LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED versus HIREHALLI SOLAR POWER PROJECT LLP & OTHERS

Citation: [2024] 8 S.C.R. 1024 · Decided: 27-08-2024 · Supreme Court of India · Bench: PAMIDIGHANTAM SRI NARASIMHA · Disposal: Dismissed

cites 2 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 8 S.C.R. 1024 : 2024 INSC 631
Bangalore Electricity Supply Company Limited 
v. 
Hirehalli Solar Power Project LLP & Others
(Civil Appeal No. 7595 of 2021)
27 August 2024
[Pamidighantam Sri Narasimha* and Pankaj Mithal, JJ.]
Issue for Consideration
Whether the extension of the Scheduled Commissioning Date 
(SCD) was occasioned under the force majeure clause of the 
Power Purchase Agreement (PPA), and consequently, whether the 
reduction in tariff payable to the respondents is justified.
Headnotes†
Electricity Act, 2003 – State of Karnataka introduced a 
policy dated 26.08.2014 to identify and promote solar energy 
projects by land-owning farmers – These solar power plants 
of 1-3 MW capacity would generate and sell power to the 
State Electricity (Distribution) Supply Companies at the 
tariff determined by the Karnataka Electricity Regulatory 
Commission (KERC) – Respondent no. 2-farmer applied 
under the policy – Respondent No.1 is a special purpose 
vehicle (SPV) to undertake the solar power project – In the 
year 2015, the appellant entered into a PPA with respondent 
no. 2 and the same was approved by KERC – The SPV had 
to achieve commercial operation within 18 months from the 
effective date – Several farmers, including the respondent, 
raised concerns regarding delay in the execution of the 
project on account of delay in getting land use conversion, 
delay in getting evacuation approvals, demonetisation, and 
other reasons – KERC rejected the various causes of delay 
put forth by the respondents and held that the force majeure 
clause must be strictly interpreted – KERC reduced the tariff 
payable to the respondent to Rs. 4.36 per unit for the term of 
the PPA by relying on Article 5.1 of the PPA – However, the 
APTEL found that the respondents had taken all necessary 
care and caution and acted with due diligence and held that 
respondents are entitled to the benefit of the force majeure 
clause and an extension of time – Also held that reduction in 
* Author
[2024] 8 S.C.R. 
1025
Bangalore Electricity Supply Company Limited v.  
Hirehalli Solar Power Project LLP & Others
tariff from Rs. 8.40 to Rs. 4.36 per unit would adversely affect 
them – Hence, it directed the appellant to pay the difference 
in per unit tariff along with the late payment surcharge as 
provided under Article 6.4 of the PPA – Correctness:
Held: The KERC’s appreciation of the evidence has led it to 
the conclusion that the delay in commissioning was due to the 
respondents’ delay in making the applications, despite the approval 
of the PPA – However, the APTEL has taken note of certain 
additional factors affecting the time taken to secure the approvals 
that were not considered by the KERC – These include the time 
taken by the government to provide the PTCL that is required for 
approval of land conversion, and the delay caused by the authority 
in evacuation approval – Considering these additional factors, the 
APTEL has re-appreciated the evidence to find that the delay was 
not attributable to the respondents but to the government bodies and 
relevant authorities – There is no error in the APTEL’s approach, 
and it is reasonable in its re-appreciation of evidence – In light 
of the above findings of fact by the APTEL that the delay is not 
attributable to the respondents and that the force majeure clause is 
applicable, it rightly held that the extension of time under Article 2.5 
is warranted and the commissioning of the project on 24.08.2017 
is within the extended period of 24 months – Consequently, the 
APTEL also rightly held that there is no occasion for the imposition 
of liquidated damages under Articles 2.2 and 2.5.7 or for the 
reduction of tariff under Article 5.1 of the PPA. [Paras 10.4, 12]
Electricity Act, 2003 – s.125 – Scope and ambit of appellate 
jurisdiction:
Held: The position that emerges in this case, it is a little more 
restrictive as the requirement under Section 125 is not merely a 
‘question of a law’ but a ‘substantial question of law’ – The restrictive 
scope of appellate jurisdiction is a product not only of the statutory 
preconditions, but also a necessary measure to enable freedom to 
statutory regulator and Tribunal to develop sectorial laws through 
a principled and consistent approach. [Paras 1, 7.4]
Contract Act, 1872 – Chapter III – ss.32 and 56 – Power 
Purchase Agreement – Force Majeure:
Held: The law on force majeure, specifically in the context of 
PPAs, has been comprehensively dealt

Excerpt shown. Read the full judgment & AI analysis in Lexace.