LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

ASIAN THERMAL INSULATION (I) P. LTD versus BRIDGE & ROOF CO. (I) LTD.

Citation: [2007] 8 S.C.R. 1004 · Decided: 13-08-2007 · Supreme Court of India · Bench: ARIJIT PASAYAT · Disposal: Disposed off

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
ASIAN THERMAL INSULATION (I) P. LTD. 
fยท 
v. 
BRIDGE & ROOF CO. (I) LTD. 
AUGUST 13, 2007 
B 
[DR. ARIJIT PASAYA T, ยฃ.K'.. THAKKER AND 
LOKESHWAR SINGH PANT A, JJ.] 
Arbitration and Conciliation Act, I 996-s. I I (6)-Dispute between 
~ 
...... 
c Company and the Contractor-Agreement between them contained an 
arbitration clause-Issue of appointing arbitrator-On application of 
Company, High Court directing the matter to be placed before the Chief 
Justice-Appeal by Contractor before Supreme Court-Contractor had 
... 
already nominated its arbitrator-Parties agreed on a consensual 
D arrangement-Appeal accordingly disposed. of-Company to nominate its 
, .. 
arbitrator within 30 days-Thereafter Chief Justice of High Court to nominate 
the Presiding Arbitrator. 
~ 
,, 
Respondent-company had entered into an agreement with Appellant-
. >< 
contractor. The agreement contained an arbitration clause. Disputes arose 
E between the parties. Order was passed by the High Court on the application 
filed by Respondent. The matter was directed to be placed before the Chief 
Justice of High Court for naming an arbitrator. High Court declined to recall 
the order on the Appellant's petition. 
During pendency of appeal before this Court, the parties agreed on a 
F consensual arrangement. 
Disposing of the appeal, the Court 
-I 
HELD: Though arguments were advanced in support of the respective 
stand about the legality of the impugned order, it was agreed to by the parties 
G that following arrangement can be made : The appellant has nominated one 
Sri J. Chawla to be its arbitrator. Within a period of 30 days the respondent 
shall nominate its arbitrator. Thereafter the Chief Justice of the High Court 
shail nominate the Presiding A.rbitrator who shall be a retired Judge of any 
High Court. [Para 6) (1008-B-C) 
ยทr 
H 
1004 
_.r:--< 
~ 
' . 
.. 
~ 
~ 
"' 
ASIAN THERMAL INSULATION (I) P. LTD .... BRIDGE & ROOF CO. (l)LTD. (PASAYAT. J.) 
} 005 
SBP & Co. v. Patel Engineering Ltd & Anr., (2005) 8 SCC 618, relied A 
on. 
Konkan Rly. Corpn. Ltd. v. Rani Construction (P) Ltd, (2002) 2 SCC 
388, referred to. 
CIVIL APPEL LA TE JURISDICTION : Civil Appeal No. 3696 of2007. 
From the Order dated 19.9.2005 of the High Court of Calcutta in A.P. No. 
209 of2005. 
Kumud Lata Das for the Appellant. 
Puneet Jain, Sushi! Kumar Jain, H.D. Thanvi, Sarad Singhania and Christi 
Jain for the Respondent. 
The Judgment of the Court was delivered by 
DR. ARIJIT PASAYA T, J. I. Leave granted. 
2. Controversy lies within a very narrow compass. 
3. The factual background as projected by the appellant is as follows: 
On 22.12.2003 work order was issued by the respondent to the appellant. 
There was a clause for arbitration in the agreement which was to the following 
effect: 
"4 l. ARB/TRA TION 
B&R confidently feel that there shall not arise any disputes or 
differences during execution and completion of this order by the 
Contractor. 
However, in the event of any disputes or differences arise between 
Company (B&R) and Contractor (hereinafter called the said parties) 
touching or concerning the interpretation of the terms and conditions 
as performance of the order or in connection therewith or the rights 
and liabilities of either of the said parties hereto, the said parties shall 
endeavour to settle the same amicably through mutual agreement 
between them, but ifthe mutual settlement is not possible between the 
Company and the Contractor, the provisions of the Indian Arbitration 
& Conciliation Act, 1996 and all statutory re-enactment and 
B 
c 
D 
E 
F 
G 
H 
A 
B 
c 
D 
E 
F 
G 
H 
1006 
SUPREME COURT REPORTS 
[2007) 8 S.C.R. 
modifications thereof and the rules made thereunder shall apply to 
such arbitrations." 
4. On 27.11.2004 a notice of demand was sent to the site of the 
respondent and it was returned with the p.ostal endorsement "refused". On 
30.6.2005 the request was reiterated. On 9.8.2005 an order was passed by the 
High Court on the application filed by the respondent. The matter was directed 
to be placed before the Chief Justice of the High Court for naming an 
arbitrator. On 19.9.2005 the High Court refused to recall its order dated 9.8.2005 
on the appellant's petition. On 26. l 0.2005, this Court in SBP & Co. v. Patel 
Engineering Ltd. & Anr., [2005] 8 SCC 618 has dealt with the nature of power 
exercised by the Chief .Justice of High Court or Chief Justice of India, as the 
case may be, under the Arbitration and Conciliation Act, 199

Excerpt shown. Read the full judgment & AI analysis in Lexace.