LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

KANPUR ELECTRICITY SUPPLY CO. LTD. & ANR. versus M/S. L.M.L. LIMITED & ORS.

Citation: [2010] 6 S.C.R. 419 · Decided: 07-05-2010 · Supreme Court of India · Bench: ALTAMAS KABIR · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

.... -. 
ยท (2010] 6 S.C.R. 419 
KANPUR ELECTRICITY SUPPLY CO. LTD. & ANR. 
A 
v. 
M/S. L.M.L. LIMITED & ORS. 
(SLP (Civil) No. 33984 of 2009) 
MAY 7, 2010 
[ALTAMAS KABIR, CYRIAC JOSEPH AND C.K. 
. 
PRASAD, JJ.] 
B 
U. P. Electricity Supply Code, 2005 - Clause 4.41 read 
with clause 4.49 -
Reduction in contracted load -
C 
Deteriorating market conditions - Application for reduction of 
contracted load from 8 MVA to 1.25 MVA with effect from 
01.04.2006, by a public limited company- Meeting between 
two companies to reduce the same subject to certain condition 
-
Load reduction approved by Electricity Regulatory D 
Commission - Company declared 'Relief undertaking' as 
also 'Sick unit' - Electricity Supply Company-KESCO raising 
monthly bills based on 8 MVA load thereafter - KESCO 
asking the company to submit Bank Guarantee for arrears of 
amount as per the amended clause 4.49 - Load not reduced 
E 
since Bond and affidavits submitted by company did not 
secure the outstanding dues - Direction by BIFR to KESCO 
to continue to accept Rs.5 lakhs p.m. against arrear dues 
together with current dues on basis of actual consumption -
Strict adherence by company to the said order - However, 
F 
issuance of disconnection notice ...,.. Writ petition by company 
seeking direction upon KESCO that load stood reduced from 
01.04.2006 - Allowed by High Court - Interference with -
Held: Not called for - KESCO, instead of helping the 
company to come out of its financial crisis, prevented it from 
G 
doing so by refusing to lower the load from 8 MVA to 1.25 
MVA, as agreed upon - In fact, company had been declared 
a 'Relief Undertaking' and a 'Sick Company' - When decision 
was ta!fen to reduce the contract load, unamended Clause. 
4.49 was in existence which provided for submission of either H 
419 
420 
SUPREME COURT REPORTS 
[201 O] 6 S.C.R. 
A a Bank Guarantee or a Bond or any other instrument to the 
satisfaction of the licensee of the equal amount of pending 
dues - After amendment, Bond was excluded from the 
provision -
Continued insistence of KESCO that Bank 
Guarantee should be provided by the company in respect of 
s its outstanding dues, had the effect of negating the decisions 
to revive the Company - Electricity Act, 2003 - s. 5. 
Respondent no.1 is a public limited company 
engaged in the manufacture and sale of two-wheelers. 
C Due to market fluctuations it had to stop its manufacturing 
activities. The respondent company was declared a 
"Relief Undertaking" uls. 3(1) of the U.P. Industrial 
Undertaking (Special Provisions for Prevention of 
Unemployment) Act, 1966. The respondent no.1-company 
applied to the petitioner-State Electricity Supply 
D Company for reduction of the contracted load from 8 MVA 
to 1.25 MVA from 1st April, 2006. The decision was taken 
by two companies to reduce the load with certain 
conditions. The Electricity Regulatory Commission 
approved the reduction of the load. However, electricity 
E bill was raised for the month of May, 2006 on basis of 8 
MVA load. The respondent paid the bill on basis of 1.25 
MVA load. The respondent company was also declared 
a "Sick Company" under Sick Industrial Companies 
(Special Provisions) Act, 1985. The load was not reduced 
F since the outstanding dues of the respondent company 
were 8.42 crores as on 31st March, 2006. The petitioner 
wrote to the respondent to submit a Bank Guarantee for 
arrears of the amount as per the amended clause 4.49 of 
the U.P. Electricity Supply Code, 2005 so that action could 
G be taken to reduce the load from 8 MVA to 1.25 MVA. 
Thereafter, the respondent company restarted its 
manufacturing activities and sought increase of the load 
from 1.25 MVA to 2.25 MVA. The petitioner rejected the 
same since the respondent did not submit the Bank 
H Guarantee for the balance amount. The respondent 
KANPUR ELECTRICITY SUPPLY CO. LTD. & ANR. v. 421 
l.M.L. LIMITED & ORS. 
company submitted a Bond stating that the Company 
A 
was agreeable to make payment of the arrears, if any, to 
petitioner upon the directions of the court and the amount 
as was decided by the courts. However, since the two 
affidavits and the Bond did not secure the outstanding 
dues of the petitioners and were also not to its B 
satisfaction, the load was not reduced. The BIFR then 
directed the petitioners to continue to accept Rs.5 lakhs 
p.m. against the arrear dues together with the current 
dues on the basis of the actual consumption and not to 
adopt coer

Excerpt shown. Read the full judgment & AI analysis in Lexace.