LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

EVERGREEN LAND MARK PVT. LTD versus JOHN TINSON & COMPANY PVT. LTD. & ANR

Citation: [2022] 4 S.C.R. 879 · Decided: 19-04-2022 · Supreme Court of India · Bench: M.R. SHAH · Disposal: Case Partly allowed

cites 2 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2022] 4 S.C.R. 879
879
EVERGREEN LAND MARK PVT. LTD.
v.
JOHN TINSON & COMPANY PVT. LTD. & ANR.
(Civil Appeal No. 2783 of 2022)
APRIL 19, 2022.
[M. R. SHAH AND B. V. NAGARATHNA, JJ.]
Arbitration and Conciliation Act, 1996: ss.17, 37(2)(b) –
Appellant was lessee in the premises of respondent no.1 and 2 and
was running a Restaurant and Bar in the said premises – Lease
agreement terminated by the owners, as a consequence of which,
dispute arose and the same referred for arbitration – During
pendency of dispute, owners made applications seeking deposit of
rental amount – Lessee sought to invoke the force majeure clause
in light of outbreak of Covid-19 pandemic – Arbitral Tribunal
allowed the application of the owners in exercise of the power u/
s.17 of the Act – High Court upheld the same – On appeal, held:
Applicability of the force majeure principle contained in clause 29
is yet to be considered by the Arbitral Tribunal – Therefore, no
order could have been passed by the Tribunal by way of interim
measure on the applications filed u/s.17 of the Arbitration Act since
there was serious dispute with respect to the liability of the rental
amounts to be paid – As the applicability of force majeure principle
(clause 29) is yet to be considered at least, for the period during
the complete closure, it would not be justified to direct the lessee to
deposit the rental amount for the said period of complete closure by
way of an interim measure, pending final adjudication – Contract,
principle of – Force majeure principle.
Partly allowing the appeal, the Court
HELD: 1. The dispute is with respect to the rental amount
for the period between March, 2020 to December, 2021, for which
the Arbitral Tribunal has directed the appellant to deposit while
passing the order by way of an interim measure on the applications
under Section 17 of the Arbitration Act. The liability to pay the
lease rental for the period between March, 2020 to December,
2021 is seriously disputed by the appellant by invoking the force
majeure principle contained in clause 29 of the lease agreement.
A
B
C
D
E
F
G
H
880
SUPREME COURT REPORTS
[2022] 4 S.C.R.
It is the case on behalf of the appellant that for a substantial period
there was a total closure due to lockdown and for the remaining
period the appellant was allowed with 50% capacity and therefore,
the force majeure principle contained in clause 29 shall be
applicable. When the same was submitted before the Arbitral
Tribunal, no opinion, not even a prima facie opinion on the
aforesaid aspect was given by the Arbitral Tribunal. Therefore,
applicability of the force majeure principle contained in clause 29
is yet to be considered by the Arbitral Tribunal. Therefore, no
order could have been passed by the Tribunal by way of interim
measure on the applications filed under Section 17 of the
Arbitration Act in a case where there is a serious dispute with
respect to the liability of the rental amounts to be paid, which is
yet to be adjudicated upon and/or considered by the Arbitral
Tribunal. Thus, no such order for deposit by way of an interim
measure on applications under Section 17 of the Arbitration Act
could have been passed by the Tribunal. However, at the same
time, the aforesaid can be considered only for the period of
complete closure due to lockdown. As per the available record,
there was complete closure for the period between 22.03.2020
to 09.09.2020; for the period between 19.04.2021 to 28.06.2021
and for the period between 11.01.2022 to 27.01.2022 and for the
remaining period the appellant was allowed to run the Restro/
Bar with 50% capacity. The appellant will therefore have to
deposit the entire rental amount except the period for which there
was complete closure due to lockdown. As the applicability of
force majeure principle (clause 29) is yet to be considered at
least, for the period during the complete closure, it would not be
justified to direct the appellant to deposit the rental amount for
the said period of complete closure by way of an interim measure,
pending final adjudication. [Para 6][885-F-H; 886-A-F]
Raman Tech. Process Engg. Co. & Anr. v. Solanki
Traders (2008) 2 SCC 302: [2007] 12 SCR 409;
Adhunik Steels Ltd. v. Orissa Manganese and Minerals
(P) Ltd. (2007) 7 SCC 125 : [2007] 8 SCR 213
– referred to.
A
B
C
D
E
F
G
H
881
Case Law Reference
[2007] 12 SCR 409
referred to
Para 3.1
[2007] 8 SCR 213
referred to
Para 3.1
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2783
of 2022.
From the Jud

Excerpt shown. Read the full judgment & AI analysis in Lexace.