LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

ECE INDUSTRIES LIMITED versus S.P. REAL ESTATE DEVELOPERS P. LTD. & ANR.

Citation: [2009] 12 S.C.R. 566 · Decided: 06-08-2009 · Supreme Court of India · Bench: TARUN CHATTERJEE · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

.'W 
[2009] 12 S.C.R. 566 
A 
ECE INDUSTRIES LIMITED 
t 
~ 
v. 
S.P. REAL ESTATE DEVE!.,.OPERS P. LTD. & ANR. 
(Civil Appeal Nos. 5127=5128 of 2009) 
8 
AUGUST 6, 2009 
[TARUN CHATTERJEE AND R.M. LODHA, JJ.] 
Code of Civil Procedure, 1908 - 0. 39 r. 1 and 2, s. 151 
- Application for injunction under - Rejection by two courts 
.., . 
c concurrently - Interference with - Held: Third court can 
interfere with the concurrent findings only when findings are 
perverse or arbitrary - On facts, courts below refused to grant 
injunction in favour of appellant from making any further 
construction in suit property - Findings of High Court and trial 
D court as also report of Advocate Commissioner appointed by 
Supreme Court were to the effect that substantial construction 
. 
, 
has already bee1 made by respondent for which crores of 
rupees have been spent - Respondent has deposited the 
entire agreement amount though belatedly - Appellant will 
E not suffer any substantial injury and balance of convenience 
lies against granting order of injunction - Thus, order of courts 
below justified - However, respondent would not claim 
equities over construction made. 
._ ' 
F 
In these appeals, thei order of High Court upholding 
the order of the triii\I court whereby it refused to grant the 
order of injunction restraining the respondent from 
making further construction in the suit property, is under 
challenge. 
G 
Dismissing the i'lppeals, the Court 
.,. 
HELD: 1.1. When two courts concurrently reject the 
....
application for injunction, it would not be open for the 
third court to interf@re with the said concurrent findings 
H 
566 
., . -+ 
1+ 
EGE INDUSTRIES LTD. v. S.P. REAL ESTATE 
567 
DEVELOPERS P.L TD . 
until and unless it is brought to the notice of the third 
A 
court that such findings are perverse or arbitrary; [Para 
12) [576-A-!3] 
1.2. As regard the construction on the suit property, 
the trial court came to the finding that as per the report 
B 
of the commissioner and also as per the photographs 
produced that major construction work was undertaken 
and completed, and it must have required the respondent 
to invest crores of rupees. High Court came to the finding 
that the defendants/respondents have already taken over 
possession and made substantial construction. These 
C 
are the two concurrent findings of fact arrived at by the 
High Court as well as by the trial court on the question 
of extent of construction on the suit property. [Para 12] 
[576-E-F] 
1.3. In order to be satisfied on the question of 
construction 
in 
the 
suit 
property, 
Advocate 
Commissioner was appointed by this Court. A perusal of 
the report shows that out of 1800 flats to be constructed 
D 
in the suit property in 8 Blocks, only in 295 apartments 
E 
in the Triangular area, work has not been started, 
whereas in the rest 1,555 apartments in 5 Blocks, work. 
is in progress at various stages. It is evident from the 
report that substantial progress has been made in the 
matter of construction on the suit property. Therefore, in 
view of the concurrent findings of the courts below and 
also from the findings arrived at by the Advocate 
Commissioner appointed by this Court in his report, it is 
held that substantial construction has been made. [Paras 
13, 15 and 17] [576-D; 577-G-H; 578-A, E-F] 
F 
G 
1.4. The Development Agreement-cum-General 
Power of Attorney was entered into by the defendants/ 
respondents with the plaintiff-appellant and as per the 
terms and conditions, parties agreed that a sum of Rs. 
13.50 crores had to be paid besides 16.72 crores for the 
H 
568 
SUPREME COURT REPORTS 
[2009] 12 S.C.R. 
A service of consultancy and Rs. 28,36,175/- was the cost, 
which comes to Rs. 30.50 crores. It was further agreed 
that it was only after the payment of the amount agreed 
upon, necessary documents were to be executed. Under 
the Agreement, the defendants/respondents had to 
8 furnish bank guarantee in regard to the amount stated to 
have been paid in four cheques. It is true that the 
respondents, after paying the first installments had failed 
to pay the other installments payable within the time 
specified, under the agreement, but it is an admitted 
C position that although, the deposits were belatedly made 
but the entire amount under the Agreement has already 
been deposited and in compliance with the Agreement, 
a Bank Guarantee has also been furnished. [Para 18) 
[578-G-H; 579-A-E] 
D 
1.5. Substantial constructi

Excerpt shown. Read the full judgment & AI analysis in Lexace.