BIHAR STATE ELECTRICITY BOARD & ORS. versus MIS. BHOLA RAM STEEL PVT. LTD. & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2016] I S.C.R. 499 BIHAR STATE ELECTRICITY BOARD & ORS. v. MIS. BHOLA RAM STEEL PVT. LTD. & ORS. (Civil Appeal No. 585 of2016) JANUARY 28. 2016 [M.Y. EQBAL AND ARUN MISHRA, JJ.] Electricity - Benefit under Industrial Policy I 995 - Of exemption from payment of minimum guarantee charges - To the industrial units having connected load of 500 KVA - Industrial unit/ consumer in question entered into an agreement for a contract demcnd of 500 KVA - Entitlement to the exemption - Held: As per the readings in Maximum Demand Indicator (MDI) Meter!Trivector Meter, theยท consumer availed electricity in excess of the contracted load which was in contravention of the agreement - Therefore, the appellant-Board was well within its right to realize the amozint as per tariff Notifications, in view of clause 16.5 of the Notification dated 21.06.1993 issued u/s. 49 of Electricity Act, 1948 - The consumer is not entitled to benefit of exemption - Electricity Act, 1948 - s. 49. Allowing the appeal, the Court HELD: 1. As per the readings recorded by the MDI meter/ Trivect< . meter, it is apparent that consumer has availed and drawn electricity in excess of the contracted load in contravention of th~ ;reement with the Electricity Board. The reading of MDI meter 1s indicator of total connected loads, the total load deman.ded and availed of during the course of actual consumption of energy. In the facts of instant case, it is apparent that for six months in the year 1999-2000 the MDI meter has recorded excess load. Thus the High Court has erred in the facts of the instant case in holding that it has not been established in the instant case that the c<mnected load was more than 500 KVA. [Para 14] [504-D-E) Orissa State Electricity Board & Am: v. !PI Steel Ltd. & Ors. (1995) 4 SCC 320: 1995 (3) SCR 684; Bhilai Rerollers & Ors. v. MP. Electricity Board & Ors. (2003) 7 SCC 185: 2003 (2) Suppl. SCR., 787 .- relied on. 499 A B c D E F G H 500 A B c D E F SUPREME COURT REPORTS (2016] I S.C.R. 2. Merely in an inspection in January, 1999 the connected load was found to be of 495 HP when for six months in a subsequent period of April, 1999 to March, 2000 maximum demand has increased beyond the contracted load of 500 KVA and it is not disputed that it was more than 110% of the contract load. Thus as per clause 16.5 of the notification dated 21.06.1993 issued under the Electricity Supply Act, 1948 the Electricity Board was well within its rights to realize the amount as per tariff notification. The High Court has erred in holding in the facts of the case that there can be no correlation with the maximum demand and the connected load. [Para 16] [507-D-F] 3. The High Court has also proceeded on irrelevant consideration while it has observed that entrepreneur has stepped up production, which will result in economic development, generation of employment and income and higher consnmption is better for the State of Bihar. This was not a question to be gone into by the High Court. The High Court was required to consider the reliability of the MDI meter and frequent violation of contract demand and the tariff notification dated 21.6.1993. ยทThere is material on record indicating that the connected load has been exceeded as reflected in the meter reading. [Para 16] [507-F-G] 4. The plea taken that there was defect in the meter and they were changed in January, 2000 and again in March, 2000 has no legs to stand. However MDI meter readings for earlier periods too indicated demand exceeding 500 KVA and in the month of November 1999, the meter was found to be in order and maximum demand exceeded contract demand. Once maximum load drawn had exceeded the contracted load, in the fact of the case, it can safely be held that there is violation of the permissible connected load. The recording in MDI meter is more credible and reliable than the stand of the industry that the meter G was faulty, set up just to escape from the liability. [Para 16] [507- H; 508-A-B] Case Law Reference 1995 (3) SCR 684 relied on. H 2003 (2 ) Suppl. SCR 787 relied on. Para 15 Para 15 BIHAR STATE ELECTRICITY BOARD v. M/S. BHOLA RAM 501 STEEL PVT. LTD. CIVIL APPELLATE JURISDICTION: Civil Appeal No. 585 of A 2016 From the Judgment and Order dated 13.11.2009 of the High Comt of Judicature at Patna in LPA No. 1613 of 2000. Moh it Kumar Shah for the Appellants. S. D. Sanjay, Devashish Bharuka, Abraha
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex