LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

BOMBAY HOUSING BOARD (NOW THE MAHARASHTRA HOUSING BOARD) versus KARBHASE NAIK & CO., SHOLAPUR

Citation: [1975] 3 S.C.R. 407 · Decided: 29-01-1975 · Supreme Court of India · Bench: KUTTYIL KURIEN MATHEW · Disposal: Case Partly allowed

Cited by 1 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
c 
D 
E 
F 
G 
H 
401· -
BOMBAY HOUSING BOARD (NOW THE MAHARASHTRA 
HOUSING BOARD) 
' \!. 
KARBHASE NAIK & CO., SHOLAPUR 
January 29, 1975 
[K. K. MATHEW, P. N, BHAG'YATI AND N. L. UNTWALIA, JJ.] 
The Bombay Housing Board Act (69 of 1948), s. 64-'Anything done or 
pll.'porti11g to lwve bee11 done in pursuance of the Acl', Scope of-Breach of 
c1111tract if comes within_ expression. 
There was a conlra1:t between the State and the respondent, which after the 
passing of the Bombay Housing Board Act, 1948, was deemed to have b-~en 
entered into between the appellant and the respondent, for the construction of· 
buildings by the respondent. 
Clause 14 of the Contract provided that where 
any additional or altered work is directed to be carried out and no rates are 
entered in the Schedu!e of Ra-tes in the Division, or agreed to, then. the contractor 
may, within 7 days of the order, give notice of the rate he intends to charge. 
In such a case, the Engineer-in,:harge would be at liber~ to cancel the order 
if h.e does not agree to the rate stated by the. contractor, and get the work done 
by another. 
Where the Engineer-in-charge has not cancelled the order and 
the contra.ctor ha!.i commenced work and incu.rred expenditure. the contractor 
shall only be entitled to be paid at su:h rate as may be fixed by the Engineer'in-
charge, and if the contractor is dissatisfied, he may raise a dispute about the 
rate and the decision of the Superintending Engineer will b·~ final. 
Clause 15 provided that the Engineer-in-charge has power to stop or to 
reduce the who'.e of the work specified in the tender or g·~t it done by ano!her, 
and the contractor has no claim to any compensation whatsoever on account of 
such stoppage or redudion.. But, befo:e th·~ Engineer-in-charge could stop the 
work and get it done by another contractor, he should give the first contractor 
a written notice, The contrac:or sha,JJ also have no right under the clause to 
claim any payment or compensation on account ·of any profit or advantage 
which he might have derived from the exe:ution of the work in full but which 
he did not derive in consequence of the full amount of work not having been 
carried out, or on account of any loss due to purchase of materia's or labour 
recruited by him. 
The clame further provides that the contractor shal! not also· 
have any claim for compensation by reason of any alteration in the original 
specifi.:a·tion which may involve curtailment of work as originally contemplated. 
The respondent filed a suit claiming a certain sum of money with respect 
to certain items and the. suit was decreed by the trial court except with respect 
to 4 items. The High Court in appeal, however decr~ed those items also. 
They were : (I) the respondent was ordered to carry out certain work with 
respect to the first two items and the respondent intimated his rate as required· 
by cl. 14. The Engineer-in-charge did not cancel the order or give the_ contract 
for. the extra work to any other contractor, and therefore. the High Court held 
that the amount due to the respondent for the extra work was to be calculated· 
on the basis of the rate specified in the notice; (2) the respondent was assured 
by the appellant that the work was to be completed in accordance with the 
»pecifications in. the agreement. and that no alteration would be made therein, 
but in fact an alteration was made as a result of whkh the respondent became 
entitled to lesser amount and the High Court held he was entitled to the 
difference; and (3) the appellant represented to the respondent that the appellant 
would entrust the respon<;lent with another item of work bu,t, contrary to the 
reprcsen~ation, got the work done by another without giving notice in writing 
to the respondent and hence, the High Court held that the respondent was 
entitied to compensation. 
408 
SUPREME COURT REPORTS 
[1975] 3 S.C.R. 
In appeal. to thi» Court, it was contended; (1 l. that with respect to the first 
2 items in view of cl. 14 the respondent was entitled only to the rate Js fixed 
.by the Engineer-in-charge; 
0
('2) with respect to the 3rd item since the Engineer-in-
.char~e was entitled to ':hange the specifications, the respondent was not en:1tled 
to compensation in view of Cl. 15; (3) with respect to the 4th item no notice 
was necessary before getting the work done by another contractor; and ( 4) the 
·su!t was barred by limitation under s. 64 of the Bombay Housing Board Ac

Excerpt shown. Read the full judgment & AI analysis in Lexace.