LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

ALL INDIA POWER ENGINEER FEDERATION & ORS. versus SASAN POWER LTD. & ORS. ETC.

Citation: [2016] 9 S.C.R. 901 · Decided: 08-12-2016 · Supreme Court of India · Bench: KURIAN JOSEPH · Disposal: Appeal(s) allowed

Cited by 8 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2016] 9 S.C.R. 901 
ALL INDIA POWER ENGINEER 
FEDERATION & ORS. 
v. 
SASAN POWER LTD. & ORS. ETC. 
(Civil Appeal Nos. 5881-5882 of2016) 
DECEMBER 08, 2016 
[KURIAN JOSEPH AND R.F. NARIMAN, JJ.] 
ELECTRICITY ACT, 2003: 
ss. 61 to 63 -
Commercial Operation Date (COD) -
Determination of- Procurement of power from generating companies 
- Sasan Power Ltd. was incorporated as a special purpose vehicle 
by Power Finance corporation the nodal agency for procuring 
power - Power Purchase Agreement (PPA) dated 7.8.2007 executed 
between Sasan Power Ltd. and procurers of generation and sale of 
electricity - Article 6 r/w Schedule 5 provided for preconditions to 
be satisfied for declaration of 'COD' namely readiness to commence 
commercial operations - This happens only when the pe1formance 
test by operating the gene1Β·ating unit at 98% of the contracted 
capacity as existing on the effective date on a continuous running 
basis for 72 hours is certified by an independent engineer by giving 
a final test certificate to the said effect - The date for commissioning 
the first unit was fixed under the PPA as 7.5.2013 - However, under 
Schedule 11 thereof. this date was preponed to 27.11.2012 - As 
Sasan kept postponing this date, the commissioning tests for 
generating Unit No.3 commenced from 20.3.2013 - Various emails 
were exchanged from 27.3.2013 to 30.3.2013 between Sasan and 
WRLDC, a statutory authority under the Act of 2003 - It was the 
case of Sasan that though they were ready to deliver electricity on 
31.3.2013 at 95% of the contracted capacity of 620 MW of the 
unit, they could not do so as WRLDC did not give them the necessary 
green signal to go ahead - They relied heavily upon the independent 
engineer's test certificate dated 30.3.2013 to show that a COD took 
place on the following day - Petition was filed by WRLDC before 
the CER Commission challenging the veracity of certificate issued 
by the independent engineer - Commission arrived at the conclusion 
that COD had not been achieved on 31.3.2013 but had only been 
901 
A 
B 
c 
D 
E 
F 
G 
H 
902 
A 
B 
c 
D 
E 
F 
G 
SUPREME COURT REPORTS 
[2016] 9 S.C.R. 
achieved tater on 16.8.2013 - Appellate Tribunal set aside the 
finding of Commission holding that though COD had not been 
achieved on 31.3.2013 in accordance with the PPA but that the 
procurers under the PPA had waived their right to demand 
performance at 95% and that the pe1formance of unit no.3 which 
was only roughly 17% of its contracted capacity was accepted by 
all the procurers and that, therefore, there was a waiver of this 
essential condition which would then entitle the generator to treat 
31.3.2013 as the-date on which commercial operation of unit no.3 
commenced - Challenged - Held: A perusal of the emails exchanged 
between the parties show that the parties did not intend to amend 
any of the provisions of the PPA - The two emails sent by the lead 
procurer to Sasan read together do not amount to waiver of the 
right mentioned in clause 6.3.1 - There is no .such clear intention 
that can be spelled out on a reading of the two emails - All that can 
be spelled out is that the first email of 31.3.2013 categorically stated 
that the test result is not as per Article 6.3.1, and is not acceptable 
- The last sentence of this very email then refers to clause 6.3.4 and 
to a de-rated capacity of 101.38 MW - Thereafter, email of 2..1.2013 
expands on the said last sentence of the earlier email by referring 
to Article 6.3.4 and Article 11 proviso - This is akin to a 'without 
prejudice' acceptance of de-rated power, being a non-acceptance 
of the test certificate dated 30.3.2013 coupled with a desperate 
attempt to somef10w get whatever power is available - But this does 
not amount to a clear and unequivocal intention to relinquish a 
known right - There is no waiver - Appellate Tribunal is wholly 
incorrect in accepting the case of waiver and is equally incorrect 
in absolving the, independent engineer for the test cer.tificate given 
by him on 30.3.2013. 
ss. 61 to 63 - Electricity tariff- Variation in - Effect on public 
interest - Held: The moment electricity tariff gets affected, the 
consumer interest comes in and public interest gets affected - Under 
s.61, the appropriate commission, when Β·it specifies terms and 
conditions for determination of tariff, is to be guided inter alia by 
the safeguarding of the consumer interest and the recovery of the 
cost of electricity in a reasonable man

Excerpt shown. Read the full judgment & AI analysis in Lexace.