – In petition 
u/s.34, Single Judge set aside the award – By the impugned 
judgment, Division Bench disagreed with certain findings of 
the Single Judge, allowing the appeals preferred by PCL to that 
extent and the appeal by L&T was dismissed – However, the 
parties were left to pursue the appropriate course of actions 
under law – Challenge to, by both PCL and L&T:
Held: 1.1 Powers of the Appellate Court u/s.37 of the Arbitration 
Act are not broader than those of the Court u/s.34 of the Arbitration 
Act – Therefore, what cannot be done in the exercise of the powers 
u/s.34 cannot be done in an Appeal u/s.37 – An Arbitral Award 
cannot be modified – In the present case, the Division Bench 
has not modified the award by partly setting aside the Judgment 
u/s.34 – The remedy of PCL was kept open to pursue appropriate 
course of action under law as there cannot be a remand to the 
Arbitral Tribunal for quantification of monetary claim – As the 
finding of the Arbitral Tribunal regarding breaches committed by 
L&T was affirmed, the Division Bench rightly segregated that part 
of the award by which, cost of arbitration was ordered to be paid 
to PCL by L&T – As documents of title were deposited with the 
Registrar, the direction to hand over the same to PCL cannot be 
faulted with. [Para 56]
1.2 In view of the clauses in the Supplementary Agreement, the 
finding recorded by the Tribunal that, as the conditions precedent 
in the relevant clauses were not complied with by L&T, the 
Supplementary Agreement was a non-starter is a possible finding 
which could not have been interfered with u/s.34 of the Arbitration 
Act – Moreover, it is a finding of fact. [Para 46]
1.3 Further, after examining the evidence, the Division Bench 
held that there was no patent illegality in the findings recorded by 
the Arbitral Tribunal that the Supplementary Agreement and the 
Tripartite Agre

Excerpt shown. Read the full judgment & AI analysis in Lexace.