LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

ANKHIM HOLDINGS PVT. LTD. & ANR. versus ZAVERI CONSTRUCTION PVT. LTD.

Citation: [2026] 3 S.C.R. 28 · Decided: 04-02-2026 · Supreme Court of India · Bench: J.B. PARDIWALA, K.V. VISWANATHAN · Disposal: Disposed off

cites 3 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2026] 3 S.C.R. 28 : 2026 INSC 137
Ankhim Holdings Pvt. Ltd. & Anr. 
v. 
Zaveri Construction Pvt. Ltd.
(Civil Appeal No. 779 of 2026)
04 February 2026
[J.B. Pardiwala and K.V. Viswanathan, JJ.]
Issue for Consideration
Whether the High Court was justified in saying that the proceedings 
held by the Arbitral Tribunal on the seven relevant dates, i.e., from 
17.03.2022 to 25.08.2022 were liable to be declared as nullity on 
the premise that those proceedings were undertaken during the 
period of moratorium u/s.14 of the Insolvency and Bankruptcy 
Code, 2016.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.11, s.15(2), s.15(3), 
s.17 and s.37 – The appellants and respondent (now under 
liquidation) entered into a partnership firm to develop and 
construct an SRA project – Dispute arose between them – The 
High Court appointed an arbitrator to arbitrate the disputes 
and differences between the parties – The NCLT admitted 
the respondent to CIRP and imposed a moratorium u/s.14 of 
IBC – Meanwhile, various applications were filed by both the 
appellants and respondent under provisions of the Act, 1996 
before the Arbitral Tribunal and the High Court – Pursuant 
thereto, various orders were passed by the Arbitral Tribunal 
and the High Court – The High Court by its impugned judgment 
and order appointed substitute arbitrator to adjudicate the 
disputes and differences between the appellants and the 
respondent – However, the High Court proceeded to observe 
the all proceedings undertaken by the Arbitral Tribunal 
between 26.09.2019 and 26.08.2022 respectively being hit by 
the moratorium could be said to be a nullity – Correctness:
Held: Since the appointment in the case at hand was made in 
terms of the Act, 1996, the original provision applicable to the 
appointment of the arbitrator would be s.11 of the Act, 1996 – The 
position of law as regards s.11 is well settled – It affords the Court 
[2026] 3 S.C.R. 
29
Ankhim Holdings Pvt. Ltd. & Anr. v. Zaveri Construction Pvt. Ltd.
with a very limited scope essentially requiring the Court only to 
make prima facie finding that an arbitration agreement exists – 
The High Court could be said to have travelled beyond its vested 
jurisdiction including by subsuming jurisdictions expressly made 
unavailable to it including s.37 of the Act, 1996 – Having regard 
to the plain language of sub-section (2) and sub-section (4) of 
s.15 respectively, the High Court exceeded in its jurisdiction while 
taking the view that the proceedings held by the Arbitral Tribunal 
between 17.03.2022 and 25.08.2022 are a nullity because of the 
operation of moratorium – The proper and legal course for the 
High Court acting u/s.15(2) of the Act, 1996, should have been 
to appoint a substitute arbitrator to continue from the existing 
stage of the proceedings – The impugned part of the judgment 
rendered by the High Court could be said to have resulted in 
a situation where the arbitration proceedings would have to be 
restarted de novo and the same would have a direct impact on 
the sale of flats made pursuant to the s.17 orders of the Tribunal – 
This could be both inequitable and inefficient – Thus, the part 
of the impugned order by which the High Court declared the 
proceedings undertaken between 17.03.2022 and 25.08.2022 as 
a nullity deserves to be interfered with and is hereby set aside. 
[Paras 34, 35, 37, 44-46]
Case Law Cited
Interplay Between Arbitration Agreements under Arbitration and 
Conciliation Act, 1996 & Stamp Act, 1899, In re [2023] 15 SCR 
1081 : (2024) 6 SCC 1 – followed.
Yashwith Constructions Pvt. Ltd. v. Simplex Concrete Piles India 
Ltd. & Anr. [2006] Supp. 3 SCR 96 : (2006) 6 SCC 204; Official 
Trustee v. Sachindra Nath Chatterjee [1969] 3 SCR 92 : 1968 
SCC Online SC 103 – relied on.
Hindustan Construction Co. Ltd. v. Bihar Rajya Pul Nirman 
Nigam Ltd., 2025 SCC OnLine SC 2578; Shailesh Dhairyawan v.  
Mohan Balkrishna Lulla [2015] 12 SCR 70 : (2016) 3 SCC 619 – 
referred to.
List of Acts
Arbitration and Conciliation Act, 1996; Constitution of India; 
Insolvency and Bankruptcy Code, 2016.
30
[2026] 3 S.C.R.
Supreme Court Reports
List of Keywords
Home-buyers; Jurisdiction; Section 11(6) of Arbitration and 
Conciliation Act, 1996; Section 15(2) of Arbitration and Conciliation 
Act, 1996; Section 15(3) of Arbitration and Conciliation Act, 1996; 
Section 14 of Insolvency and Bankruptcy Code, 2016; Minimal 
Judicial Intervention; Self-Contained Code; Doctrine of Nullity; 
S

Excerpt shown. Read the full judgment & AI analysis in Lexace.