LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

KUKREJA CONSTRUCTION COMPANY & OTHERS versus STATE OF MAHARASHTRA & OTHERS

Citation: [2024] 9 S.C.R. 830 · Decided: 13-09-2024 · Supreme Court of India · Bench: B.V. NAGARATHNA

cites 13 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 9 S.C.R. 830 : 2024 INSC 692
Kukreja Construction Company & Others  
v. 
State of Maharashtra & Others
(Civil Appeal No. 9702 of 2024)
13 September 2024
[B.V. Nagarathna* and  
Nongmeikapam Kotiswar Singh, JJ.]
Issue for Consideration
Whether the High Court was right in declining to grant relief to 
the writ petitioners-appellants herein on the ground of delay and 
laches; whether the appeals filed by the respondent-Mumbai 
Municipal Corporation would call for any interference; what order 
to be passed.
Headnotes†
Maharashtra Regional and Town Planning Act, 1966 –  
s.126(1)(b) – Acquisition of land required for public purposes 
specified in plans – Development Control Regulations for 
Greater Bombay, 1991 – Regulations 33; 34 r/w Para 6 of 
Appendix-VII – Determination of compensation in form of Floor 
Space Index (FSI) and/or Transferrable Development Rights 
(TDR) – Claim for additional FSI/TDR against the development/
construction of the amenity on the surrendered land at owner 
or lessee’s costΒ  – Inapplicability of doctrine of delay and 
laches – Appellants-land owners held plots reserved in the 
sanctioned development plan for Development Plan Road 
(DP Road) – Appellants had constructed DP Road at their 
own cost and voluntarily surrendered the reserved lands to 
the respondent-Corporation, were granted 25% TDR for the 
construction of said amenity at their cost – Later, after the 
judgment of Supreme Court in Godrej & Boyce Manufacturing 
Company Limited v. State of Maharashtra reported as [2009] 
1 SCR 1016 (Godrej & Boyce I) holding that the owner or 
lessee would be entitled to FSI or TDR equivalent to 100% 
of the area of the road constructed by them, the appellants 
* Author
[2024] 9 S.C.R. 
831
Kukreja Construction Company & Others v. 
State of Maharashtra & Others
claimed additional FSI/TDR – Rejected by High Court on the 
ground of delay and laches – Correctness:
Held: Not correct – Question of delay and laches would not 
arise in present cases – Once the compensation is determined 
in the form of FSI/TDR, the same is payable even without any 
representation or request being made, as otherwise there would 
be a breach of Article 300-A of the Constitution – Respondent did 
not establish that owing to a short delay even if it had occurred in 
any of these cases owing to uncertainty in law, it was prejudiced 
by the same or that third-party rights were created which could 
not be disturbed owing to delay or laches – Neither the doctrine 
of delay and laches nor the principle of abandonment of claim or 
waiver would apply in these cases – Rather, the delay occurred 
on the part of the Mumbai Municipal Corporation in complying 
with the Regulations insofar as the appellants are concerned – 
High Court not right in dismissing the writ petitions on the ground 
of delay and laches, impugned order set aside to that extent –  
However, reasoning of the High Court holding that the 2016 
notification amending Regulation 34 of the 1991 DCR would not 
apply retrospectively or retroactively to a land reserved under the 
development plan which is surrendered and amenity is developed 
on the said land by the owner or lessee thereof at his own cost 
prior to the amendment, not interfered on merits – Respondent to 
consider the case of writ petitioners-appellants herein in light of 
Godrej & Boyce I case and release the balance FSI/TDR to the 
appellants however, in the case of appellant – Kukreja Construction 
company and others, the respondent to consider the nature of 
the amenities constructed and thereafter consider their case for 
additional FSI/TDR. [Paras 4.8, 18, 20]
Case Law Cited
Godrej & Boyce Manufacturing Company Limited v. State of 
Maharashtra [2009] 1 SCR 1016 : (2009) 5 SCC 24; Municipal 
Corporation of Greater Bombay v. Natwar Parikh & Co. Pvt. Ltd., 
Civil Appeal No. 1748 of 2015; Noida Entrepreneur Association 
v. NOIDA [2011] 8 SCR 25 : (2011) 6 SCC 508; Sukh Dutt Ratra 
v. State of Himachal Pradesh [2022] 2 SCR 1041 : (2022) SCC 
OnLine SC 410; Lalaram v. Jaipur Development Authority [2015] 
14 SCR 403 : (2016) 11 SCC 31; Moon Mills Ltd. v. M.R. Meher, 
832
[2024] 9 S.C.R.
Digital Supreme Court Reports
President, Industrial Court, Bombay, AIR 1967 SC 1450; M/s Dehri 
Rohtas Light Railway Company Limited v. District Board, Bhojpur, 
[1992] 2 SCR 155 : (1992) 2 SCC 598; Hindustan Petroleum 
Corporation Ltd. v. Dolly Das (1999) 4 SCC 450; Mohar Singh 
(Dead) Thr. Lrs. v. State of UP Collect

Excerpt shown. Read the full judgment & AI analysis in Lexace.