ASSAM STATE ELECTRICITY BOARD AND ORS. versus BUILDWORTH PVT. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2017) 7 S.C.R. 123 ASSAM STATE ELECTRICITY BOARD AND ORS. A v. BUILDWORTH PVT. LTD. (Civil Appeal No. 484 of2008) JULY04, 2017 [JAGDISH SINGH KHEHAR, CJI, DR. D. Y. CHANDRACHUD AND S~NJAY KISHAN KAUL, JJ.) Arbitration Act, 1940: Award - Price escalation - Work contract - Claimant was allowed to work beyond the formal extended time - Respondent- Board cannot be allowed to take the stand that claimant is not entitled to escalation price for the period he worked even though there is no formal extension of time and taking refuge under the clause of contract wherein ceiling of contractual amount is fixed. Award - Idling charges - Arbitrator noted in the award the contributory delay on the part of claimant - Once the aspect of contributory delay was present to the mind of the arbitrator, as is reflected in the reasons in the award, and taken into consideration B c D in the assessment 'of damages, the award does not call for E interference. s.29 - Award of interest - Arbitrator has power to grant interest on damages u/s.3(/)(b) of the Interest Act, 1978, from the date mentioned in this regard in a written notice claiming such interest - The contract in the instant case contains no bar or F prohibition against the award of interest - The claimant is entitled to interest on the sum awarded from the date Β·of notice i.e. 20 April 1987 to 31December1997 and thereafter from the date of the decree of the trial Court until payment or realisation - The rate of interest is, however, modified to 12 per cent per annum, in respect of both the above periods - Interest Act, 1978 - s.3(1)(b). G Disposing of the appeals (in favour of claimant), the Court HELD: 1. The arbitrator has taken the view that the provision for price escalation would not bind the claimant beyond 123 H 124 SUPREME COURT REPORTS [2017) 7 S.C.R. A the scheduled date of completion. This view of the arbitrator is based on a construction of the provisions of the contract, the correspondence between the parties and the conduct of the Board in allowing the completion of the contract even beyond the formal extended dated of 6 September 1983 up to 31 January 1986. B c D E Matters relating to the construction of a contract lie within the province of the arbitral tribunal. Moreover, in the present case the view which has been adopted by the arbitrator is based on confidential material which was relevant to the decision. There is no error apparent on the face of record which could have warranted the interference of the court within the parameters available under the Arbitration Act, 1940. The arbitrator has neither misconducted himself in the proceedings nor is the award otherwise invalid. The award does not suffer from any error apparent on the face of the record insofar as the aspect of price escalation is concerned. [Paras 12, 15][130-F-G; 132-F] P.MPaul v. Union of India (1989) Suppl. 1 SCC 368; Food Corporation of India v. A.M.Ahmed & Co. and Another (2006) 13 SCC 779 : [2006] 8 Suppl. SCR 148; K.N.Sathyapalan (Dead) by Lrs. v. State of Kera/a and Another (2007) 13 SCC 43 : [2006) 9 Suppl. SCR 864 - relied on. General Manager, Northern Railway v. Sarvesh Chopra (2002) 4 SCC 4:5 : (2002] 2 SCR 156 - referred to. 2. On the aspect of idling charges for machine and labour, the arbitrator noted that three additional items of work were . F required to be carried out by the claimant which did not form part of the original work. These items of work required the mobilization of labour and machinery separately from that which had already been mobilized. The arbitrator held that to some extent, the claimant contributed to the delay in the execution of the work and referred in that connection toΒ· the letters addressed G by the Board to the claimant. The arbitrator also observed that the inability of the claimant to place the required number of supervisors at the site also contributed to the delay in the completion of the work. The point of the matter is that the arbitrator has duly borne in mind the circumstance that "the H claimant also contributed to a certain extent and must share ASSAM STATE ELECTRICITY BOARD v. BUILDWORTH PVT. LTD. 125 responsibility for causing delay in completion of the project. The A award does indicate that the contributory delay on the part of the claimant was present to the mind of the arbitrator and has been duly taken into consideration in computing the extent of
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex