GRID CORPORATION OF ORISSA LIMITED versus INDIAN CHARGE CHROME LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
GRID CORPORATION OF ORI SSA LIMITED A v. INDIAN CHARGE CHROME LIMITED MAY 13, 1998 [G.T. NANA VA Tl AND S.P. KURDUKAR, JJ.] B Arbitration & Conciliation Act, 1996-Section I I-Maintainability of Application under-Proceedings before Regulatory Commission under Orissa Electricity Reform Act, 1995-0ne of the parties later applying under Section C 11 of the Arbitration Act before the High Court-Proceeding before the Regulatory Commission adjourned by it on an application filed by the party approaching High Court under Section 11 of the Arbitration Act-High Court on erroneous assumption that Regulatory Commission has failed to arbitrate under Section 37(1) of the Reform Act, entertained the application under Section I I-Held, application under Section 11 was premature and D High Court exceeded its jurisdiction in entertaining the same-Orissa Electricity Reform Act, 1995, Section 37(1). Orissa Electricity Reform Act, 1995-Sections 37(1), 33, 2(e) and (j) and 14-Arbitrability of dispute-Licensee-Respondent was authorised! engaged in supplying electricity through its captive power plant to Electricity E Board and later to appellant, its successor-No formal licence issued to respondent under the Electricity Act or under the Reform Act-Held, High court erred in taking the view that the respondent was licensee under the Section 2(h) of Electricity Act and continued to be the same even after coming into force of the Reform Act-Hence the dispute was arbitrable under F Section37(1) read with Section 33 of the Reform Act-Electricity Act, 1910, Section 2(h). Electricity Act, 1910-Section 24-Notice for payment of arrears of electricity bill or else power supply would be disconnected-Application for injunction-Held, injunction orders could be passed only if prima facie case G existed and balance of convenience in favour of the party-Financial constraint cannot be a ground to allow the party to use power without ; charges-However, instalments fixed for payment of undisputed outstanding arrears-Arbitration & Conciliation Act, 1996, Section 9-Civil Procedure Code, 1908, Order 39, Rules 1& 2. H 375 376 SUPREME COURT REPORTS [1998] 3 S.C.R. A Respondent set up a Captive Power Plant in 1989 after due permission from the state for supplying power to its sister concerns IMFA and PPL and surplus power to State Electricity Board (OSEB) and accordingly an agreement was signed between the respondent and the OSEB. This arrangement continued until a MOU of 1994 followed by an agreement of 1995 signed between the respondent and OSEB. Under the MOU of 1994 the B power supplied by the respondent to OSEB was charged at 77 paise per unit and a wheeling charge@ 15% Appellant became the successor of OSEB in 1996. Appellant thereafter called upon respondent to pay outstanding dues for the pehod December 1994 to December 1996 amounting to Rs. 24.8281 crores. DJring this period the OSEB and thereafter appellant had been C wheeling/supplying power to respondent. Respondent filed an application before the Regulatory Commission in February 1997 constituted under the Orissa Electricity Reform Act raising a dispute as regard bill amounts and its liability to pay to appellant In April 1997 appellant informed respondent that unless the arrears are paid, they D would be compelled to discontinue the power supply in accordance with law. When no payment was, made the appellant issued another notice under Section 24(1) of the Electricity Act calling upon the respondent to pay the arrears within seven days or else face disconnection. The respondent on the contrary moved a petition under Section 9 of the Arbitration & Conciliation Act iii the Court of District Judge for relief of injunction which was granted E by it ex-parte. Appellant thereafter filed an appeal before the High Court which stayed the operation of the order of the District Judge. However the High Court recalled its earlier Order and directed the appellant to restore the supply which was disconnected subject to the condition that 5 crores would be deposited out of the total areas. Aggrieved by that order of the High F Court, an SLP was filed before this Court which confirmed the order of the ยท High Court but granted facility to make the payment in two instalments. In the meantime the Regulatory Commission asked respondent to clarify as to how its petition could be treated as reference under Section 37(1) of the Reform Act since it was
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex