DURGA CHARAN RAUTRAY versus STATE OF ORISSA & ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B [2011] 13 (ADDL.) S.C.R. 16 DURGA CHARAN RAUTRAY v. STATE OF ORISSA & ANR. (Civil Appeal No. 1735 of 2006) NOVEMBER 1, 2011 [R. M. LODHA AND JAGDISH SINGH KHEHAR, JJ.] Arbitration Act, 1940 - Contractual agreement - Disputes/claims raised by contractor-appellant - After receipt C of payment on preparation of the final bill, without raising objection - Redressal by way of arbitration - High Court holding that the appellant having received payment after preparation of final bill without raising objections, could not have initiated arbitral proceedings - On appeal, held: o Appellant despite having received payment after preparation of final bill without raising objections, could seek redressal of his disputes by way of arbitration in terms of the contractual agreement - He could still raise his unsatisfied claims before an arbitrator - Order referring the dispute raised by the E appellant to the arbitral tribunal, having attained finality, the respondents were precluded from asserting that the claims raised by the appellant could not be adjudicated upon by way of arbitration - Order passed by the High Court was contradictory in terms - Once the High Court concluded that F the Miscellaneous Case filed by the respondents raising objections was barred by limitation, it was not open to the High Court to consider one of the objections raised by the respondents and to uphold the same, so as to disentitle the appellant from reaping the fruits of the arbitral award - Thus, order passed by the High Court is set aside and that of the G civil judge making arbitral award rule of the court, is upheld. Appellant was entrusted with a construction work by respondent-State. Dispute arose between the parties and were referred to an arbitral tribunal. The arbitral tribunal H 16 DURGA CHARAN RAUTRAY v. STATE OF ORISSA & 17 ANR. passed an award in favour of the appellant. The appellant A filed an application to make the arbitral award, rule of the court. The respondents filed objections under Sections 30 and 33 of the Arbitration Act, 1940 by filing Miscellaneous Case. The Civil Judge dismissed the Miscellaneous Case on the ground of limitation. The B award was made rule of the court. Aggrieved, the respondents filed an appeal before the High Court under Section 39 of the Arbitration Act, 1940. The High Court upheld the order of the Civil Judge on the issue of limitation, however, held that the appellant could not c obtain the benefits of the award rendered by the Arbitral Tribunal in his favour since the appellant had received payments on the preparation of final bill without raising objections. Therefore, the appellant filed the instant appeal. D Allowing the appeal, the Court HELD: 1.1 A perusal of clause 23 of the contractual agreement leaves no room for any doubt that the appellant could claim arbitration on account of disputes E arising from the contract "except where otherwise provided". Clause 23 includes within the purview of arbitration, disputes whether arising during the progress of the work or after the completion or abandonment thereof. There is no restraint whatsoever expressed in F clause 23, which would deprive the appellant from seeking redressal by way of arbitration, merely because he had received payments after the preparation of the final bill, without raising any objections. Accordingly, even after the receipt of payment on the preparation of G the final bill, it was open to the appellant to seek redressal of his disputes.by way of arbitration, even though he had not raised any objections. [Para 8] [23-G-H; 24-A-C] Bharat Coking Goa Ltd. v. Annapurna Construction H 18 SUPREME COURT REPORTS [2011] 13 (ADDL.) S.C.R. A (2003) 8 sec 154: 2003 (3) Suppl. SCR 122 - relied on. 1.2 Despite receipt of payment on the preparation of the final bill, it was still open to the appellant to raise his unsatisfied claims before an arbitrator, under the contract B agreement. It was no longer open to the respondents to contest the claim of the appellant on the instant issue after the appellant had obtained the court order dated 15.05.1981 which referred the disputes raised by the appellant to an arbitral tribunal. The court order dated c 15.05.1981 referring the disputes raised by the appellant to arbitration, attained finality inasmuch as the same remained uncontested at the hands of the respondents. The respondents were, thereafter precluded
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex