JAN DE NUL DREDGING INDIA PVT. LTD. versus TUTICORIN PORT TRUST
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2026] 2 S.C.R. 86 : 2026 INSC 34 Jan De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust (Civil Appeal No. 98 of 2026) 07 January 2026 [Pamidighantam Sri Narasimha and Pankaj Mithal,* JJ.] Issue for Consideration Whether the Division Bench of the High Court in exercise of powers u/s.37 of the Arbitration and Conciliation Act, 1996 was justified to interfere with the judgment and order of the Single Judge of the High Court passed u/s.34 of the Arbitration and Conciliation Act, 1996 upholding the award of the Arbitral Tribunal. Headnotesβ Arbitration and Conciliation Act, 1996 β Major Port Trust Act, 1963 β The respondent-Tuticorin Port Trust undertook a major dredging project and issued Notice Inviting Tender β The appellant-Dredging India was one of the bidders and the contract was awarded to it β The appellant-Dredging India completed work project much ahead of schedule β Disputes arose between the parties relating to alleged non-payment and under-payment of dues as raised under the final bill β Arbitration clause was invoked by the the appellant-Dredging India β The Arbitral Tribunal vide its award dated 18.10.2014 inter alia awarded an amount of Rs.14,66,04,216/- β The arbitral award was challenged by the respondent-Port Trust u/s.34 of the 1996 Act β The award of the Arbitral Tribunal was upheld by the Single Judge of the High Court β However, the High Court directed for the deletion of the claim awarded by the Arbitral Tribunal in respect of Claim No.7 i.e. idle charges for the Backhoe Dredger (BHD) β Correctness: Held: In the instant case, the power to award compensation for idle time of the equipment including Backhoe Dredger is traceable to Clause 51.1 of the Lease Agreement and therefore the Arbitral Tribunal was not wrong in interpreting the clauses so as to make an award in favour of the appellant-Dredging India under Claim No.7 β *βAuthor [2026] 2 S.C.R. 87 Jan De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust In such a situation, the interpretation given by the Arbitral Tribunal is apparently a plausible view and was rightly not disturbed by the Single Judge in exercise of power u/s.34 of the Act β Therefore, in appeal u/s.37 of the Act, the said reasoning could not have been disturbed so as to permit a different view β The interpretation given by the Arbitral Tribunal had to be accepted by the Appellate CourtΒ β In the case at hand, the Arbitral Award contains logical reasons in construing the various clauses of the License Agreement and the view taken by the Arbitral Tribunal had been accepted by the court u/s.34 of the Act as a reasonable and a possible view β The License Agreement permits deployment of Backhoe Dredger (BHD) without specifying whether it is a minor or a major dredger β This Court is of the opinion that the Appellate Court manifestly erred in law in interfering with the judgment and order of the Single Judge of the High Court passed u/s.34 of the Act so as to disturb the arbitral award in respect of Claim No.7. [Paras 46, 48, 49, 50] Arbitration and Conciliation Act, 1996 β s.34 β Whether the Challenge to the award, in the instant case was on any of the grounds enumerated u/s.34 or on the ground that the award of the Claim No.7 is against the fundamental policy of India or the basic notions of morality or justice: Held: In the case at hand, a challenge to the award of the Arbitral Tribunal before the Single Judge of the High Court would reveal that it was confined to Claim No.7 and that too on the merits of the same and not on the ground of violation of the public policy of India or that it is against the basic notions of morality or justiceΒ β The Arbitral Tribunal, in making the award, has interpreted the various clauses of the License Agreement so as to hold that the appellant-Dredging India is entitled for appropriate compensation with regard to idling of its Backhoe Dredger (BHD) for want of non-supply of site within time β Apparently, the challenge to the award of the Arbitral Tribunal was neither on any of the grounds enumerated u/s.34, nor even on the ground that the award of the Claim No.7 is against the fundamental policy of India or the basic notions of morality or justice β That being the position, the award of the Arbitral Tribunal was not liable to be disturbed u/s.34 of the Act and was rightly not disturbed β It is settled in law that the appellate powers u/s.37 are limited to the scope of s.34 and
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex