LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

DLF LTD. (FORMERLY KNOWN AS DLF UNIVERSAL LTD) AND ANR. versus KONCAR GENERATORS AND MOTORS LTD.

Citation: [2024] 8 S.C.R. 291 · Decided: 08-08-2024 · Supreme Court of India · Bench: PAMIDIGHANTAM SRI NARASIMHA · Disposal: Case Partly allowed

cites 9 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 8 S.C.R. 291 : 2024 INSC 593
DLF Ltd. (Formerly Known as DLF Universal Ltd) and Anr. 
v. 
Koncar Generators and Motors Ltd.
(Civil Appeal No. 7702 of 2019)
08 August 2024
[Pamidighantam Sri Narasimha* and Aravind Kumar, JJ.]
Issue for Consideration
The issue arising in the present appeal relates to enforcement of 
an arbitral award expressed in foreign currency. In this context, 
two questions arise for consideration. First, what is the correct 
and appropriate date to determine the foreign exchange rate for 
converting the award amount expressed in foreign currency to Indian 
rupees. Second, what would be the date of such conversion, when 
the award debtor deposits some amount before the court during 
the pendency of proceedings challenging the award. 
Headnotes†
Arbitration and Conciliation Act, 1996 – Arbitral Award  – 
Enforcement of an arbitral award expressed in foreign 
currency  – What is the correct and appropriate date to 
determine the foreign exchange rate for converting the award 
amount expressed in foreign currency to Indian rupees:
Held: The statutory scheme of the Act makes a foreign arbitral 
award enforceable when the objections against it are finally 
decided – Therefore, as per the Act and the principle in Forasol 
case, the relevant date for determining the conversion rate of 
foreign award expressed in foreign currency is the date when the 
award becomes enforceable. [Para 20(i)]
Arbitration and Conciliation Act, 1996 – Arbitral Award – 
Enforcement of an arbitral award expressed in foreign 
currency  – What would be the date of such conversion, 
when the award debtor deposits some amount before the 
court during the pendency of proceedings challenging the 
award:
Held: When the award debtor deposits an amount before the 
court during the pendency of objections and the award holder is 
permitted to withdraw the same, even if against the requirement of 
* Author
292
[2024] 8 S.C.R.
Digital Supreme Court Reports
security, this deposited amount must be converted as on the date 
of the deposit – After the conversion of the deposited amount, the 
same must be adjusted against the remaining amount of principal 
and interest pending under the arbitral award – This remaining 
amount must be converted on the date when the arbitral award 
becomes enforceable, i.e., when the objections against it are finally 
decided. [Para 20(ii)(iii)]
Arbitration and Conciliation Act, 1996 – Appellants are Indian 
companies and the respondent is a Croatian company – 
Dispute arose between the parties – Matter referred to 
arbitration before the International Chamber of Commerce – 
Arbitral tribunal passed its award dated 12.05.2004 in favour 
of the respondent-claimant – Appellants then filed objections 
against the award u/s. 48 – The appellants deposited Rs. 7.5 
crores with the Executing Court on 22.10.2010 – Trial Court 
dismissed the objections filed u/s. 48 – Appellants filed 
a revision, which the High Court admitted by order dated 
03.06.2011 – The High Court stayed the operation of the Trial 
Court order dismissing objections, subject to the appellants 
depositing a further amount of Rs. 50 lakhs, in addition to 
Rs. 7.5 crores, with the Executing Court – The revision came 
to be dismissed by the High Court on 01.07.2014, by which 
the award attained finality as this order was not challenged 
any further – What would be relevant conversion date of the 
amount:
Held: The deposit of Rs. 7.5 crores was permitted for withdrawal by 
furnishing a bank guarantee – So, the first deposit of Rs. 7.5 crores 
must be converted as on the date of deposit being 22.10.2010 – 
The second deposit of Rs. 50 lakhs pursuant to the High Court 
order dated 03.06.2011 stands on a different footing from the first 
deposit – This order did not permit the respondent to withdraw this 
amount till the completion of the proceedings –  Hence, the amount 
cannot be converted as on the date of deposit as the respondent 
could not have benefitted from the same – Here, the revision 
proceedings were complete on 01.07.2014 – Thus, the second 
deposit of Rs. 50 lakhs as well as the remaining amount due under 
the award must be converted when the objections proceedings 
attained finality on 01.07.2014 – The Executing Court, being the 
Additional District Judge cum Commercial Court, must determine 
the amount payable by taking into account the exchange rate as 
on 01.07.2014. [Paras 11.2, 18, 19, 21]
[2024] 8 S.C.R. 
293
DLF Ltd. (Formerly 

Excerpt shown. Read the full judgment & AI analysis in Lexace.