CONTINENTAL CONSTRUCTION CO. LTD. versus STATE OF MADHYA PRADESH
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
,
-~
'
CONTINENTAL CONSTRUCTION CO. LTD.
A
v.
STAIB OF MAIJHYA PRADESH
MARCH 7, 1988
[SABYASACHI MUKHARJI AND S. RANGANATHAN, JJ.]
B
Arbitration Act, 1940--Whether a contractor can claim extra cost
and compensation towards rise in prices of material and labour on
account of delay on the part of other party to contract in discharge of its
obligations and allotment of work under the contract and irivoke arbi-
tration clause in contract and ask for a reference to arbitrator under C
section 20--0f
The petitioner in this application under Article 136 of the Con-
stitution entered into a contract with the respondent State for construc-
tion work. The contract could not be completed within the stipulated
time because of alleged gross delay on the part of the State in allotment D
of work and discharge· of its obligations under the contract. The
petitioner incurred unforeseen expenditure and approached the
Superintending Engineer for payment. Upon refusal of the Superin-
tending Engineer to pay and also to refer the matter to arbitration, the
petitioner moved the District Judge under Section 20 of the Arbitration
Act, ('the Act') for the filing of the arbitration. agreement and for
E
reference of the dispute to arbitration. The District Judge directed the
respondent State to file the agreement, and made a reference for
specific question to the arbitration. The High Court dismissed the
State's appeal against the Order of the District Judge. Thereafter, an
arbitrator was appointed, who made an award partly allowing the
petitioner's claim. The award was filed in the Court of the District F
Judge, who made the award a rule of the court. The respondent
.appealed to the High Court. The High Court remanded the matter to the
District Judge for a fresh decision. The District Judge accepted the
respondent's objections and set aside the award. The High Court dis-
missed the appeal of the petitioner. The petitioner then moved this
Court for relief by this petition for special leave.
G
Dismissing the petition, the Court,
HELD: The District Judge rightly found that the question
regarding extra-.:ost was a general question and not a specific legal
question and the decision of the arbitrator was not final. The arbitrator H
103
A
B
c
D
E
F
G
-104
SUPREME COURT REPORTS
[1988] 3 S.C.R.
misconduCted himself in allowing the claim without deciding the objec-
tion of the State. In view of the specific clauses, the petitioner was not
legally entitled to claim for extra-cost. The decision of this Court in
Seth Thawardas v. Union of India, I 1955] 2 SCR 48-was of no avail on
this point. If no specific question of law is referred, the decision of the
arbitrator on that question is not final however much it may be within
his jurisdiction and indeed essential for him to decide the question
incidentally. The arbitrator is not a conciliator and cannot ignore the
law or mis-apply it in order to do what he thinks is just and reasonable.
The arbitrator is a Tribunal selected by the parties to decide their
disputes according to law and so he is hound to foJlow and apply the
law, and if he does not, he can be set right by the Court provided his
error appears on the face of the award. In this case, the contractor
having contracted, could not go back to the agreement simply because it
did not suit him to abide by it. [IllC-F]
The petitioner had argued that since specific issues had been
framed and referred by the District Judge to the arbitrator, the same
had been answered by a non-speaking award and there was no mistake
of law apparent on the face of the record, and the District Judge had
erred in setting aside the award by looking into the terms of the contract
which neither formed part of the award nor were appended to it. The
Court did not agree. This being a general question, the District Judge
rightly examined the question and found that the petitioner was not
entitled to claim for extra cost in view of the terms of the contract, and
the arbitrator misdirected himself by not considering this objection of
the State before giving the award. [112B·C]
The limits of the jurisdiction of the Court to challenge the award
are well-settled. While considering the objection under section 30 of the
Act, the Court does not act as an appellate Court; it can only interfere
with the award if the arbitrator misconducts himself or the proceedings
or if the award has been made after the issue of an Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex