CHAMUNDESHWARI ELECTRICITY SUPPLY COMPANY LTD. (CESC) versus SAISUDHIR ENERGY (CHITRADURGA) PVT. LTD. & ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2025] 8 S.C.R. 1493 : 2025 INSC 1034 Chamundeshwari Electricity Supply Company Ltd. (CESC) v. Saisudhir Energy (Chitradurga) Pvt. Ltd. & Anr. (Civil Appeal No. 6888 of 2018) 25 August 2025 [Sanjay Kumar and Satish Chandra Sharma,* JJ.] Issue for Consideration The following questions arise for determination: (i) the effect of respondent no.2/KPTCL’s delay in commissioning the 220 kV evacuation system upon the timelines stipulated for fulfilment of the CPs and achievement of COD under the PPA; (ii) the entitlement of appellant to invoke and encash the performance bank guarantee in the facts of the present case; (iii) the sustainability of the finding of Force Majeure recorded by the State Commission in the absence of the contractual notice contemplated under Article 14.5 of the PPA; (iv) the character of the PPA as a contingent contract; and (v) the competence of the State Commission and the APTEL to direct restoration of the bank guarantee, extension of timelines, and renegotiation of tariff. Headnotes† Electricity Act, 2003 – APTEL affirmed the order dated 28.01.2015 of the Karnataka Electricity Regulatory Commission (State Commission/KERC), whereby the State Commission directed Chamundeshwari Electricity Supply Corporation Limited, the appellant herein, to restore to the Developer i.e. respondent no.1 herein, the amount realised from the encashment of the performance bank guarantee; extend the timelines for fulfilment of contractual obligations; and to undertake renegotiation of the tariff under the Power Purchase Agreement (PPA) for a solar power project: Held: 1. Appellant’s invocation and encashment of the performance security was in full conformity with the contractual framework under the PPA – The non-fulfilment of the respondent no.1/Developer’s obligations within the stipulated time, non-seeking of extension under Article 5.7 or valid Force Majeure claim under Article 14, necessarily attracted Article 4.4 of the PPA – The impugned * Author 1494 [2025] 8 S.C.R. Supreme Court Reports judgment dated 21.03.2018 of the APTEL passed in Appeal No.176 of 2015, and the order dated 28.01.2015 of the State Commission in O.P. No.24 of 2014 are set aside. [Paras 44-45] 2. The record discloses beyond dispute that the evacuation system, integral for delivery of power, was to be executed by respondent no.2/KPTCL through the construction of two 220 kV double-circuit lines – By its communication dated 19.08.2014, respondent no.2/ KPTCL itself acknowledged that the lines would be commissioned only in August 2015, well beyond the contractual timelines – The respondent no.1/Developer submission that such delay, being beyond its control, automatically extended the contractual schedule, cannot be accepted – The contractual framework does not operate on automaticity – Contractual rights and remedies must be asserted within the framework of the agreement, not dehors it. [Paras 37-38] 3. Turning then to the invocation of the performance bank guarantee, in the present case, supply did not commence within the agreed period; no formal extension was obtained under Article 5.7 of the PPA; and no notice of Force Majeure was issued under Article 14.5 of the PPA – The preconditions for invocation of Article 4.4 of the PPA thus stood satisfied – Appellant’s invocation of the bank guarantee was, therefore, an exercise of a remedy specifically conferred by the contract, and to deny it would be to disregard the allocation of risk embodied in the PPA. [Para 39] 4. The finding of Force Majeure by the State Commission cannot be sustained for the reason that Article 14.5 of the PPA stipulates that the affected party “shall” issue notice within seven days of knowledge of the event – This requirement is not merely directory; it is a condition precedent for invoking the clause – Even if the delay in completion of the evacuation system was beyond the respondent no.1/Developer’s control, the appropriate provision for relief was Article 5.7, not Article 14 of the PPA – Significantly, Article 14.3.1 of the PPA details the events and circumstances which constitute Force Majeure and delay in the readiness of the evacuation system, even if attributable to Respondent No.2/KPTCL, does not constitute a Force Majeure. [Para 40] 5. The completion of the evacuation system by respondent no.2/ KPTCL was indeed an uncertain event outside the respondent no.1/Developer’s control, and in a practical sense, supp
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex