FOOD CORPORATION OF INDIA versus SURENDRA, DEVENDRA & MOHENDRA TRANSPORT CO.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
FOOD CORPORATION OF INDIA
v.
~ •
SURENDRA, DEVENDRA & MOHENDRA TRANSPORT CO.
DECEMBER 10, 1987
ISABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.J
Arbitration Act, 1940--Challenge to award of the arbitration
under section 30, 33-0f.
The respondent was appointed a transport and handling Con-
tractor by the appellant subject to the terms and conditions mentioned
in three successive written agreements entered into by both the parties.
After disputes arose between the parties, an arbitrator was appointed
as per the arbitration clause to adjudicate upon the disputes. The
arbitrator made and published an award which was a speaking one. He
did not allow the appellant's claim for demurrage and wharfage
charges paid to the Railways amounting to Rs.15,63,863.02 by reason
of the alleged wrongful conduct of the respondent but awarded only
25% of the claim. The arbitrator also did not allo~ the appellant's claim
for shortage in transit but reduced the claim by 40% and allowed only
60% of it amounting to Rs.52,971.99. The arbitrator awarded to the
respondent Rs.12,64,175.97 and pendente lite interest at 6% per
annum.
The appellant filed objections in the High Court under sections 30
A
B
c
D
E
and 33 of the Arbitration Act, 1940 ('The Act') for setting aside the
award. The High Court (Single Judge) set aside the award. The respon-
dent filed an appeal to the Division Bench of the High Court which
allowed the same, setting aside the judgment of the learned single judge
F
and upholding the award. Being aggrieved by the dicision of the High
Court, the appellant appealed to this Court for relief by special leave
under Article 136 of the Constitution.
Disposing of the appeal, this Court,
HELD: While issuing noiice on the application under Article 136
of the Constitution, it was indicated that only three questions would be
adjudicated upon in this appeal, viz, Rs.13,94,982.46 being the amonnt
allowed on account of demurrage and wharfage charges mentioned in
the award, secondly, the sum of Rs.2,35, 769.46 and lastly, the question
of interest. l332G I
329
G
H
330
SUPREME COURT REPORTS
[ 1988] 2 S.C.R.
A
So far as the second question was concerned, counsel for the
appellant did not make any submission before the Court. The Court also
could not find any substance in this aspect. Therefore, it was not neces-
sary to deal with this aspect of the matter. [332H; 333A)
So far as the amount ofRs.13,94,982.46 on account ofdemurrage
B and wharfage was concerned, which was allowed, it appeared that the
total demurrage and wharfage charges paid by the Corporation to the
Railways in respect of the wagons cleared by the claimant firm, respon-
dent herein, after obtaining such waiver as the Railways were per-
suaded to make were Rs.15,63,863.21. There was no dispute about the
actual payment of the charges. The appellant's case was that it was
C entitled to recover the entire amount it had to pay on account of the
demurrage and wharfage charges from the respondent under clause
9(a) of the agreement. [333B-C]
Under clause 9(a) according to the appellant, the Agent was liable
to make good any compeusatiou/demurrage/wharfage as per Railway
D rates in force during the period of contract and other charges or ex-
penses that might be incurred hy the Corporation on account of delay in
loading/unloading of trucks/carts and unloading/loading of wagons un·
less the delay was for reasons beyond the Agent's control. It appeared
lh11t the appellant had periodically served notices upon the respondent·
firm calling upon it to pay demurrage and wharfage charges with liberty
E to prefer objections. Such objections·as the respondent-firm preferred
were disposed of by the District Manager. This procedure continued till
the end of November, 1975. Then the respondent-firm went to the Civil
Court and obtained discontinuance of all proceedings for the recovery of
demurrage and wharfage charges. The arbitrator noted that as a result
of the hearings by the Corporation npto November, 1975, relief to the
F tune of Rs.1,21,884.55 was granted to the respondent-firm and the
recovery of Rs.45,996.20 was made from the respondent-firm's bills.
The Corporation, therefore, claimed before the arbitrator recovery of
the remaining or the claim of Rs.13,94,982.46. Counsel for the appel-
lant drew this Court's attention to clauses 9(a) and (b) of the agreement
and submitted that the adjudication made by the Manager was final Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex