LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

KALPATARU POWER TRANSMISSION LTD. (NOW KNOWN AS KALPATARU PROJECTS INTERNATIONAL LTD.) versus VINOD AND ORS. ETC.

Citation: [2025] 8 S.C.R. 1053 · Decided: 19-08-2025 · Supreme Court of India · Bench: M.M. SUNDRESH · Disposal: Disposed off

cites 5 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 8 S.C.R. 1053 : 2025 INSC 1004
Kalpataru Power Transmission Ltd. 
(Now Known as Kalpataru Projects International Ltd.)  
v. 
Vinod and Ors. Etc.
(Civil Appeal No(s). 10882-10888 of 2025)
19 August 2025
[M.M. Sundresh and Rajesh Bindal,* JJ.]
Issue for Consideration
Issue arose as regards the landowners seeking further 
enhancement of compensation on account of damages suffered by 
erection of transmission lines and towers, whereas the Contractor 
challenging the amount of compensation awarded; and whether 
there should be some remedy of appeal against order passed by 
the District Judge.
Headnotes†
Telegraph Act, 1885 – s.16(3), (4) – Disputes as to compensation – 
Assessment of compensation for the Tower Base Area (land 
beneath four legs of the tower) and the Right of Way-ROW 
Corridor – Utilization of land owned by the landowners for 
erection of tower or drawing power lines in four districts, 
however ownership of the land not transferred – Damages 
suffered by the landowners – Petition u/s.16(3) before the 
District Judge by the landowners – Award of compensation 
by District Judge of Sonepat and Jhajjar respectively – High 
Court decided bunch of petitions, and awarded uniform 
compensation to the landowners @ 85% of the collector rate 
beneath the tower area, determined at ₹1.50 crores per acre, 
and for diminishing the value of land across the width of 
ROW, 15% of the value of land, on account of imposition of 
restrictions on utilization thereof – High Court assessed the 
compensation in all cases on basis of the facts pertaining 
to land in district Sonepat only, without touching the facts 
pertaining to district Jhajjar – Sustainability:
Held: Order passed by the High Court cannot be legally sustained – 
High Court failed to appreciate the fundamental fact that land 
* Author
1054
[2025] 8 S.C.R.
Supreme Court Reports
pertaining to different villages falling in different districts, which 
may be the subject matter of consideration for assessment of 
compensation, would have been assessed differently by the 
Collector based on their respective locations and characteristics – 
Facts only pertaining to district Sonepat have been discussed – 
Applying a uniform rate for the entire transmission corridor would 
not be a proper methodology for assessing fair compensation to 
which the landowners are entitled to – Thus, the manner adopted 
by the High Court for assessment of compensation not approved – 
Some parties invoked Art. 226, whereas others filed petitions 
invoking Art. 227 challenging the judgments of the trial court, 
which were delivered on appreciation of evidence – This is solely 
because no proper appellate remedy has been provided against 
the order passed by the District Judge – There are other gaps as 
well in the statutory scheme-limited determination of compensation, 
no timelines regarding payment of compensation to the affected 
parties after the right u/s.10(d) is exercised by the competent 
authority – This being an Act of Parliament, its application has 
to be uniform throughout the country – In the absence of defined 
parameters, it will depend on different courts, how they interpret 
the provisions – Unless statutory remedy of appeal is provided 
where all issues of law and facts can be re-examined, any other 
remedy may be illusionary – Remedies availed by different parties 
were different – Reappriciation of evidence in those proceedings 
may be an issue – Anomalies with reference to various timelines 
as well, the matter to be examined – Issues to be examined by 
the Law Commission of India and the Ministry of Law and Justice, 
Government of India, to determine whether a statutory remedy 
of appeal should be provided against judgments/orders passed 
u/s.16(3) and 16(4), the Petroleum Act or any other similar statute – 
In district Sonepat, application for dispute related to compensation 
was registered and numbered as a Civil Suit where a judgment 
and decree was passed, whereas in district Jhajjar, the same was 
registered as a Civil Miscellaneous Application and only judgment 
was passed – Need to bring uniformity in the nomenclature to be 
assigned to these kind of proceedings, which may come to the 
court under the 1885 Act and also the proceedings under the 
Petroleum and Minerals Pipelines (Acquisition of Right of User in 
Land) Act, 1962 – Order passed by the High Court set aside – 
Matters remitted back to the High Court for fresh consideration – 
Electricity Act, 200

Excerpt shown. Read the full judgment & AI analysis in Lexace.