LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

ALAKNANDA HYDRO POWER CO. LTD. versus ANUJ JOSHI & ORS.

Citation: [2013] 11 S.C.R. 784 · Decided: 13-08-2013 · Supreme Court of India · Bench: K.S. RADHAKRISHNAN · Disposal: Disposed off

Cited by 1 judgment(s) · cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
B 
[2013) 11 S.C.R. 784 
ALAKNANDA HYDRO POWER CO. LTD. 
v. 
ANUJ JOSHI & ORS. 
(Civil Appeal No. 6736 of 2013) 
AUGUST 13, 2013 
[K.S. RADHAKRISHNAN AND DIPAK MISRA, JJ.] 
Hydroelectric Power Project - Environmental and Forest 
clearance for - Granted to project developer - Writ petition 
C filed objecting to the clearance - High Court directing the 
Ministry of Environment and Forest to hold public hearing -
On appeal, held: The project in question is ongoing project, 
environmental clearance and forest clearance wherefor were 
granted way back in 1985 and 1987 - 95% work is already 
D over and nearly 4, 0001- crores been spent on the project -
No purpose would be achieved by way of public hearing at 
this stage - Now the safety and security of the dam and the 
people is of paramount importance - Directions issued to the 
authorities concerned and to the project developer to give 
E effect to recommendations made by the Technical experts. 
Environmental Law - Mushrooming of large number of 
hydroelectric projects in the state of Uttarakhand and its 
impact on Alaknanda and Bhagirathi river basins -
Cumulative impact of those project components on eco-
F system - Direction to Ministry of Environment and Forest to 
constitute expert body to make detailed study as to the effect 
of the projects on environmental degradation - Till then 
MoEF as well as State Government directed not to grant any 
hydroelectric power project - Disaster Management Authority 
G of the State also directed to submit its report to the Supreme 
Court as to whether they had any disaster management plan 
for combating unprecedented tragedy in the State of 
Uttarakhand. 
H 
784 
ALAKNANDA HYDRO POWER CO. LTD. v ANUJ 
785 
JOSHI 
The Srinagar Hydro Electric Project (SHEP), which 
A 
was basically run-of -the-river Scheme, was given 
Techno-Economic approval for 200 MW by Central 
Electricity Authority in 1982, subject to environmental 
clearance. After being segregated from other Ganga 
Valley Projects, a separate Environment Impact B 
Assessment (EIA) of the Project was made in 1985. A 
temple (Dhari Devi Temple) which was likely to be 
submerged in water, it was suggested in the Assessment 
that the height of the same would be raised. The Ministry 
of Environment and Forest also granted environmental c 
clearance for the Project. Later the capacity of the Project 
was enhanced to 330 MW in 1987, which was duly 
approved and Planning Commission also accorded 
investment approval. However, effective progress was 
not made in the Project due to paucity of funds. 
Β·Pursuant to liberalisation policy, the State invited 
private investment in the Project and MOU was entered 
into with a private company. The State GovernJTient 
requested Ministry of Environment and Forest to transfer 
D 
the environmental clearance to the private company and 
E 
the clearance was transferred for 330 MW in the year 
1999. Techno-Economic clearance for implementation of 
the project was also issued to the private company. The 
Project, therefore, was transferred to the appellant-
company and environmental clearance was transferred 
F 
in its favour in the year 2006. 
Respondent No.1 filed writ petition challenging the 
decision as to environmental clearance for the increased 
capacity of generation i.e. 330 MW. Ministry of G 
Environment and Forest by its letter dated 3.8.2011 
clarified that transfer in favour of the appellant-Company 
was for 330 MW. High Court disposed of the petition 
directing the appellant-Company to place the document 
before Ministry of Environment and Forest and further 
H 
786 
SUPREME COURT REPORTS 
[2013) 11 S.C.R. 
A directed the Ministry to hold public hearing. Hence, the 
present appeals. 
Certain litigation had also been initiated before 
National Green Tribunal on the issue. The proceedings 
8 before the Tribunal have also been transferred to this 
Court. 
Disposing of the appeal and transferred cases, the 
Court 
c 
HELD: 1.1. Srinagar Hydro Electric Project is an 
ongoing project for which environmental clearance was 
granted as early as in the year 1985 and forest clearance 
in the year 1987. Further, about 95 % of the work is 
already over and nearly Rs.4,()00 crores has been spent. 
o If public hearing is found necessary then the same 
should have been held before granting environmental 
clearance. The purpose of public hearing is to know the 
concerns of the affected people and to incorporate their 
concerns 
appropriately 
into 

Excerpt shown. Read the full judgment & AI analysis in Lexace.