K.N. SATHYAPALAN (DEAD) BY LRS. versus STATE OF KERALA AND ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B K.N. SATHYAPALAN (DEAD) BY LRS. v. ST A TE OF KERALA AND ANR. NOVEMBER 30, 2006 [DR. AR. LAKSHMANAN AND ALT AMAS KABIR, JJ.] Arbitration Act, 1940-s.17-Non-completion of work within stipulated time-Ex_tension of time on co_ndition that contractor not eligible to escalation C costs for work done during extended period-Arbitrator allowing the claims on account of escalation costs-High Court setting aside the same holding that arbitrator had exceeded its jurisdiction in granting award-Justification of-Held, not justified as delay had occurred due to law and order problem at the work site which should have been avoided by the State Government. D The appellant entered into an agreement with the Respondent-State whereby it undertook the construction work. The whole work could not be completed on the scheduled dates and under clause 50 of the General Conditions of Contract extension of time was sought by the appellant. The respondents_ extended the time of completion but while doing so made it conditional that such extension of time would be subject to execution of a E Supplemental Agreement to the effect that the contractor would not be eligible for any enhanced rate for the work done during the extended period. The dispute arose and the matter was referred to the sole arbitrator. F Appellant raised claims under various heads. Arbitrator allowed some of the claims and awarded a sum of Rs. 42 lacs with 12% interest per annum on account of losses suffered by appellant due to interruption of work by anti social elements and failure of State in removing such miscreants from the sites causing heavy financial losses by way of idle men and machinery; price escalation of material that had taken place during G extended period of completion; failure of State to handover a suitable quarry which resulted in bringing rubble and metal from far off places involving additional transportation costs; and non-availability of a suitable dumping yard for dumping excess earth. H 864 K.N. SATHYAPALAN (DEAD) BY LRS. iยท. STATE OF KERALA 865 Appellant filed O.P. under S.17 of Arbitration Act for passing a decree A in terms of the award. The Respondent-State filed petition under S.30 which was dismisse~ On appeal, High Court set aside the award holding that the Arbitrator had exceeded its jurisdiction in granting the award. Hence the present appeal. Allowing the appeal, the Court HELD: 1.1. Admittedly, the original Agreement did not contain a clause for escalation of rates. On the other hand, the Supplemental Agreement contained a specific provision that the contractor would not claim any enhanced B rate for such item of work on account of the extension of time either due to C the increase in the rate of labour or materials or on any other ground whatsoever. Ordinarily, the parties would be bound by the terms agreed upon in the contract, but in the event one of the parties to the contract is unable to fulfil its obligations under the contract which has a direct bearing on the work to be executed by the other party, the Arbitrator is vested with the authority to compensate the second party for the extra costs incurred by him D as a result of the failure of the first party to live up to its obligations. (870-G, H; 874-E-F) P.M Paul v. Union of India, (19891 Supp. 1 SCC 368; T.P. George v. State of Kera/a and Anr., [20.!H I 2. S~C 758; Mis. Alopi Parshad & Sons Limited v. The Union of India, [1960) 2 SCR 793 and State of U.P. v. Patel E Engg. Co. ltd. and Ors., (2004) 10 SCC 566, referred to. 1.2. The appellant was prevented by unforeseen circumstances from completing the work within the stipulated period of eleven months. Such delay could have been prevented had the State Government stepped in F to maintain the law and order problem which had been created at the work site. It is also clear that the rubble and metal, which should have been available at the departmental quarry had to be obtained from ยทquarries which were situated at double the distance, and even more, . resulting in doubling of the transportation charges. Even the space for dumping of excess earth was not provided by the respondents which G compelled the appellant t-0 dump the excess earth at a place which was far away from the work site entailing extra costs for the same. (875-B-C) 2. In the aforesaid circumstances, the Arbitrator appears to have acted within his jurisdiction in allowing some of the claims o
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex