LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

DELHI DEVELOPMENT AUTHORITY versus KENNETH BUILDERS & DEVELOPERS LTD. & ORS.

Citation: [2016] 3 S.C.R. 1126 · Decided: 29-06-2016 · Supreme Court of India · Bench: MADAN B. LOKUR · Disposal: Dismissed

Cited by 2 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
c 
D 
E 
F 
G 
H 
[2016] 3 S.C.R. 1126 
DELHI DEVELOPMENT AUTHORITY 
v. 
KENNETH BUILDERS & DEVELOPERS LTD. & ORS. 
(Civil Appeal No .. 53 70of2016) 
JUNE 29, 2016 
( MADAN B. LOKUR AND N.V. RAMANA, JJ. ) 
Contract Act, 1872 - s. 56 - Contract impossible of 
performance ~Auction of 'residential' land by DDA on 'as is where 
is' basis - For construction of houses - Bid of the respondent-builder 
accepted - Project land allotted and possession thereofgiven to 
builder - Development agreement between DDA and the builder -
As per agreement various approvals and clearances from the 
appropriate authorities including environmental age11cies was o 
responsibility of the builder - The development work on project 
land objected to by Department of Forests of Government of National 
Capital Territory (GNCTD) on the ground that the land fell in the 
Ridge and hence construction without consent of Ridge Management 
Board and permission of the Supreme Court not allowed - Ministry 
of Environment and Forest, Government of India gave environment 
clearance subject to condition that Delhi Pollution Control 
Committee (DPCC) gave "consent to establish" - However, DPCC 
refused to give "consent to establish" in absence of "ridge 
demarcation report" - Builder also could not obtain "ridge 
demarcation report" - Builders writ petition under Art. 226 of 
Constitution for setting aside of auction, for declaration that project 
was incapable of performance and sought refund of the amount 
paid to DDA - High Court held that if DPCC did not permit 
construction activity, the builder was entitled to refund of the entire 
amount deposited witli'DDA - Even after the judgment of High 
Court, DPCC refused to grant "consent to establish" - Appeal by 
DDA and also by GNCTD and DPCC - Held: Despite the fact that 
builder took all the necessary steps to commence the construction 
activity, it co_uld not proceed the development activity due to the 
impasse created_ by the Government agencies - Thus the development 
agreement between DDA and the builder was frustraied having 
become impossible of performance within meani111g of s.56, due to 
1126 
DELHI DEVELOPMENT AUTHORITY v. KENNETH 
BUILDERS & DEVELOPERS LTD. & ORS. 
the intervening circumstances not contemplated by either party -
DDA directed to refimd the deposit made by the builder with interest 
@6%. 
Dismissing the appeal filed by DDA, the Court 
HELD: 1. The objection to the maintainability of the writ 
petition, having not been raised by the DDA before the High 
Court or even in the petition filed in this Court, cannot be 
entertained. The submission has been advanced by the DDA for 
the first_ time during the final hearing of these appeals. It is too 
late in the day to raise such an objection. [Para 27) [1146-D] 
2.1 The respondent-builder did take all necessary steps to 
commence the construction activity on the project land but due 
to the impasse created by the governmental agencies, it could 
not proceed in the development activity. Under these 
circumstances, the provisions of Section 56 of the Contract Act, 
1872 would be attracted to the facts of the case. [Para 32) [1147-
F-G) 
2.2 The word "impossible" used in Section 56 of the 
Contract Act has not been used in the sense of physical or literal 
impossibility. It ought to be interpreted as impracticable and 
useless from the poiยตt of view of the object and purpose that the 
parties had in view when they entered -into the contract. This 
impracticability or uselessness could arise due to some 
intervening or supervening circumstance which the parties had 
not contemplated. However, if the intervening circumstance was 
contemplated by the parties, then the contract would stand despite 
the occurrence of such circumstance. In the present case, the 
DDA certainly did not contemplate a prohibition on construction 
activity on the project land which would fall within the Ridge or 
had morphological similarity to the Ridge. It is this circumstance 
that frustrated the performance of the contract in the. sense of 
making it impracticable of performance. [Paras 33 and 34) [1148= 
D-E; 1150-A-B) 
Satyabrata Ghose v. Mugneeram Bangur & Co. (1954) 
SCR 310 - relied on. 
2.3 It is true that the Government of India had notified the 
project land as "Residential" and that the project land was shown 
1127 
A 
8 
c 
D 
E 
F 
G 
as "Residential" in the MPD-2001 and MPD-2021. But that fact 
alone would not change the position at law. The exact

Excerpt shown. Read the full judgment & AI analysis in Lexace.