GUJARAT ELECTRICITY BOARD versus AHMEDABAD ELECTRICITY CO. LTD. & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
492
GUJARAT ELECTRICITY BOARD
v.
AHMEDABAD ELECTRICITY CO. LTD. & ORS.
November 28, 1973
[D. G. PALEKAR, V. R. KRISHNA ]YER AND R. S. SARKARIA, JJ.]
Electricity Supply Act, 1948. Ss. 51A, 60(1), 76 (I) and (2) and Para 16of Sch. 6-
Reference by licensee of dispure between it and Electricity Board to arbitration of
Central Electricity Authol'ity-Jf operates as bar ro appointment of Rating Committee
by Board.
In September 1963 the respondent company intimated to the appellant-Board
and the State Governmfnt of its intention to revise the rates of electricity on certain
grounds. Both the State Government and the Board informed the respondent th3t
they were not satisfied , that there was any justification for the revision. The res-
pondent, however, brought the rates into effect in November, 1963. Being of the
view that the ITSpondent'was over charging the consumers in breach of the provisions
of the 6th Schedule to the Electricity Supply Act, the appellant issued a notice to show
cause why a Rating Coirimittee under s. 57A should not be constituted for inquiring
into .the matter. The respondent justified the increase and also intimated that if
its explanation was not accepted the issues involved would be referred to the ar-
bitration of the Central. Electricity Authority under para 16 of the Schedule read
with s. 76 of the Act.
As the respondent did not receive any intimation, it referred
the matter to the arbittation of the Central Electricity Authority. The appellant,
however, not being satisfied with the explanation given to the show cause notice
appointed a Rating Coi;nmittee.
On a petition filed' by the respondent, the High Court held that a dispute or
difference between the Soard and the Electricity Company which was referable to
the arbitration of the Authority under para 16 of the 6th Schedule had arisen, and
since pending such arbitration, no Rating Committee could be constituted because
of the second proviso to s. 57A the constitution of the Rating Committee by the
appellant was illegal and the Committee had no power to function.
Allowing the appeal to this Court,
HELD : There is no provision in the Act which makes a dispute between the
Board and the licensee as to whether the provisions of the 6th Schedule had been
complied with or not referable to the Central Electricity Authority,
The second
proviso to s. 57A does not contemplate holding up of the constitution of the Rating
Committee merely on' the ground that such a dispute was referred by the licensee to
B
c
()
E
the Authority. [504 C-EJ
F
(a) Under s. 57A the State Electricity Board has power to interfere by the ap-
pointment of a Rating Committee if it is satisfied that the licensee has over charged
the consumers by committing a breach of any of the financial principles mentioned
in the 6th Schedule. The second proviso to the section contains three conditions
which are to coexist, if the Rating Committee was not to be constituted by the Board:
{i) there should be an alleged failure of the licensee to comply with any provisions
of the 6th Schedule; (ii) such alleged failure niust raise a dispute or difference as to
the interpretation of the said provisions or any matter arising therefrom; and (iii)
G
and such difference or dispute had been referred by the licensee to the arbitration of
the Authority tJnder,para 16 of that Schedule before a certain date. [497 H-498 B;
501 CยทE; 502 FJ
In the present case, there is an allegation by the appellant Board that the licensee
had failed to comply with the provisions of the 6th Schedule. It could also be
assumed that the alleged failure raised a dispute or difference as to the interpretation
of the said provisions or any matter arising therefron;i, though it is not clear whether
Parliament wanted, for.purposes ofs. 57A and para 16 of the 6th Schedule, that the
Ii
Authority should be approached not merely for the interpretation of the provisions
of the 6th Schedule but also for sundry matters of detail arising out of the provisions.
As regards the third condition the dispute had been referred by the licensee to the
arbitration of the Authority within the time allowed by the statute, but it was not a
A
D
c
D
E
F
G
GUJARAT ELEC. BOARD V โข . AHMEDABAD ELEC, CO. LTD.
493
(Palekar, l.)
reference under para 16 of the Schedule, because, the reference to arbitration by the
Authority under that paragraph could be made by the licensee only against the
gExcerpt shown. Read the full judgment & AI analysis in Lexace.
Lex