LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

ENERCON (INDIA) LTD. & ORS. versus ENERCON GMBH & ANR.

Citation: [2014] 2 S.C.R. 855 · Decided: 14-02-2014 · Supreme Court of India · Bench: S.S. NIJJAR · Disposal: Disposed off

Cited by 15 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2014] 2 S.C.R. 855 
ENERCON (INDIA) LTD. & ORS. 
V. 
ENERCON GMBH & ANR. 
(Civil Appeal No. 2086 of 2014 etc.) 
FEBRUARY 14, 2014 
[SURINDER SINGH NIJJAR AND FAKKIR MOHAMED 
IBRAHIM KALIFULLA, JJ.] 
ARBITRATION AND CONCILIATION ACT, 1996: 
s.45 rlw s. 16 - International Commercil Arbitration - Suit 
for declaration that Intellectual Property Licence Agreement 
(IPLA) was not concluded contract and coffespondingly there 
was no arbitration agreement therein - Application by 
respondent uls 45 - Held: parties have iffevocably agreed to 
resolve all the disputes through arbitration - Parties can not 
A 
B 
c 
D 
be permitted to avoid arbitration, without satisfying the court 
that it would be just and in the interest of all the parties not to 
proceed with arbitration - Findings recorded by appellate 
court that the parties can proceed to arbitration are affirmed -
Findings recorded by trial court dismissing the application ul 
E 
s 45 are set aside -- Application filed by respondents for 
reference of the dispute to arbitration u/s 45 has been 
correctly allowed by appellate court as well as by High Court 
- Issue as to whether there is a concluded contract between 
the parties can be left to arbitral tribunal - All the disputes 
arising between the parties in relation to the following 
agreements viz. SHA, TKHA, SSHAs and STKHA, Agreed 
Principles and IPLA, including the controversy as to whether 
IPLA is a concluded contract are referred to arbitral tribunal 
for adjudication -Third arbitrator who shall act as Chairman 
of Arbitral Tribunal, is appointed -- Arbitration clause 
(agreement) is independent of the underlying contract, i.e. the 
IPLA containing the arbitration clause -- s.16 provides that 
arbitration clause forming part of a contract shall be treated 
855 
F 
G 
H 
856 
SUPREME COURT REPORTS 
[2014] 2 S .. C.R. 
A as an agreement independent of such a contract --
UNCITRAL Model Law. 
s. 16 - Separability of arbitration clause from underlying 
contract - Held: Concept of separability of the arbitration 
8 clause/agreement from the underlying contract is a necessity 
to ensure that the intention of parties to resolve disputes by 
arbitration does not get frustrated with every challenge to 
legality, validity, finality or breach of the underlying contract -
The Act, u/s 16 accepts the concept that the main contract 
and the arbitration agreement form two independent contracts 
C - Therefore, it cannot be accepted that Arbitration Agreement 
will perish as the IPLA has not been finalised - Rule of 
necessity. 
Arbitration clause - Seemingly unworkable arbitration 
D clause - Held: It would be the duty of court to make the same 
workable within the permissible limits of law - A common 
sense approach has to be adopted to give effect to the 
intention of parties to arbitrate - Arbitration clause cannot be 
construed with a purely legalistic mindset, as if one is 
E construing a provision in a statute - In the instant case, the 
arbitration clause as it stands cannot be frustrated on the 
ground that it is unworkable - Unworkability in the case is 
attributed only to the machinery provision - Arbitration 
agreement, otherwise, fulfils the criteria laid down u/s 44 of the 
F Act - Given that two arbitrators have been appointed, the 
missing line that "the two arbitrators appointed by the parties 
shall appoint the third arbitrator" can be read into the 
arbitration clause - Omission is so obvious that the court can 
legitimately supply the missing line - In the circumstances, 
G the Court would apply the officious bystander principle -
Parties can be permitted to proced to arbitration. 
H 
'Seat' of arbitration and 'venue' -- International 
Commercial Arbitration -
Held: In an International 
Commercial Arbitration, venue can often be different from the. 
ENERCON (INDIA) LTD. & ORS. v. ENERCON GMBH 857 
& ANR. 
seat of arbitration - In the instant case all the three laws: (i) A 
the law governing the substantive contract; (ii) the law 
governing the agreement to arbitrate and the performance of 
that agreement; and (iii) the law governing the conduct of the 
arbitration, are Indian - Therefore, the parties have designated 
India as the seat - Parties being Indian and German, except B 
for London being chosen as a convenient place/venue for 
holding the meetings of arbitration, there is no other factor 
connecting the arbitration proceedings to London - In such 
circumstances, hearing of arbitration will be condu

Excerpt shown. Read the full judgment & AI analysis in Lexace.