INDSIL HYDRO POWER & MANGANESE LTD. versus STATE OF KERALA & ORS ETC
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 647 INDSIL HYDRO POWER & MANGANESE LTD. v. STATE OF KERALA & ORS ETC. (Civil Appeal Nos. 5943-5945 of 2019) JULY 30, 2019 [DR. DHANANJAYA Y CHANDRACHUD AND INDIRA BANERJEE, JJ.] Electricity : Pursuant to the policy decision of State Government to allow the private agencies to set up hydel schemes, the appellant was allowed to set up a Hydro Electric Project – MoU was executed between the appellant and the KSEB – In terms of the MoU, the appellant would operate the unit for 30 years from the date of commissioning i.e. the date from which the power generated by the appellant is fed into the KSEB grid – The MoU contemplated that the transmission line required for transferring power from the power house to the nearest grid sub-station upto a length of 4 Kms. would be built by KSEB at the cost of the appellant and rest of the transmission line was to be constructed by the KSEB at its own cost – Delay in construction of transmission line led to institution of writ petition by appellant before High Court wherein appellant claimed power free of cost in terms of clause 9 and 10 of the agreement and sought direction for expeditious construction of transmission line – Pursuant to interim order, the Chief Electrical Inspector filed a report to the effect that the installation of transformers was completed by the appellant on 21 August 2000 but the sanction for energization of 110 KV was not issued since the transmission lines were not ready – High Court directed the State Government to deal with the representations submitted by the appellant – Pursuant to order of High Court, State Government passed order on 7 February 2001 opining inter alia that appellant was not entitled to the benefit of the pre 1992 tariff concession till the completion of the transmission line by KSEB; that the delay in the construction of the transmission lines was not deliberate and was due to factors beyond control; that the tariff concessions were provided to new industries which is a distinct issue from captive power generation and hence the plea [2019] 10 S.C.R. 647 647 A B C D E F G H 648 SUPREME COURT REPORTS [2019] 10 S.C.R. for a tariff concession could not be acceded to; and having regard to the grievance of the appellant that it had been unable to evacuate the power which it was positioned to generate for its captive unit, KSEB ought to adhere to the time schedule which it had undertaken to fulfill and complete the construction of the transmission lines by 28 February 2001 without fail – High Court dismissed the writ petition eventually holding that there was no intentional delay in construction of the transmission lines on the part of KSEB; that the tariff concession was made available only to new industries; and that the agreement between the parties did not disclose any specified time limit for the provision of transmission lines – On appeal, held: The agreement stipulated that the date of commissioning would be construed as the date from which the power generated by the units set up by the appellant was fed into KSEB grid – Though the contract did not specify the exact length of the transmission line, clause 9 made it clear that for a length of 4 kms, construction would be at the cost and expense of the appellant while the balance would be constructed by KSEB at its own cost – Clause 3 postulated that commercial operations would begin within a period of 30 months – Thus, the only reasonable construction of the contract would be that the obligations which were to be performed by KSEB, namely, the construction of the transmission line must necessarily be completed within the same period – Otherwise imposing an obligation upon the appellant to commence commercial operations within 30 months would have no meaning – Therefore, High Court was not correct in holding that the contract did not stipulate any timelines for the completion of the work of constructing the transmission line – Clause 12 of the agreement contemplated a situation where the KSEB grid is not in a position to absorb the energy generated from the project for any reason including the breakdown of transmission lines or any other reason beyond the control of KSEB – In that event, clause 12 provided the generation from the project to be restricted to the extent of generation for captive consumption as directed by KSEB – These provisions indicated that the contract was not entirely silent in regard to a situation involving the inability of KSEB’s grid to absorb t
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex