ASIA FOUNDATION AND CONSTRUCTION LTD. versus TRAFALGAR HOUSE CONSTRUCTION (I) LTD. AND ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
-ยท. ASIA FOUNDATION AND CONSTRUCTION LTD. A v. TRAFALGAR HOUSE CONSTRUCTION (I) LTD. AND ORS. DECEMBER 17, 1996 B [S.C. AGRAWAL AND G.B. PATTANAIK, JJ.) Judicial Review-In the area of contractual Jurisdiction-It it not within the pennissible limits of interference for a Co wt of law, in the absence of any allegation of malice or ulterior motive or finding by the court of any malafide C or favouritism in the grant of a contract. For construction of a wharf intended for mechanised handling facility of coal at Paradip Port, Asian Development Bank at Manila agreed to give loan. A prequalified notice was issued inviting offers and the pre-qualification documents received were sent to the Committee of con- D sultants for evaluation. The Consultants submitted their evaluation report recommending six firms including the appellant and the respondent No. 1 for the const1uction of the wharf. The tender committee of the Port Trust reviewed the evaluation made by the consultants and recommended all six firms. The Board of Trustees of the Paradip Port Trust approved the said E six firms and invited bids. Out of the six firms, only three submitted their bids, namely the appellants, respondent No. 2 and one Mahibba Engineer- ing (M) BHD Malaysia. The bids were sent to the consultant for evaluation report. The consultants concluded that the first respondent's bid was the lowest. Tender Committee accepted the recommendations of the consult- ants and submitted the same to Asian Development Bank for approval. F Asian Development Bank, by its communication dated 23.4.1996 intimated that they were unable to support the bid evaluation report and cannot accept the proposed bid change in quantity. The Bank came to the conclusion that the lowest evaluated substantially responsive bidder was G the appellant and recommended the contract of the construction of the . wharf be awarded to the appellant. The special tender committee formu- lated its view and communicated the same to Asian Development Bank. Bank indicated that the suggestions given were on due consideration of the practicability of mobilising finance quickly. The tender committee called H 209 ยท210 SUPREME COURT REPORTS[1996] SUPP.10 S.C.R. A the appellant for some clarifications. The project manager addressed a letter stating that in view of the additional information available there was no technical barrier or commercial disincentive to award the contract to B ยท the appellant. Even before the contract was awarded respondent No. 1 approached the High Court. After the contract was finally awarded in favour of the appellant by Board resolution, the writ petition was amended seeking the relief of quashing the award. The appellant filed their counter affidavit. The High Court took note of several clauses in the bid documents and came to the conclusion that the award of contract should be made to the C bidder whose bid has been determined to the lowest evaluated bid and who meets the appropriate standards of capability and financial responsibility. The High Court came to the conclusion that it would be in the public interest to quash the award in favour of the appellant and accordingly quashed the award. Hence this appeal. D Allowing this appeal, this Court HELD : 1.1. It is not for the court to determine whether a particular policy or particular decision taken in the fulfil~ent of that policy is fair. ltis concerned with the manner in which those decisions have been taken. E The administrative action which is subject to control by judicial review, can be classified into (1) illegality, (2) irrationality, (iii) procedural im- propriety. Principle of Judicial Review is intended to prevent arbitrariness or favoritism and in the matter of award of contract, if power had been exercised for any collateral purpose, Judicial Review is exercised in the F larger public interest. (217-G-H; 218-A-D] G 1.2. In the matter of tender, the lowest bidder may not claim any enforceable right to get the contract though ordinarily the authorities should accept the lowest bids. [218-F] 1.3. Court cannot lose sight of the fact of escalation of cost on account of delay and the time involved. In a coordinated project if one component is not worked out the entire project gets delayed and will cost enormously on that score if rebidding is done. High Court lost sight of this fact. In the facts and circumstances of this case rebidding would be gro
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex