LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

K.V. GEORGE versus SECRETARY TO GOVT., WATER AND POWER DEPARTMENT, TRIVANDRUM & ANR.

Citation: [1989] SUPP. 1 S.C.R. 398 · Decided: 05-10-1989 · Supreme Court of India · Bench: SABYASACHI MUKHERJI · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
K.V. GEORGE 
v. 
SECRETARY TO GOVT., WATER AND POWER 
DEPARTMENT, TRIVANDRUM & ANR. 
OCTOBER 5, 1989 
. 
[SABYASACHI MUKHARJI AND B.C. RAY, JJ.] 
Arbitration Act 1940-Sections 30, 33 and 41-Arbitrator to 
make award after considering claims and counter claims of the parties-
Failure to do so is misconduct-Principles of res·judicata applicable to 
C arbitration proceedings. 
The appellant, a contractor had entered into a contract with the 
Respondent on 22nd April 1978 for the construction of an embankment 
across Mnsaliyar Podom between chainage 2573.5 M-to 2827 M of E.B. 
D Main conal of Kallada Irrigation Project. Under the contract-agree-
ment, the work was to the completed by March 30, 1980 i:e. two years 
ftom the date of selection notice which was dated March 30, 1978. The 
appellant having failed to complete the work as per the terms of the 
contract, the Respondent by a notice dated 26.4.80 cancelled the con-
tract at his riskcand cost. Consequent there-to the appellant filed a 
I; claim before the named Arbitrator (Case No. 132 of 1980), claiming 
enhancement of rates in respect of the earth work involved in the con-
tract. He also claimed interest on delayed payment and costs. The 
respondent resisted the claim and urged that the appellant was not 
entitled to any enhancement, as the appellant should have visualised 
and assessed the position before entering into work contract which was 
to be completed within 2 years. According to respondent the appellant 
had not even completed 35% of the work. Respondent, No. 2, therefore, 
filed a"counter-ciaiin for-Rs~28,84,ooo: 
G 
H 
The Arbitrator made the award on 22.1.1981 in respect of rlaim 
No. I therby directing the Respondents to pay 35 per cent increase in 
the agreed rate for the item of earth work. However claim regarding 
interest on delayed payment was disallowed. As regards the counter-
claim filed by the Respondent, the Arbitrator ordered that those issues 
will be considered separately and thus no award in respect thereof was 
made. The appellant thereupon filed O.P. ·(Arbitrator) 81 of 1981 
before the Sub-Judge Trivandrum for making the award a rule of the 
Court. 
398 
K.V. GEORGE v. SECY. TO. GOVT., WATER DEPTT. 
399 
The Responde_nts having raised objection to the making of the 
award a Rule of the Court, the Sub-Judge remitted the reference to the 
arbitrator by his order dated 18.8.81 for fresh consideration, as the 
arbitrator had failed to consider the couuter-claim made by the respon-
dent. The appellant applied for review of the said order passed by 
Sub-Judge. Contemporaneously, the ap_pellant filed another claim_,peti-
tion before the arbitrator (case No. 276of1980) in respect of the wrong-
ful termination of the contract and made claim in respect of 13 items. 
On 29th October 1981, the arbitrator made an award whereby he 
ordered that the re-arrangement of the work should not be at the risk 
and cost of the appellants. He also ordered 30% increase in rates for all 
items of work carried out by the appellant, except however those items, 
which stood covered by his earlier award. Some of the other claims were 
also allowed. The appellant tiled O.P. (Arbitrator) 296 of 1981 for 
making the second award a Rule of the Court to which the Respondents 
raised objections. The Sub-Judge by his order dated. March 18, 1982 
made the award a rule of the Court dismissing_ the plea of_ res-,judicata 
raised by the Respondents. The Respondents b~ing dissatisfied wit_h the 
order passed by Sub-Judge preferred two appeals before the Kerala 
High Court. The High Court allowed both the apeals holding that the 
Sub-Judge couid not review his order of the facts of the present case. 
The High Court also held that principle of constructive res-judicata 
would apply to the arbitration case. Accordingly the High Court set 
aside the orders of the Sub-Judge as also the award and directed that 
the arbitrator shall dispose of the Arbitration case No. 132 of 1980 
afresh in the light of the Judgment of Sub-Judge in O.P. (Arbitrator) 
No. 81 of 1981 and in accordance with Jaw after taking into considera-
tion the claim of the appellant and the counter claim of the Respon-
dents. Hence these appeals by the appellant by Special Le'!ve. 
Dismissing the appeals, this Court, 
HELD: It is the duty of the Arbitrator while considering the 
claims of the appellants to consider also the counter claims made on 
behalf of the Respondents and to make'the award after considerin

Excerpt shown. Read the full judgment & AI analysis in Lexace.