LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

A.P. POWER COORDINATION COMMITTEE & ORS. versus MIS. LANCO KONDAPALLI POWER LTD. & ORS.

Citation: [2015] 12 S.C.R. 447 · Decided: 16-10-2015 · Supreme Court of India · Bench: VIKRAMAJIT SEN · Disposal: Dismissed

Cited by 4 judgment(s) · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2015] 12 S.C.R. 447 
A.P. POWER COORDINATION COMMITTEE & ORS. 
A 
v. 
MIS. LANCO KONDAPALLI POWER LTD. & ORS. 
(Civil Appeal No. 6036 of 2012) 
OCTOBER 16, 2015 
[VIKRAMAJIT SEN AND SHIVA KIRTI SINGH, JJ.] 
B 
Electricity Act, 2003 - s. 86(1 )(f), 17 4 - Limitation Act, 
1963 - ss. 3, 14, Schedule - Disputes between /icencees c 
and power generating company- Bill for capacity charges-
Claim for reimbursement of minimum alternate Tax (MAT) -
Whether the Limitation Act, s. 3 and the Schedule would 
apply to any action instituted before the Commission uls. 
86(1)(f) - Whether the impugned order passed by APTEL D 
permitting application of principles emerging from s. 14, is 
against law - Whether the claim for reimbursement of MAT 
is in contravention of relevant terms and conditions of the 
Power Purchase Agreement (PPA) - Held: A claim coming 
before the Commission cannot be entertained or allowed if it E 
is barred by limitation prescribed for an ordinary suit before 
the civil court - However, in appropriate case, a specified 
period may be excluded on account of principle underlying 
salutary provisions like s. 5 or 14 - Further, such limitation 
upon the Commission would be only in respect of its judicial F 
power uls. 86(1 )(f) and not in respect of its other powers or 
functions which may be administrative or regulatory - As 
regards order passed by APTEL, in law, the APTEL could 
grant exclusion of certain period on the basis of principles ul G 
s. 14 - On facts, AP TEL adopted a just and lawful approach 
in examining the relevant facts and in excluding the entire. 
period claimed by respondent which starts from the notice 
for arbitration dated 8.9.2003 given by the respondent, till 
the application of the respondent u/s. 11 of the Arbitration H 
448 
SUPREME COURT REPORTS 
[2015] 12 S.C.R. 
A Act before the High Court was finally disposed of on 
18. 3. 2009 - Challenge to impugned order in respect of views 
taken on the issue of limitation in the light of principles of s. 
14 fails - As regards the claim for reimbursement, entire 
phraseology used in Article 3.8 of the PPA clarifies that 
B parties were aware that tax regime keeps changing and 
therefore any advance income tax payable for the income 
from the project only had to be reimbursed by the Board -
As a successor of the Board the appeliant cannot avoid the 
liability to reimburse advance income tax paid by_ the 
C respondent, on the ground that MAT was a new variety of tax 
concept introduced subsequently in which minimum tax 
became payable on the basis of mere book profits of even 
power generating companies - It cannot be said that such, 
0 
tax is not on income from the project and thus, not covered 
by Article 3.8- Taxable income became amenable to MAT 
on account of s. 115JB - Claim for MAT covered by Article 
3. 8 and payable as such when requisite conditions stand 
E 
~~~d 
. 
Dismissing the appeals, the Court 
HELD: 1.1 There is no possibility of any difference 
of opinion in accepting that on account of judgment of 
this Court in Gujarat Urja the Commission has been 
F elevated to the status of a substitute for the Civil Court 
in respect of all disputes between the licencees and 
generating companies. Such dispute need not arise from 
the exercise of powers under the Electricity Act. Even 
claims or disputes arising purely out of contract like in 
G the instant case have to be either adjudicated by the 
Commission or the Commission itself has the discretion 
to refer the dispute for arbitration after exercising its 
power to nominate the arbitrator. A statutory authority 
H like the Commission is also required to determine or 
A.P. POWER COORDINATION COMMITTEE v. LANCO 
449 
KONDAPALLI POWER LTD. 
decide a claim or dispute either by itself or by referring it A 
to arbitration only in accordance with law and thus 
Section 174 and 175 of the Electricity Act assume 
relevance. Since no separate limitation has been 
prescribed for exercise of power under Section 86(1)f) 
nor this adjudicatory power of the Commission has been B 
enlarged to entertain even the time barred claims, there 
is no conflict between the provisions of the Electricity 
Act and Limitation Act to attract the provisions of Section 
17 4 of the Electricity Act. In such a situation on account 
of provisions in Section 175 of the Act or even otherwise C 
the power of adjudication and determination or even the 
power of deciding whether a case requires reference to 
arbitration

Excerpt shown. Read the full judgment & AI analysis in Lexace.