G H SOUTH EAST ASIA MARINE ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.) versus OIL INDIA LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 254 SUPREME COURT REPORTS [2020] 4 S.C.R. SOUTH EAST ASIA MARINE ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.) v. OIL INDIA LIMITED (Civil Appeal No. 673 of 2012) MAY 11, 2020 [N. V. RAMANA, M. M. SHANTANAGOUDAR AND AJAY RASTOGI, JJ.] Contract: Tender floated for well drilling and other auxillary operations โ Work order awarded to appellant โ During subsistence of contract, prices of High Speed Diesel (HSD) one of the essential materials for carrying out the drilling operations increased through a circular issued by Government โ Appellant raised a claim that increase in the price of HSD triggered the โchange in lawโ clause contained in clause 23 under the contract and the respondent became liable to reimburse them for the same โ In terms of Clause 23, if subsequent to the date of price of Bid Opening, there was a change in or enactment of any law or interpretation of existing law, which resulted in additional cost/reduction in cost to contractor on account of the operation under the contract, the contractor would be entitled to receive such additional/reduced cost actually incurred โ Appellant invoked the arbitration clause โ Arbitral Tribunal allowed the claim holding that Clause 23 must be liberally construed and any circular of the Government would amount to a change in law โ On appeal, High Court set aside the award โ Held: There are price fluctuations which a prudent contractor would take into margin, while bidding in the tender โ Such price fluctuations cannot be brought under โchange in lawโ clause unless specific language points to the inclusion โ The contract in question was based on a fixed rate โ The party, before entering the tender process, entered the contract after mitigating the risk of such an increase โ The interpretation of Arbitral Tribunal to expand the meaning of Clause 23 to include change in rate of HSD was not a possible interpretation of this contract as the appellant did not introduce any evidence to prove same โ Arbitral award set aside โ Contract Act โ s.56 โ Arbitration and Conciliation Act, 1996 โ s.34 โ Doctrine of Force Majeure. 254 [2020] 4 S.C.R. 254 A B C D E F G H 255 Arbitration and Conciliation Act, 1996: s.34 โ Scope of courtโs jurisdiction under s.34, discussed. Dismissing the appeals, the Court HELD: 1. It is settled position that a Court can set aside the award only on the grounds as provided in the Arbitration Act as interpreted by the Courts. It is also settled law that where two views are possible, the Court cannot interfere with the plausible view taken by the arbitrator supported by reasoning. [Paras 12, 13][260-G-H; 261-D] 2. The interpretation of the โchange in lawโ clause of the contract by the Arbitral Tribunal, to provide a wide interpretation, cannot be accepted, as the thumb rule of interpretation is that the document forming a written contract should be read as a whole and so far as possible as mutually explanatory. In the case at hand, this basic rule was ignored by the Tribunal while interpreting the clause. In this case, the contract was based on a fixed rate basis. The party, before entering the tender process, entered the contract after mitigating the risk of a price increase. If the purpose of the tender was to limit the risks of price variations, then the interpretation placed by the Arbitral Tribunal cannot be said to be possible one, as it would completely defeat the explicit wordings and purpose of the contract. The interpretation of the Arbitral Tribunal to expand the meaning of the โchange in lawโ clause of the contract to include change in price of HSD is not a possible interpretation of this contract, as the appellant did not introduce any evidence which proves the same. [Paras 28, 30 and 31][267-A, D-F] Sumitomo Heavy Industries Limited v. Oil and Natural Gas Corporation Limited (2010) 11 SCC 296 : [2010] 9 SCR 176 โ Held inapplicable. Satyabrata Ghose v. Mugneeram Bangur & Co. AIR 1954 SC 44 : [1954] SCR 310; Mcdermott International Inc. v. Burn Standard Co. Ltd. (2006) 11 SCC 181 : [2006] 2 Suppl. SCR 409; Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd. (2019) SCC Online SC 1656 โ referred to. SOUTH EAST ASIA MARINE ENGINEERING AND CONSTRUCTIONS LTD. (SEAMEC LTD.) v. OIL INDIA LTD. A B C D E F G H 256 SUPREME COURT REPORTS [2020] 4 S.C.R. Chandler v. Webster [1904] 1 KB 493; Fibrosa Spolka Akcyjna v. Fairbairn Lawson Combe Barbour Ltd; [1942] UKHL 4; Cantiare San Rocco SA (Shipbuilding Company) v. Clyde Shipbuilding and E
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex