KARNATAKA POWER TRANSMISSION CORPORATION LIMITED AND ANOTHER versus M/S. DEEPAK CABLES (INDIA) LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2014] 4 S.C.R. 771 KARNATAKA POWER TRANSMISSION CORPORATION LIMITED AND ANOTHER v. MIS. DEEPAK CABLES (INDIA) LTD. (Civil Appeal No. 4424 of 2014) APRIL 07, 2014 [ANIL R. DAVE AND DIPAK MISRA, JJ.] A B Arbitration and Conciliation Act, 1996: s.11 (6) - Appointment of arbitrator - Dispute between the parties - C Respondent seeking appointment of arbitrator - Resisted by appellant on the ground that the agreement did not provide for arbitration - Held: Clause 48 of the agreement provided that when disputes or differences of any kind arise between the parties relating to the performance of the works during D progress of the works or after its completion or before or after the termination, abandonment or breach of the contract, it is to be referred to and settled by the engineer - There is also a stipulation that his decision in respect of every matter so referred to shall be final and binding upon the parties until the E completion of works and is required to be given effect to by the contractor who shall proceed with the works with due diligence - This clause did not provide any procedure to even remotely indicate that the concerned engineer was required to act judicially as an adjudicator by following the principles of natural justice or to consider the submissions of both the parties - This only depict that the said clause was engrafted to avoid delay and stoppage of work and facilitate smooth carrying on of the work - The language employed in the clause F did not spell out the intention of the parties to get the disputes G adjudicated through arbitration - Apart from that clause 4. 1 of the agreement stated that it was specifically agreed by and between the parties that all the differences or disputes arising ?ut of the Agreement or touching the subject matter of the 771 H 772 SUPREME COURT REPORTS [2014) 4 S.C.R. A Agreement would be decided by a competent Court at Bangalore - Thus, clause 48, read in conjunction with clause 4.1, clearly established that there was no arbitration clause in the agreement. 8 Appellant No. 1, a State Transmission utility invited tenders for establishing sub-stations. Respondent- company was successful bidder and contract was entered with it. Dispute arose and tile respondent filed application under Section 11 (5) and (6) of the Arbitration and Conciliation Act, 1996 before the High Court for C appointment of an arbitrator. The application was resisted by the appellant on the ground that clause 48 did not provide for arbitration and same cannot be co...,strued as an arbitration clause. The High Court held that a plain reading of clause 48 would indicate that it partak~ the D character of an arbitration clause and, accordingly, appointed a sole arbitrator to adjudicate the matters in dispute. Hence these appeals. E Allowing the appeals, the Court HELD: 1. Section 7 of the Arbitration and Conciliation Act, 1996 states that unless an arbitration agreement stipulates that the parties agree to submit all or certain disputes which have arisen or which may arise in respect . F of defined legal relationship, whether contractual or not, there cannot be a reference to an arbitrator. It conveys that there has to be intention, expressing the consensual acceptance to refer the disputes to an arbitrator. In the absence of an arbitration clause in an agreement, as defined in sub-section (4) of Section 7, the dispute/ G disputes arising between the parties cannot be referred to the arbitral tribunal for adjudication of the dispute. [Para 9] [779-F-H; 780-A] 2. Clause 48 is to the effect that it provides for the H parties to amicably settle any disputes or differences KARNATAKA POWER TRANSMISSION CORP. LTD. v. 773 DEEPAK CABLES (INDIA) LTD. arising in connection with the contract. This is the first A part. The second part is that when disputes or differences of any kind arise between the parties to the contract relating to the performance of the works during progress of the works or after its completion or before or after the termination, abandonment or breach of the contract, it is B to be referred t,o and settled by the engineer, who, on being requested by either party, shall give notice of his decision within thirty days to the owner and the contractor. There is also a stipulation that his decision in respect of every matter so referred to shall be final and c binding upon the parties until the completion o
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex