LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

ANSAL ENGINEERING PROJECTS LTD. versus TEHRI HYDRO DEVELOPMENT CORPORATION LTD. AND ANR.

Citation: [1996] SUPP. 4 S.C.R. 226 · Decided: 31-07-1996 · Supreme Court of India · Bench: K. RAMASWAMY, S. SAGHIR AHMAD, G.B. PATTANAIK · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
c 
D 
ANSAL ENGINEERING PROJECTS LTD. 
v. 
TEHRI HYDRO DEVELOPMENT CORPORATION 
LTD. AND ANR. 
JULY 31, 1996 
fK. RAMASWAMY, S. SAGHIR AHMAD AND 
G.B. PATTANAIK, JJ.] 
Arbitration Act, 1940: 
Ss. 20. and 41 read with Schedule II-Bank guarante&-Letter of ill-
vocation-Application by contractor for injunction to restrain the respondent 
Coporation fron1 invoking the bank guarantee contending that aniount due 
and payable should be detemiined-Held bank guarantee is an independe!lt 
alld disti!lct contract between bank and beneficimy and is not qualified by the 
underlying transaction and validity of p1in1a1y contract between the 11ar-
ties-U!lless fraud or special equity is pleaded and plima facie established by 
strong evidence as a lliable issue, beneficia1y cannot be restrained froni 
encashing bank guarantee even tf a dispute hqd a1isen in pe1fonnance of 
contract or execution of lvork undertaken-In tenns of bank guarantee the 
E be!leficia1y is entitled to invoke bank guarantee and seek ellcaslunent of the 
an1ount specified in bank guarantee-Fina/ adjudication is not a pre-condi-
tion to invoke bank guarantee and that is not a ground to issue injunction 
restraining the beneficiary to enforce bank guarantee-Liability of bank is 
absolute and unequivocal; it is not concen1ed with ultbnate decision of a 
F 
G 
cowt or a tlibunal as to the amount due and payable to the beneficimy-'4ny 
paymellf by bank would be subject to the final decision by the cowt or 
llibunal-No case of fraud or special injwy is made out for imeiference by 
way of injunction-High Cowt was 1igltt in refusing injunction. 
Bank guarallfee---lnvocation of-Discussed. 
Hindustan Steel W01kers Constmction Ltd. v. G.S. Atwal & Co. (En-
gineei>) Pvt. Ltd., [1995) 6 SCC 76 and Hindustan Steel Works Constmction 
Ltd. v. Tarapore & Co. & Anr., JT (1996) 6 SC 295, relied on. 
CIVIL APPELLATE JURISDICTION: Special Leave Petition (C) 
\ 
H No. ~5878 of 1996. 
226 
j ; 
1 
ANSALENGG. PROJELlS LTD. v. TEHRI HYDRO DEV. CORPN. LTD. 227 
From the Judgment and Order dated 17.1.96 of the Delhi High Court A 
in Suit No. 990 of 1995. 
Nageswar Rao, Makarand D. Adkar, S.D. Singh and Sudhanshu 
Atreya for tho petitioner. 
The following Order of the Court was delivered : 
This Special Lea\"e Petition arises from the order of the learned 
Single Judge uf the Delhi High Court dated January 17, 1996 made in Suit 
B 
No. 990/95. The petiti01,er had sought for injunction under Section 41 read 
with Schedule II of the Arbitration Act, 1940 (for short, the 'Act') to 
restrain the respondent from invoking the bank guarantee No. 33/1991 
dated February 13, 1991 to encash Rs. 57,57,970 pursuant to the letter of 
invocation dated April 5, 1995. The facts mentioned therein are that 
petitioner had entered into contract on March 30, 1991 pursuant to a 
tender submitted by him to construct 108 residential quarters at Kalharia, 
Bhagirath Puram, Tehri. The construction was to be completed within D 
stipulated period but was not completed. In terms of the contract, the first 
respondent had terminated it. The petitioner availed of the remedy under 
Section 20 of the Act for appointment of an arbitrator for reference of the 
dispute in terms of the contract. Pending consideration thereof, he filed an 
application to restrain the respondent to encash the bank guarantee. The 
respondent after termination of the contract had issued a letter of invoca-
tion dated April 5, 1995 calling upon the UCO Bank to pay the aforesaid 
amount in terms of the bank guarantee. It was contended in the High Court 
c 
E 
. that the amount due and payable by the petitioner should be determined 
in the suit. The bank guarantee could not be invoked till then and the 
payment thereof could not be made. The respondent had played fraud on 
the petitioner in entering into the contract and seeking extension of the 
time. There are exceptional circumstances which necessitated the 
petitioner to seek relief of injunction pending determination of the amount 
due and payable by the petitioner. The High Court rejected the contentions 
and dismissed the petition. Thus, this special leave petition. 
Admittedly, the bank guarantee given by the UCO Bank on behalf 
of the petitioner reads as under : 
F 
G 
"On production of a Bank Guarantee for the above principal 
amount and interest due thereon, we, UCO Bank, 5, Parliament H 
228 
A 
B 
c 
D 
E 
F 
G 
H 
SUPREME COURT REPORTS [1996] SUPP. 4 S.C.R. 
Street, New Delhi (h

Excerpt shown. Read the full judgment & AI analysis in Lexace.