LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

HINDUSTAN PETROLEUM CORPORATION LTD. versus BCL SECURE PREMISES PVT. LTD.

Citation: [2025] 12 S.C.R. 455 · Decided: 09-12-2025 · Supreme Court of India · Bench: J.B. PARDIWALA · Disposal: Appeal(s) allowed

cites 7 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 12 S.C.R. 455 : 2025 INSC 1401
Hindustan Petroleum Corporation Ltd. 
v. 
BCL Secure Premises Pvt. Ltd.
(Civil Appeal No. 14647 of 2025)
09 December 2025
[J.B. Pardiwala and K.V. Viswanathan,* JJ.]
Issue for Consideration
Issue arose whether the High Court, was justified in referring 
the parties to arbitration by allowing the petition u/s.11(4) of the 
Arbitration and Conciliation Act, 1996.
Headnotes†
Arbitration and Conciliation Act, 1996 – Appointment of 
arbitrators – Appellant-Corporation floated a tender and 
issued a purchase order in favour of the contractor-successful 
tenderer – Tender prohibited sub-letting, sub-contracting 
without the prior consent of the owner obtained in writing – 
Appellant issued notice to the contractor with regard to 
non-functioning and unsatisfactory performance – Later, the 
respondent informed the appellant that they were working 
as sub-vendor of the contractor and were entitled to receive 
94% of the payment due – Appellant informed respondent 
that the appellant had not entered into any contract with the 
respondent and as such no payments due to the respondent 
from the appellant – Thereafter, series of proceedings between 
them – Respondent issued notice to the appellant invoking 
arbitration – Resolution of disputes between the respondent 
and the contractor, Settlement-cum-Assignment Agreement 
signed, to assign the receivables of contractor against the 
appellant to the respondent – Respondent then raised claim 
which was denied by the appellant – Respondent filed petition 
u/s.11(4) – High Court allowed application and appointed an 
arbitrator to adjudicate upon the disputes and differences 
between the parties – Justification:
Held: Referral court should be prima facie satisfied that there exists 
an arbitration agreement and as to whether the non-signatory is a 
veritable party – Even if the referral court prima facie arrives at the 
* Author
456
[2025] 12 S.C.R.
Supreme Court Reports
satisfaction that the non- signatory is a veritable party, the arbitral 
tribunal is not denuded of its jurisdiction to decide whether the non- 
signatory is indeed a party to the arbitration agreement on the basis 
of factual evidence and application of legal doctrine – Appellant 
has no privity at all with the respondent – To the documentation 
between the contractor and the respondent, the appellant was 
not a party – Appellant and the respondent have been operating 
on separate orbits – Not been established even prima facie that 
there was any intention to bind respondent to the contract between 
appellant and contractor – Respondent not shown any consent for 
assignment as required under the clause of the tender document – 
Nothing even prima facie shown to establish that there was any 
semblance of an intent to effect legal relationship between the 
respondent and the party originally granting the contract and/or to 
indicate that the respondent was a veritable party – Applying the 
consensual theory or the non-consensual theory, the respondent 
not established its case to show even prima facie the existence of 
an arbitration agreement between appellant and the respondent – 
Settlement-cum-Assignment Agreement between contractor and 
respondent have been perused and under the clause, the contractor 
has represented and warranted that any amount/receivables 
accruing to the contractor as a result of litigation/proceeding 
initiated by respondent against the appellant was to be transferred 
to respondent – This does not mean that there is an arbitration 
agreement existing between the appellant and respondent or 
that respondent was a veritable party to the agreement between 
appellant and contractor – Respondent fails the prima facie test 
of being a veritable party to the arbitration agreement between 
the appellant and the contractor – Non-existence of an arbitration 
agreement between the parties – Thus, the judgment and order 
passed by the High Court set aside. [Paras 24, 30-32, 36, 38, 
40, 42, 43]
Case Law Cited
Cox and Kings Limited v. Sap India Private Limited and Another 
[2023] 15 SCR 621 : (2024) 4 SCC 1; In Re: Interplay Between 
Arbitration Agreements under Arbitration and Conciliation Act, 
1996 & Stamp Act, 1899 [2023] 15 SCR 1081 : (2024) 6 SCC 
1; SBI General Insurance Company Limited v. Krish Spinning 
[2024] 7 SCR 840 : (2024) 12 SCC 1; Ajay Madhusudan Patel 
and Others v. Jyotrindra S. Patel and Others [2024] 9 SCR 894 : 
[2025] 12 S.C.R. 
457
Hindust

Excerpt shown. Read the full judgment & AI analysis in Lexace.